  1. 1. THE NEXT FIFTY YEARS Restoration Update and Review July 24, 2016
  2. 2. SCOPE OF WORK  Roof  Masonry  Pointing  Eavestrough  Stained glass windows  Storm windows
  3. 3. UPDATE  On budget  On schedule
  4. 4. KEY OUTCOMES TO DATE  Roof – dry and no unanticipated repairs  Shingles and copper flashing and venting complete  New lightening rod system installed  New warming coils installed  Mortar and pointing work progressing  Window frames stripped on north side  Initial storm cleaning and venting going well  Grafton window progressing
  5. 5. UPCOMING  Shifting scaffolding from the exterior to the interior  Shifting entrances to the church
  6. 6. EVOLVING ISSUES  Listing Wall  Lighting  Stucco work and painting  Park Street Stairs  Stone fence  Landscaping
  7. 7.  Project based discussion  Benefits of timing  Projected costs  Motion for consideration  Next steps
  8. 8. LISTING WALL  Rod, plate and crank solution  No option
  9. 9. LIGHTING  Long discussed at Worship committee  Plans inclusive of the Sanctuary, Chancel and aisles  Require scaffold to complete electrical
  10. 10. PAINTING AND STUCCO  Discussed previously  Initially intended for post restoration decision  Requires scaffolding
  11. 11. PARK STREET STEPS  New matter  Deterioration evident  Plan to include stairs, platforms and rails
  12. 12. OTHER  Stone fence  Landscaping
  13. 13. BENEFITS  Trades onsite  Scaffold and lifts available as needed  Liability insurance in place  Project management available where needed  One period of disruption not multiple  Completion equals easier long term maintenance
  14. 14. ESTIMATED COSTS (HST excluded)  Lights and Electrical $132000  Listing wall $28000  Interior stucco work and painting $312000  Stairs $110000  Stone fence $20000  Landscaping $60000  Management fees
  15. 15. MOTION  The congregation approve the allocation of a maximum of $800,000 for the completion of additional interior and exterior projects related to the Next Fifty years project from the Jackson Magee estate.
  16. 16. QUESTIONS/COMMENTS

×