Case study - Stoke Newington School: Assessing new build vs. refurbishment value options

Published in: Education
  • Be the first to comment

  • Be the first to like this

Jude Harris & Jill Cameron

  1. 1. Case Study: Assessing New Build v Refurbishment Jude Harris, Associate Director Jestico + Whiles Jill Cameron, Director of Resourcing (BSF Lead) Stoke Newington School Remodelling Education Spaces | Stoke Newington School
  2. 2. London Borough of Hackney Remodelling Education Spaces | Stoke Newington School
  3. 3. Aerial View of Site Remodelling Education Spaces | Stoke Newington School
  4. 4. The Existing School (2006) Remodelling Education Spaces | Stoke Newington School
  5. 5. Original Drawings (1967) Remodelling Education Spaces | Stoke Newington School
  6. 6. The Existing School (2006) Remodelling Education Spaces | Stoke Newington School
  7. 7. Education Vision and Priorities Remodelling Education Spaces | Stoke Newington School
  8. 8. Existing School (11,784m²) Remodelling Education Spaces | Stoke Newington School
  9. 9. New Build Proposals | Reference Scheme Remodelling Education Spaces | Stoke Newington School
  10. 10. New Build Proposals Remodelling Education Spaces | Stoke Newington School
  11. 11. New Build Proposals Remodelling Education Spaces | Stoke Newington School
  12. 12. New Build Proposals (13,618m²) Remodelling Education Spaces | Stoke Newington School
  13. 13. Aerial Perspective | As Existing Remodelling Education Spaces | Stoke Newington School
  14. 14. Aerial Perspective | As Proposed Remodelling Education Spaces | Stoke Newington School
  15. 15. Construction Phase 1 Remodelling Education Spaces | Stoke Newington School
  16. 16. Construction Phase 2 Remodelling Education Spaces | Stoke Newington School
  17. 17. Temporary Accommodation Remodelling Education Spaces | Stoke Newington School
  18. 18. Street Elevation (Clissold Road) Remodelling Education Spaces | Stoke Newington School
  19. 19. The ‘Street’ Remodelling Education Spaces | Stoke Newington School
  20. 20. The ‘Street’ Remodelling Education Spaces | Stoke Newington School
  21. 21. The ‘Street’ Remodelling Education Spaces | Stoke Newington School
  22. 22. Dining Hall Remodelling Education Spaces | Stoke Newington School
  23. 23. New Build v Refurbishment | Ground Floor 14% 40% 31% 15% Remodelling Education Spaces | Stoke Newington School
  24. 24. New Build v Refurbishment | First Floor 14% 40% 31% 15% Remodelling Education Spaces | Stoke Newington School
  25. 25. New Build v Refurbishment | Second Floor 14% 40% 31% 15% Remodelling Education Spaces | Stoke Newington School
  26. 26. SEN School and Housing on the Site Remodelling Education Spaces | Stoke Newington School
  27. 27. Landscaping Strategy Remodelling Education Spaces | Stoke Newington School
  28. 28. New Welcome Plaza Remodelling Education Spaces | Stoke Newington School
  29. 29. Wayfinding Remodelling Education Spaces | Stoke Newington School
  30. 30. Wayfinding | Ground Floor Remodelling Education Spaces | Stoke Newington School
  31. 31. Wayfinding | First Floor Remodelling Education Spaces | Stoke Newington School
  32. 32. Wayfinding | Second Floor Remodelling Education Spaces | Stoke Newington School
  33. 33. Wayfinding Remodelling Education Spaces | Stoke Newington School
  34. 34. Sustainability Remodelling Education Spaces | Stoke Newington School
  35. 35. Sustainability Remodelling Education Spaces | Stoke Newington School
  36. 36. New Build v Refurbishment | Costs Stoke Newington School £20m 13,618m² £1,468/m² 1500 pupils £13,333 per pupil The Hackney City Academy £30m 10,357m² £2,896/m² 1140 pupils £26,315 per pupil Remodelling Education Spaces | Stoke Newington School

×