CMGC Contracting at UDOT

  1. 1. CMGC Contracting at UDOT Carlos Braceras, P.E. Deputy Director
  2. 2. Why CMGC? • Deliver the Best Value Project • Owner Makes Informed Decisions • Exceed Public Expectations • Optimize Innovations • Risk Assessment & Management
  3. 3. UDOT Committed Funds by Delivery Methodby Year of Advertisement Date ($ in Millions) $1.85B $800 9 $700 8 $600 223 $500 71 5 DBB 12 6 100 DB $400 128 106 136 CMGC $300 $200 $100 9 3 6 4 3 11 3 $0 2006 2007 2008 2009 2010 2011
  4. 4. UDOT Development of CMGC CMAR Concept CMGC Concept Owner Owner Contract Manager Designer ContractorAt-Risk Subs Designer Specialty Sub Specialty SubContractor
  5. 5. CMGC Team Approach• Partnering• Build Trust CMGC Team• Project Challenges All Identified Contractor UDOT Designer• Contractor Bids Actual Line Items
  6. 6. Fair Price Strategy • Engineer’s Estimate Typically based on State Averages • Contractor’s Estimate Prepared for specific project bid items Typically based on production rates and unit price • Independent Cost Estimate (ICE) Cost Validation Reflects Current Market Conditions
  7. 7. MVC Project Overview• Salt Lake County (2010 to 2013) CMGC 15 mile segment Two lanes in each direction• Utah County (2010 to 2011) Low bid 3 mile segment Two lanes in each direction
  8. 8. Phased Approach
  9. 9. Phased Approach
  10. 10. Phased Approach
  11. 11. Preconstruction Phase
  12. 12. Results – Reduced Construction Cost100% 90% $276 $287 $350 $403 80% 70% 60% 50% $249 $259 $307 $346 OPCC1 40% OPCC2A 30% OPCC3 20% OPCC4 10% $228 $232 $269 $285 0% $200 $225 $250 $275 $300 $325 $350 $375 $400 $425 $450
  13. 13. Benefits of CMGC • Deliver the Best Transportation Project at the Best Value • Owner Makes Informed Decisions • Optimize Innovations • Risks Managed Throughout Project Delivery
  14. 14. Reference Materials & Questions UDOT Annual CMGC Reports, and other related documents available online at udot.utah.gov
  15. 15. CMGC Contracting at UDOT Carlos Braceras, P.E. Deputy Director

×