What is the best way to measure progress on an Agile project?

  1. What is the best way to measure progress on an Agile project?
  2. 100 75 The Ubiquitous Burndown? 50 25 0 June 6 June 7 June 8 June 9 June 10 June 13 June 14 June 15 June 16 June 17
  3. What is wrong with this? The Ubiquitous Burndown? 100 75 50 25 0 June 7 June 9 June 13 June 15 June 17
  4. What is wrong with this? 1. Unclear Information
  5. 100 What Remaining Task Hours 75 65 50 is wrong with this? 25 1. Unclear Information 0 June 6 June 7 June 8 June 9 June 10 June 13 June 14 June 15 June 16 June 17 What does this burndown tell you?
  6. 100 What Remaining Task Hours 75 65 50 is wrong with this? 25 1. Unclear Information 0 June 6 June 7 June 8 June 9 June 10 June 13 June 14 June 15 June 16 June 17 What does this burndown tell you? Here we are on June 10th with 65 task hours remaining.
  7. What 65 hours could equal... 1. Unclear Information Status Total Hours Hours Remaining = 65 10 Not Done 20 13 11 Not Done 20 13 12 Not Done 20 13 13 Not Done 20 13 14 is wrong with this? Story # Not Done 20 13 OR Story # Status Total Hours Hours Remaining = 65 10 11 12 13 14 Done Done Done Not Done Not Done 15 10 10 35 30 0 0 0 35 30 And quite a few other scenarios....
  8. What is wrong with this? 2. No visibility of scope
  9. What is wrong with this? 2. No visibility of scope And scope creep
  10. What is wrong with this? 3. Inaccuracies
  11. What is wrong with this? 3. Inaccuracies A burndown holds accurate data if: Every team member remembers to accurately estimate the hours remaining on all their tasks every single day, and enter it into the system every single day.
  12. What is wrong with this? 4. Wasteful
  13. What is wrong with this? 4. Wasteful A lot of effort spent making frequent estimates and updates
  14. What is wrong with this? 4. Wasteful For a report that has: 1. Unclear information 2. No visibility of scope 3. Inaccuracies
  15. What A lot of overhead is wrong with this? 4. Wasteful for little benefit
  16. What do we recommend instead?
  17. What do we recommend instead? Always measure business value
  18. What do we recommend instead? Always measure what the customer wants
  19. What Always measure what the customer wants do we recommend instead? Not hours
  20. How?
  21. How Measure Story Completion
  22. What does this report tell you? How 100% Measure Story Completion 75% 50% 25% 0% Set Location Show Set Email Location Preferences Save Search Edit Search Delete Search
  23. What does this report tell you? How How much is done 100% Measure Story Completion 75% 50% 25% 0% Set Location Show Set Email Location Preferences Save Search Edit Search Delete Search
  24. What does this report tell you? How How much is done What’s done 100% Measure Story Completion 75% 50% 25% 0% Set Location Show Set Email Location Preferences Save Search Edit Search Delete Search
  25. What does this report tell you? How How much is done What’s done What’s not done 100% Measure Story Completion 75% 50% 25% 0% Set Location Show Set Email Location Preferences Save Search Edit Search Delete Search
  26. How Burnup to a fixed date
  27. What does this report tell you? How Burnup to a fixed date
  28. What does this report tell you? How Burnup to a fixed date Changes in scope.
  29. What does this report tell you? How Burnup to a fixed date Changes in scope. What’s done and how we’re progressing.
  30. What does this report tell you? How Burnup to a fixed date Changes in scope. What’s done and how we’re progressing. Story count deficit on timeline.
  31. What does this report tell you? How Burnup to a fixed date Changes in scope. What’s done and how we’re progressing. Story count deficit on timeline. Forecast completion based on previous velocity.
  32. How do you track progress on your project?
  33. Agile workers talk often and welcome change. Mingle creates a shared space to make quick decisions and track details, even when the team can’t be together. See how Mingle can help you effectively track the progress of your project or program