Whatis the best way to measureprogress on an Agile project?
100 75 50            The Ubiquitous Burndown? 25  0      June 6   June 7   June 8   June 9   June 10   June 13   June 14  ...
What                            The Ubiquitous Burndown?                      100                       75                ...
Whatis wrong with this?1. Unclear Information
100                                                                               Remaining Task HoursWhat                ...
100                                                                               Remaining Task HoursWhat                ...
65 hours could equal...What                          Story #    Status    Total Hours   Hours Remaining = 65              ...
Whatis wrong with this?2. No visibility of scope
And scope creepWhat is wrong with this?2. No visibility of scope
Whatis wrong with this?3. Inaccuracies
What is wrong with this?                       A burndown holds accurate data if:                             Every team m...
Whatis wrong with this?4. Wasteful
lot of effort spent makingWhatis wrong with this?                      A                      frequent estimates and update...
What                  For a report that has:is wrong with this?                         1. Unclear information4. Wasteful ...
A lot of overheadWhatis wrong with this?4. Wasteful                        for little benefit
Whatdo we recommend instead?
Always measure business valueWhatdo we recommend instead?
Always measure what the customer wantsWhatdo we recommend instead?
Always measure what the customer wantsWhatdo we recommend instead?                                     Not hours
How?
HowMeasure Story Completion
What does this report tell you?How                        100%Measure Story Completion    75%                            5...
What does this report tell you?                           How much is doneHow                        100%Measure Story Com...
What does this report tell you?                           How much is doneHow                           What’s done       ...
What does this report tell you?                           How much is doneHow                           What’s done       ...
HowBurnup to a fixed date
What does this report tell you?HowBurnup to a fixed date
What does this report tell you?                         Changes in scope.HowBurnup to a fixed date
What does this report tell you?                         Changes in scope.How                         What’s done and how w...
What does this report tell you?                         Changes in scope.How                         What’s done and how w...
What does this report tell you?                         Changes in scope.How                         What’s done and how w...
Howdo you track progress on your project?
Agile workers talk often and welcome change. Mingle creates a shared space tomake quick decisions and track details, even ...
Upcoming SlideShare
Loading in …5
×

What is the best way to measure progress on an Agile project?

10,364 views

Published on

What is the best way to measure progress on an Agile project?

  1. 1. Whatis the best way to measureprogress on an Agile project?
  2. 2. 100 75 50 The Ubiquitous Burndown? 25 0 June 6 June 7 June 8 June 9 June 10 June 13 June 14 June 15 June 16 June 17
  3. 3. What The Ubiquitous Burndown? 100 75 50 25is wrong with this? 0 June 7 June 9 June 13 June 15 June 17
  4. 4. Whatis wrong with this?1. Unclear Information
  5. 5. 100 Remaining Task HoursWhat 65 75 50 is wrong with this? 251. Unclear Information 0 June 6 June 7 June 8 June 9 June 10 June 13 June 14 June 15 June 16 June 17 What does this burndown tell you?
  6. 6. 100 Remaining Task HoursWhat 65 75 50 is wrong with this? 251. Unclear Information 0 June 6 June 7 June 8 June 9 June 10 June 13 June 14 June 15 June 16 June 17 What does this burndown tell you? Here we are on June 10th with 65 task hours remaining.
  7. 7. 65 hours could equal...What Story # Status Total Hours Hours Remaining = 65 10 Not Done 20 13 11 Not Done 20 13 12 Not Done 20 13 is wrong with this? 13 Not Done 20 13 14 Not Done 20 131. Unclear Information OR Story # Status Total Hours Hours Remaining = 65 10 Done 15 0 11 Done 10 0 12 Done 10 0 13 Not Done 35 35 14 Not Done 30 30 And quite a few other scenarios....
  8. 8. Whatis wrong with this?2. No visibility of scope
  9. 9. And scope creepWhat is wrong with this?2. No visibility of scope
  10. 10. Whatis wrong with this?3. Inaccuracies
  11. 11. What is wrong with this? A burndown holds accurate data if: Every team member remembers to accurately estimate the hours remaining on3. Inaccuracies all their tasks every single day, and enter it into the system every single day.
  12. 12. Whatis wrong with this?4. Wasteful
  13. 13. lot of effort spent makingWhatis wrong with this? A frequent estimates and updates4. Wasteful
  14. 14. What For a report that has:is wrong with this? 1. Unclear information4. Wasteful 2. No visibility of scope 3. Inaccuracies
  15. 15. A lot of overheadWhatis wrong with this?4. Wasteful for little benefit
  16. 16. Whatdo we recommend instead?
  17. 17. Always measure business valueWhatdo we recommend instead?
  18. 18. Always measure what the customer wantsWhatdo we recommend instead?
  19. 19. Always measure what the customer wantsWhatdo we recommend instead? Not hours
  20. 20. How?
  21. 21. HowMeasure Story Completion
  22. 22. What does this report tell you?How 100%Measure Story Completion 75% 50% 25% 0% Set Show Set Email Save Edit Delete Location Location Preferences Search Search Search
  23. 23. What does this report tell you? How much is doneHow 100%Measure Story Completion 75% 50% 25% 0% Set Show Set Email Save Edit Delete Location Location Preferences Search Search Search
  24. 24. What does this report tell you? How much is doneHow What’s done 100%Measure Story Completion 75% 50% 25% 0% Set Show Set Email Save Edit Delete Location Location Preferences Search Search Search
  25. 25. What does this report tell you? How much is doneHow What’s done What’s not done 100%Measure Story Completion 75% 50% 25% 0% Set Show Set Email Save Edit Delete Location Location Preferences Search Search Search
  26. 26. HowBurnup to a fixed date
  27. 27. What does this report tell you?HowBurnup to a fixed date
  28. 28. What does this report tell you? Changes in scope.HowBurnup to a fixed date
  29. 29. What does this report tell you? Changes in scope.How What’s done and how we’re progressing.Burnup to a fixed date
  30. 30. What does this report tell you? Changes in scope.How What’s done and how we’re progressing. Story count deficit on timeline.Burnup to a fixed date
  31. 31. What does this report tell you? Changes in scope.How What’s done and how we’re progressing. Story count deficit on timeline. Forecast completion based on previous velocity.Burnup to a fixed date
  32. 32. Howdo you track progress on your project?
  33. 33. Agile workers talk often and welcome change. Mingle creates a shared space tomake quick decisions and track details, even when the team can’t be together. See how Mingle can help you effectively track the progress of your project or program

×