RG Mobility Rollout

  1. 1. Reference Group Meeting Mobility Rollout Approach 26 June 2008
  2. 2. <ul><li>Presentation Objectives </li></ul><ul><li>Overview of how Mobile phones will be cutover to Optus </li></ul><ul><ul><li>Process and engagement aspects </li></ul></ul><ul><li>Reference Group feedback on proposed approach </li></ul><ul><li>Group members know what’s coming </li></ul>
  3. 3. Current Status <ul><li>Optus contract progressing </li></ul><ul><li>Phone range, provisioning and support processes ready </li></ul><ul><li>Supporting website content ready </li></ul><ul><ul><li>Release after contract signed </li></ul></ul><ul><li>Mobility rollout process drafted </li></ul><ul><ul><li>Basis of this presentation </li></ul></ul>
  4. 4. Rollout entails two phases <ul><li>Phase one </li></ul><ul><ul><li>Pilot small group of IS users </li></ul></ul><ul><ul><li>Transition centrally-managed users </li></ul></ul><ul><ul><li>Refine processes in readiness for phase 2 </li></ul></ul><ul><li>Phase two </li></ul><ul><ul><li>Transition remaining faculties and professional dept’s </li></ul></ul>
  5. 5. Rollout Roadmap <ul><li>Pilot IS users and refine processes </li></ul><ul><li>Conduct information forum </li></ul><ul><li>Commence cutover of centrally managed users </li></ul><ul><li>Utilise site contact to also kick off faculties for phase two </li></ul><ul><li>Apply deployment process to progressively work through the University </li></ul>
  6. 6. Mobility Transition Roadmap 18 19 14 16 17 20 21 22 23 24 15 25 13 12 11 10 9 8 7 6 5 4 3 2 1 NEW SERVICES AND PROVISIONING SECOND LEVEL FAULT RESOLUTION Week Number Version 0.4 Pilot Information Forum 0 Transition Faculties (one per week) Phase 1 Phase 2 Faculties and Professional Departments kick off meetings Transition Centrally Managed Accounts Transition Professional Departments
  7. 7. First phase approach <ul><li>Limited number of known users with known devices </li></ul><ul><li>Active and targeted communications to build awareness and readiness for deployment </li></ul><ul><li>Carefully scheduled communications leading to cutover </li></ul><ul><li>Solicit feedback to adjust deployment and communication processes </li></ul>
  8. 8. Second phase approach <ul><li>Starts with key contacts information forum </li></ul><ul><ul><li>Project overview </li></ul></ul><ul><ul><li>Service delivery, billing, transition , phone selection, etc. </li></ul></ul><ul><ul><li>Promote active involvement and understanding the rollout process </li></ul></ul><ul><li>Kick-offs with management and IT contact </li></ul><ul><ul><li>Foster collaborative approach </li></ul></ul><ul><ul><li>Review rollout process </li></ul></ul><ul><ul><li>Build commitment toward site participation </li></ul></ul><ul><li>Provide sequenced, site-specific coms </li></ul><ul><ul><li>About the project, what changes, why, when, who will do what, what users need to do etc. </li></ul></ul><ul><ul><li>Newsletter inserts, staff memos and email releases </li></ul></ul>
  9. 9. Second phase approach continued <ul><li>LITE populate user info spreadsheet </li></ul><ul><li>Project and LITE set deployment schedule </li></ul><ul><li>Deployment staff (including Optus staff) see one user at a time </li></ul><ul><ul><li>deploy to Optus and provide user support </li></ul></ul><ul><li>Formal Project closure approximately one week after the last user is cutover </li></ul><ul><li>LITEs will be enabled to cutover remaining/new users </li></ul>
  10. 10. Rollout principles <ul><li>Re-apply the ‘eXchange approach’ </li></ul><ul><li>Deployment techs on site for one week only </li></ul><ul><li>Local preparation will achieve fast/smooth cutover </li></ul><ul><ul><li>Inadequate preparation will result in fewer/more problematic deployments </li></ul></ul><ul><ul><li>Remaining deployments will be for LITEs to complete </li></ul></ul><ul><li>High emphasis on coordination by the Project office – </li></ul><ul><ul><li>Kick offs, communications and deployments tightly scheduled </li></ul></ul>
  11. 11. <ul><li>Feedback - Questions? </li></ul><ul><li>Thank you </li></ul>

×