  1. 1. Euclid Creek Tunnel Community Update December 18, 2012 euclidcreek.blogspot.com
  2. 2. The Communications Team• Jim Bunsey Deputy Director of Engineering & Construction• Doug Gabriel Program Manager, Euclid Creek Tunnel• Ryan Sullivan Senior Construction Supervisor• Bob Auber Construction Manager• Jenn Elting Public Information Specialist euclidcreek.blogspot.com
  3. 3. Current Communications• Contractor Communications – Hard-copy letters – McNally/Kiewit• Euclid Creek Newsletter – Quarterly• Construction Hotline – (216) 432-7157 – Multiple Sewer District projects• E-mails from Doug Gabriel euclidcreek.blogspot.com
  4. 4. Current Communications• Euclid Creek Blog (euclidcreek.blogspot.com) – Construction updates (Ryan) & articles of interest (Jenn)• E-mail Newsletter – Twice-monthly (Jenn)• Collinwood Observer – More Sewer District articles & Euclid Creek Tunnel updates• Regular Meetings – Third Tuesday of each month: 6 p.m. euclidcreek.blogspot.com
  5. 5. Project Overview euclidcreek.blogspot.com
  6. 6. Construction Updates• East 156th Street utility relocation – Work completed last week• New sewer, Lakeshore Boulevard East 150th Street to (east of) Collinwood Rec. – Work complete: Sept 2013• New sewer, St. Clair Ave. and Nottingham Rd. – Work completed: Oct 2013 euclidcreek.blogspot.com
  7. 7. Shaft #1 Construction Staging Site• “Mackenzie” tunneled and lined 2800’• Operating 24/7 with regularly-scheduled maintenance periods euclidcreek.blogspot.com
  8. 8. Shaft #2 Easterly Wastewater Treatment Plant• 60 feet excavated• Add’l 40 feet before bedrock – Blasting last 100 feet – Will not begin until 2013 euclidcreek.blogspot.com
  9. 9. Shaft #3 Beulah Park• Construction staging area – Crews to site week of November 5 – Secant pile wall • Contractors mobilize week of December 17 • Monday through Saturday – Other activities • 100 ton crane arrived today • Add’l large equipment arriving on site later this week euclidcreek.blogspot.com
  10. 10. Shaft #3 Beulah ParkWithin construction site looking north. euclidcreek.blogspot.com
  11. 11. Shaft #3 Beulah Park: SafetyConstruction Entrance to be 4-Way Stop euclidcreek.blogspot.com
  12. 12. Shaft #4 Triangle Park• Excavation work is complete at this site• Currently installing rebar to reinforce shaft• Fencing will remain throughout 2014 euclidcreek.blogspot.com
  13. 13. Shaft #4 Triangle Park• Work is complete at this site• Fencing will remain throughout 2014 euclidcreek.blogspot.com
  14. 14. Shaft #5 Nottingham & St. Clair• Excavation nearing completion – 175 feet excavated – 25 more to go euclidcreek.blogspot.com
  15. 15. Shaft #5 Nottingham & St. Clair• 175 feet excavated, 25 more to go• No blasting at this site euclidcreek.blogspot.com
  16. 16. euclidcreek.blogspot.com
  17. 17. Upcoming Construction Impacts• AT&T UG Relocation at 3-5 (E 156th and Lakeshore) – work to begin Late Dec• Structure 3-2 – excavation to begin late January• Structure 5-4 – solider pile installation and excavation to begin mid January euclidcreek.blogspot.com
  18. 18. Next Meeting• Tuesday, January 15, 2013 6:00 p.m. Cleveland Public Library, Memorial-Nottingham Branch• Save the Date! – February 19 – March 19 – April 16 euclidcreek.blogspot.com

×