INDUSTRY
Automotive
DEPARTMENT
Precision Engineering
SOLUTION
Microsoft Project Server
TPG PSLink
TPG ProjectLink
Integrated Project Management Solution:Even
complex projects on time and on budget
SMALL THINGS SET LARGE ONES IN MOTION
Precision engineering company Alfmeier Präzision SE
refers to the tiny components it makes with the inspir-
ing phrase: “Small things set large ones in motion”.
Starting with small steps, a change of system supporting
its project management organization has also moved
the company forward, making it more efficient and
competitive.
A key component of the enterprise project manage-
ment solution is the bidirectional data synchronization
between SAP and Microsoft Project, making cost and re-
source planning simpler and more accurate.
Alfmeier Präzision SE is a global high-tech company serv-
ing the automotive and other industries. With about 2000
employees worldwide, it is a recognized specialist in plastic
injection molding and fluid systems as well as electronics,
mechatronics and car seat solutions.
The Fluid Systems business unit develops intelligent solu-
tions for applications such as fuel supply, servo assistance,
flap control, crank case ventilation as well as thermal man-
agement. The Seat Comfort division focuses on a range of
advanced solutions for car seats that adapt to the anatomy
of the vehicle’s occupants.
The company is headquartered in Treuchtlingen (Germany)
and has subsidiaries in the USA, Mexico, Czech Republic,
China and Korea.
Case Study
PATCHWORK OF DIFFERENT TOOLS
With the implementation of SAP PS and other tools for
project planning, the precision engineering company end-
ed up using a plethora of different systems. Each project
manager had their own preference. So if management
wanted to know how a specific project – or even the over-
all project cost – was progressing, they had to ask each
project manager individually.
This was a particularly complex undertaking in Alfmeier’s
case as the company operates in multiple different coun-
tries. Project managers would request and create projects
in SAP PS, while documents produced by the teams dur-
ing the course of the project work were in other formats,
such as Word and Excel – particularly for cost estimates,
proposal approvals and change requests.
The staff entered their timesheet information in SAP and
managers produced reports in Excel, PowerPoint, Access
and Word as well as APIS and QlikView.
This made it challenging to consolidate all the infor-
mation as a basis for planning and decision-making. As
each project manager was using his or her preferred
planning and scheduling tool, there was no quick way
to review the teams’ schedules and ensure optimal
staff resource utilization.
CENTRALIZE AND STREAMLINE
PROJECT PLANNING
Erich Taube, Head of Project Management Office (PMO)
at Alfmeier Präzision SE, headed up a team tasked with
finding a suitable solution for streamlining and stand-
ardizing project planning processes.
“With our fairly intensive use of Microsoft Office prod-
ucts, we thought Microsoft Project Server would be the
best fit, so we set about looking for potential partners,”
says Erich Taube.
Meeting specialists from TPG The Project Group, Erich
Taube and his team were impressed by their experi-
ence and their quick grasp of the project management
situation at Alfmeier. The team drew up a matrix com-
paring the offerings of the various providers, and TPG
came out clearly on top.
“But what really clinched it for TPG was their TPG
PSLink product for bidirectional data synchronization
between SAP and Microsoft Project Server, along with
their ability to customize Microsoft Project Server to
our needs,” adds Taube.
CUSTOMIZED FUNCTIONALITY
The first step was for everyone involved to get round a ta-
ble and define the project’s specifications and goals. This
was followed by the implementation of a test system to
run alongside the production system on both the Micro-
soft Project and SAP sides.
The two teams worked together to implement over 100
user-defined fields in Microsoft Project, mainly SAP-relat-
ed. Alfmeier staff ran a sample project through the sys-
tems to test both sides, including the planning process as
well as schedules and costs.
TPG was then tasked with developing a custom function
for Alfmeier’s project managers. “We wanted a profit-
ability indicator, updated in real time, to enable project
managers to see at a glance how profitable their projects
were,” comments Erich Taube.
That way, project staff could work with their familiar tool
without needing any expertise in the use of SAP. TPG de-
veloped the custom feature and implemented it together
with the rest of the system.
On the Alfmeier side, Erich Taube and his team facilitated
user acceptance by organizing multiple training courses.
They also designated individuals in the PMO who could in-
tervene immediately in case of any problems in the field.
In addition, the team supports several power users in the
local offices who are able to help their colleagues quickly
when queries arise.
„What really clinched it for TPG was their
TPG PSLink product for bidirectional data
synchronization between SAP and Micro-
soft Project Server.“
“We’re really pleased with the new PPM system, as it standardizes the entire planning
procedure. We’ve set up a project cockpit that enables us to see the status of every pro-
ject at the click of a mouse.“
RESULT: PRODUCTION SYSTEM RUNNING WELL
The production system has been running smoothly since
May 2016 and supports all new projects. Although the
previous system is still being used to support some older
projects, it will gradually be retired once these projects
are completed. Erich Taube believes this stage will be
reached by the end of 2017.
“We’re really pleased with the new Microsoft PPM sys-
tem, as it standardizes the entire planning procedure.
We’ve set up a project cockpit that enables us to see
the status of every project at the click of a mouse,” Erich
Taube says.
The bidirectional synchronization between Microsoft
Project and SAP, based on TPG PSLink, is also running sat-
isfactorily. It sends project information, WBS elements
and planned costs from Project Server to SAP; and actu-
al costs, profitability information and resource updates
from SAP to Project Server.
TPG ProjectLink is used for multi-level scheduling. As a
Microsoft Project Server extension, this product enables
cross-project links. These are used for large-scale com-
ponents handled in a master plan and several sub-plans.
The master plan contains the requirements which the
sub-project managers have to observe. The information
from the sub-plans is reported back to the masterplan
(see figure on the next page).
The Company: Alfmeier Präzision SE is a global manufac-
turer of precision system solutions using valves, actuators,
pumps, and controllers. Based in Treuchtlingen (Germa-
ny) and with a global workforce of about 2,000 employees
world-wide, its core competencies include plastic tech-
nology, electronics, mechatronics, fluid tech-nology and
industrial solutions. Alfmeier is a leading supplier to the
automotive industry as well as medical technology and
other sectors.
The Challenge: The company’s project managers were all
using a mix of different project management solutions, in-
cluding a variety of Microsoft Office applications. If a man-
ager wanted an overview of project costs, he or she had to
ask each project manager individually. This made cost and
resource planning, as well as scheduling and reporting,
difficult and time consuming.
The Solution: The project management solution is based
on Microsoft Project Server, which TPG has customized
with over 100 user-defined fields. As SAP is a central busi-
ness solution at Alfmeier, the company has also imple-
mented TPG PSLink to synchronize information between
the project management and ERP systems. TPG Project-
Link is used for multi-level scheduling in the case of large-
scale components with multiple sub-projects.
The Benefits: All aspects of project planning – including
scheduling, resource planning, actual and planned costs,
reporting and more – are significantly faster and more ef-
ficient since the company has been using the enterprise
project management solution. It has saved time and mon-
ey through across-the-board project visibility and accel-
erated reporting, while facilitating the firms’ capacity to
complete even complex projects on time and on budget.
SHORT PROJECT PROFILE
www.theprojectgroup.com
www.theprojectgroup.com/blog/en
www.youtube.com/tpgtheprojectgroup
www.twitter.com/tpg_com(@tpg_com)
Copyright TPG The Project Group / All rights reserved 12/2017 (v1.0)
BENEFITS OF THE NEW SOLUTION
“The solution’s main benefit to our business is better and
more efficient planning, which helps us ensure we complete
our projects on time and on budget,” notes Erich Taube.
“We also save a lot of time on reporting, as we no longer
need to ask each project manager individually to pro-
duce a report – we simply roll them all up together as
everyone’s using the same system.” These reports com-
pare actual costs, profitability information and complet-
ed milestones. They also visualize the differences be-
tween target and actual values with a traffic light display.
Plus, the PMO is able to look into the workloads of project
managers and teams, which also contributes to better plan-
ning. Alfmeier has about 100 projects in the new system,
of which approximately 60 are running in parallel. Around
80% of the projects comprise 300-350 tasks.
“The larger ones can have up to 1000 tasks, so the new
enterprise project management solution is essential to
help us ensure these complex projects are completed
efficiently from a cost and resourcing point of view,”
adds Taube.
NEXT STEPS
Erich Taube and his team are expanding usage of the pro-
ject management system to more users – there are cur-
rently around 35 people using Microsoft Project Client
and 150 using Project Web App – while increasing the
number of projects running on the system.
“We’ve started with fairly small steps to ensure we got
things right before extending it to a large group of us-
ers,” concludes Erich Taube. “As we say at Alfmeier, it’s
small things that set large ones in motion!”.
SOLUTION PARTNER
TPG The Project Group GmbH
Destouchesstr. 68
80796 Munich / Germany
Dr. Thomas Henkelmann
Director Consulting Services
Tel: +49 89 615 593 30
ThomasH@theprojectgroup.com
www.theprojectgroup.com
CLIENT
Alfmeier Präzision SE
Industriestraße 5
91757 Treuchtlingen / Germany
Erich Taube
PMO Leader
Tel. +49 9142 / 70-0
Erich.Taube@Alfmeier.de
www.alfmeier.de
“We also save a lot of time on reporting, as we no longer need to ask each project
manager individually to produce a report – we simply roll them all up together as
everyone’s using the same system.”
Multi-level scheduling with TPG ProjectLInk enables cross-project links to control sub-projects from a master project.

More Related Content

What's hot

MS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for YouMS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for YouCA Technologies
 
Asta Powerproject: Business Case
Asta Powerproject: Business CaseAsta Powerproject: Business Case
Asta Powerproject: Business CaseCisco
 
Re-Architecting with Agile Delivery featuring Forrester's Randy Heffner
Re-Architecting with Agile Delivery featuring Forrester's Randy HeffnerRe-Architecting with Agile Delivery featuring Forrester's Randy Heffner
Re-Architecting with Agile Delivery featuring Forrester's Randy HeffnerHeadspring
 
Digital Time Capture Integrates with Primavera
Digital Time Capture Integrates with PrimaveraDigital Time Capture Integrates with Primavera
Digital Time Capture Integrates with PrimaveraKlopstra
 
Aras Community Update 2016
Aras Community Update 2016Aras Community Update 2016
Aras Community Update 2016Aras
 
Xvison Lundin petroleum case study
Xvison Lundin petroleum case studyXvison Lundin petroleum case study
Xvison Lundin petroleum case studyOlav Sylthe
 
Building the Intellectual Capital of Innovative Organizations using Aras PLM ...
Building the Intellectual Capital of Innovative Organizations using Aras PLM ...Building the Intellectual Capital of Innovative Organizations using Aras PLM ...
Building the Intellectual Capital of Innovative Organizations using Aras PLM ...Aras
 
Introduction to Modern Software Architecture
Introduction to Modern Software ArchitectureIntroduction to Modern Software Architecture
Introduction to Modern Software ArchitectureJérôme Kehrli
 
Field View Analytics - Sempre Analytics
Field View Analytics - Sempre AnalyticsField View Analytics - Sempre Analytics
Field View Analytics - Sempre AnalyticsNick Patrick
 
Field Activity Planner SaaS SW for the Digital Oilfield
Field Activity Planner SaaS SW for the Digital OilfieldField Activity Planner SaaS SW for the Digital Oilfield
Field Activity Planner SaaS SW for the Digital OilfieldOlav Sylthe
 
Success story schaeffler_migration_en
Success story schaeffler_migration_enSuccess story schaeffler_migration_en
Success story schaeffler_migration_enSascha Löffler
 
Field Activity Planner SaaS SW Overview for the Digital Oilfield
Field Activity Planner SaaS SW Overview for the Digital OilfieldField Activity Planner SaaS SW Overview for the Digital Oilfield
Field Activity Planner SaaS SW Overview for the Digital OilfieldOlav Sylthe
 
What is Field Activity Planner SaaS SW
What is Field Activity Planner SaaS SWWhat is Field Activity Planner SaaS SW
What is Field Activity Planner SaaS SWOlav Sylthe
 
New Approaches to ALM PLM Cross Discipline Product Development
New Approaches to ALM PLM Cross Discipline Product DevelopmentNew Approaches to ALM PLM Cross Discipline Product Development
New Approaches to ALM PLM Cross Discipline Product DevelopmentAras
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and schedulingAditi Garg
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalAMIT PAYAL
 

What's hot (20)

MS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for YouMS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for You
 
Asta Powerproject: Business Case
Asta Powerproject: Business CaseAsta Powerproject: Business Case
Asta Powerproject: Business Case
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Re-Architecting with Agile Delivery featuring Forrester's Randy Heffner
Re-Architecting with Agile Delivery featuring Forrester's Randy HeffnerRe-Architecting with Agile Delivery featuring Forrester's Randy Heffner
Re-Architecting with Agile Delivery featuring Forrester's Randy Heffner
 
Digital Time Capture Integrates with Primavera
Digital Time Capture Integrates with PrimaveraDigital Time Capture Integrates with Primavera
Digital Time Capture Integrates with Primavera
 
Aras Community Update 2016
Aras Community Update 2016Aras Community Update 2016
Aras Community Update 2016
 
Xvison Lundin petroleum case study
Xvison Lundin petroleum case studyXvison Lundin petroleum case study
Xvison Lundin petroleum case study
 
Building the Intellectual Capital of Innovative Organizations using Aras PLM ...
Building the Intellectual Capital of Innovative Organizations using Aras PLM ...Building the Intellectual Capital of Innovative Organizations using Aras PLM ...
Building the Intellectual Capital of Innovative Organizations using Aras PLM ...
 
Introduction to Modern Software Architecture
Introduction to Modern Software ArchitectureIntroduction to Modern Software Architecture
Introduction to Modern Software Architecture
 
Field View Analytics - Sempre Analytics
Field View Analytics - Sempre AnalyticsField View Analytics - Sempre Analytics
Field View Analytics - Sempre Analytics
 
Field Activity Planner SaaS SW for the Digital Oilfield
Field Activity Planner SaaS SW for the Digital OilfieldField Activity Planner SaaS SW for the Digital Oilfield
Field Activity Planner SaaS SW for the Digital Oilfield
 
Success story schaeffler_migration_en
Success story schaeffler_migration_enSuccess story schaeffler_migration_en
Success story schaeffler_migration_en
 
Artist essoc 2013_12092013
Artist essoc 2013_12092013Artist essoc 2013_12092013
Artist essoc 2013_12092013
 
Field Activity Planner SaaS SW Overview for the Digital Oilfield
Field Activity Planner SaaS SW Overview for the Digital OilfieldField Activity Planner SaaS SW Overview for the Digital Oilfield
Field Activity Planner SaaS SW Overview for the Digital Oilfield
 
What is Field Activity Planner SaaS SW
What is Field Activity Planner SaaS SWWhat is Field Activity Planner SaaS SW
What is Field Activity Planner SaaS SW
 
New Approaches to ALM PLM Cross Discipline Product Development
New Approaches to ALM PLM Cross Discipline Product DevelopmentNew Approaches to ALM PLM Cross Discipline Product Development
New Approaches to ALM PLM Cross Discipline Product Development
 
SmartPlant Construction
SmartPlant ConstructionSmartPlant Construction
SmartPlant Construction
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
PlanENDoc
PlanENDocPlanENDoc
PlanENDoc
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 

Similar to Case Study Alfmeier Präzision SE - English

Case Study Automotive Electronic: Integration Microsoft Project with SAP
Case Study Automotive Electronic: Integration Microsoft Project with SAPCase Study Automotive Electronic: Integration Microsoft Project with SAP
Case Study Automotive Electronic: Integration Microsoft Project with SAPTPG The Project Group
 
Case Study: TPG Project Management Solution Delivers Big Savings to Emmi Schw...
Case Study: TPG Project Management Solution Delivers Big Savings to Emmi Schw...Case Study: TPG Project Management Solution Delivers Big Savings to Emmi Schw...
Case Study: TPG Project Management Solution Delivers Big Savings to Emmi Schw...TPG The Project Group
 
Accesa - Cloud4Gantt SharePoint product
Accesa - Cloud4Gantt SharePoint productAccesa - Cloud4Gantt SharePoint product
Accesa - Cloud4Gantt SharePoint productAccesa
 
Demolition project-management-solution
Demolition project-management-solutionDemolition project-management-solution
Demolition project-management-solutionVishakhaBhagia1
 
Demolition project-management-solution
Demolition project-management-solutionDemolition project-management-solution
Demolition project-management-solutionMaitrikpaida
 
Workplace-of-the-Future
Workplace-of-the-FutureWorkplace-of-the-Future
Workplace-of-the-FutureOscar Kessen
 
OpenText Extended ECM for Engineering
OpenText Extended ECM for EngineeringOpenText Extended ECM for Engineering
OpenText Extended ECM for EngineeringVILT
 
Project portfolio management comparison of microsoft epm and primavera p6 v...
Project portfolio management   comparison of microsoft epm and primavera p6 v...Project portfolio management   comparison of microsoft epm and primavera p6 v...
Project portfolio management comparison of microsoft epm and primavera p6 v...p6academy
 
OnPlan Digital Work Management Platform
OnPlan Digital Work Management PlatformOnPlan Digital Work Management Platform
OnPlan Digital Work Management PlatformStuart Burckhardt
 
Rapid Application Development
Rapid Application DevelopmentRapid Application Development
Rapid Application DevelopmentVILT
 
Application Transformation Workshop
Application Transformation WorkshopApplication Transformation Workshop
Application Transformation WorkshopVMware Tanzu
 
Beyond PLM enabling Live Engineering - Digital Engineer 2016
Beyond PLM enabling Live Engineering - Digital Engineer 2016Beyond PLM enabling Live Engineering - Digital Engineer 2016
Beyond PLM enabling Live Engineering - Digital Engineer 2016John McNiff
 
Keith Marchand CV 2015
Keith Marchand CV 2015Keith Marchand CV 2015
Keith Marchand CV 2015Keith Marchand
 
Keith marchand cv 2015
Keith marchand cv 2015Keith marchand cv 2015
Keith marchand cv 2015Keith Marchand
 
SuccessGlo navigating safely through the Corona crisis with Plunet
SuccessGlo navigating safely through the Corona crisis with PlunetSuccessGlo navigating safely through the Corona crisis with Plunet
SuccessGlo navigating safely through the Corona crisis with PlunetPlunet BusinessManager
 
Manufacturing x - Success Story 2019 - Interplex
Manufacturing x  - Success Story 2019 - InterplexManufacturing x  - Success Story 2019 - Interplex
Manufacturing x - Success Story 2019 - InterplexIn Mind Cloud
 
Shane hutchison - Technology & Business Manager
Shane hutchison - Technology & Business ManagerShane hutchison - Technology & Business Manager
Shane hutchison - Technology & Business ManagerShane Hutchison
 

Similar to Case Study Alfmeier Präzision SE - English (20)

Case Study Automotive Electronic: Integration Microsoft Project with SAP
Case Study Automotive Electronic: Integration Microsoft Project with SAPCase Study Automotive Electronic: Integration Microsoft Project with SAP
Case Study Automotive Electronic: Integration Microsoft Project with SAP
 
Case Study: TPG Project Management Solution Delivers Big Savings to Emmi Schw...
Case Study: TPG Project Management Solution Delivers Big Savings to Emmi Schw...Case Study: TPG Project Management Solution Delivers Big Savings to Emmi Schw...
Case Study: TPG Project Management Solution Delivers Big Savings to Emmi Schw...
 
Accesa - Cloud4Gantt SharePoint product
Accesa - Cloud4Gantt SharePoint productAccesa - Cloud4Gantt SharePoint product
Accesa - Cloud4Gantt SharePoint product
 
Demolition project-management-solution
Demolition project-management-solutionDemolition project-management-solution
Demolition project-management-solution
 
Demolition project-management-solution
Demolition project-management-solutionDemolition project-management-solution
Demolition project-management-solution
 
Workplace-of-the-Future
Workplace-of-the-FutureWorkplace-of-the-Future
Workplace-of-the-Future
 
OpenText Extended ECM for Engineering
OpenText Extended ECM for EngineeringOpenText Extended ECM for Engineering
OpenText Extended ECM for Engineering
 
Project portfolio management comparison of microsoft epm and primavera p6 v...
Project portfolio management   comparison of microsoft epm and primavera p6 v...Project portfolio management   comparison of microsoft epm and primavera p6 v...
Project portfolio management comparison of microsoft epm and primavera p6 v...
 
OnPlan Digital Work Management Platform
OnPlan Digital Work Management PlatformOnPlan Digital Work Management Platform
OnPlan Digital Work Management Platform
 
Rapid Application Development
Rapid Application DevelopmentRapid Application Development
Rapid Application Development
 
rtb_success_mark
rtb_success_markrtb_success_mark
rtb_success_mark
 
Application Transformation Workshop
Application Transformation WorkshopApplication Transformation Workshop
Application Transformation Workshop
 
Beyond PLM enabling Live Engineering - Digital Engineer 2016
Beyond PLM enabling Live Engineering - Digital Engineer 2016Beyond PLM enabling Live Engineering - Digital Engineer 2016
Beyond PLM enabling Live Engineering - Digital Engineer 2016
 
Keith Marchand CV 2015
Keith Marchand CV 2015Keith Marchand CV 2015
Keith Marchand CV 2015
 
Keith marchand cv 2015
Keith marchand cv 2015Keith marchand cv 2015
Keith marchand cv 2015
 
Transnet Engineering
Transnet EngineeringTransnet Engineering
Transnet Engineering
 
SuccessGlo navigating safely through the Corona crisis with Plunet
SuccessGlo navigating safely through the Corona crisis with PlunetSuccessGlo navigating safely through the Corona crisis with Plunet
SuccessGlo navigating safely through the Corona crisis with Plunet
 
Manufacturing x - Success Story 2019 - Interplex
Manufacturing x  - Success Story 2019 - InterplexManufacturing x  - Success Story 2019 - Interplex
Manufacturing x - Success Story 2019 - Interplex
 
Global Squad Leader - Resume
Global Squad Leader - ResumeGlobal Squad Leader - Resume
Global Squad Leader - Resume
 
Shane hutchison - Technology & Business Manager
Shane hutchison - Technology & Business ManagerShane hutchison - Technology & Business Manager
Shane hutchison - Technology & Business Manager
 

More from TPG The Project Group

Don’t Overlook the Million Dollar Idea –Idea Management with K2 and Project O...
Don’t Overlook the Million Dollar Idea –Idea Management with K2 and Project O...Don’t Overlook the Million Dollar Idea –Idea Management with K2 and Project O...
Don’t Overlook the Million Dollar Idea –Idea Management with K2 and Project O...TPG The Project Group
 
Slideshare webinar 2017-02-22_pm_skill-modellierung
Slideshare webinar 2017-02-22_pm_skill-modellierungSlideshare webinar 2017-02-22_pm_skill-modellierung
Slideshare webinar 2017-02-22_pm_skill-modellierungTPG The Project Group
 
Agile, klassisch oder hybrid: Welche Projektmanagement-Methode ust die Richtige?
Agile, klassisch oder hybrid: Welche Projektmanagement-Methode ust die Richtige?Agile, klassisch oder hybrid: Welche Projektmanagement-Methode ust die Richtige?
Agile, klassisch oder hybrid: Welche Projektmanagement-Methode ust die Richtige?TPG The Project Group
 
11 Argumente für ein Projekt, Ressourcen- und Portfoliomanagement System
11 Argumente für ein Projekt, Ressourcen- und Portfoliomanagement System11 Argumente für ein Projekt, Ressourcen- und Portfoliomanagement System
11 Argumente für ein Projekt, Ressourcen- und Portfoliomanagement SystemTPG The Project Group
 
Ausblick auf die zukunft des pmo slideshare
Ausblick auf die zukunft des pmo   slideshareAusblick auf die zukunft des pmo   slideshare
Ausblick auf die zukunft des pmo slideshareTPG The Project Group
 
Projekte und Portfolios mit Reports steuern - sinnvolle und nötige Berichte
Projekte und Portfolios mit Reports steuern - sinnvolle und nötige BerichteProjekte und Portfolios mit Reports steuern - sinnvolle und nötige Berichte
Projekte und Portfolios mit Reports steuern - sinnvolle und nötige BerichteTPG The Project Group
 
TPG PSLink - Integration of Financial and Project Data (Integration of Micros...
TPG PSLink - Integration of Financial and Project Data (Integration of Micros...TPG PSLink - Integration of Financial and Project Data (Integration of Micros...
TPG PSLink - Integration of Financial and Project Data (Integration of Micros...TPG The Project Group
 
Case Study Vaillant: Multi-Projektmanagement mit MS Project und SAP integration
Case Study Vaillant: Multi-Projektmanagement mit MS Project und SAP integrationCase Study Vaillant: Multi-Projektmanagement mit MS Project und SAP integration
Case Study Vaillant: Multi-Projektmanagement mit MS Project und SAP integrationTPG The Project Group
 

More from TPG The Project Group (9)

Don’t Overlook the Million Dollar Idea –Idea Management with K2 and Project O...
Don’t Overlook the Million Dollar Idea –Idea Management with K2 and Project O...Don’t Overlook the Million Dollar Idea –Idea Management with K2 and Project O...
Don’t Overlook the Million Dollar Idea –Idea Management with K2 and Project O...
 
Slideshare webinar 2017-02-22_pm_skill-modellierung
Slideshare webinar 2017-02-22_pm_skill-modellierungSlideshare webinar 2017-02-22_pm_skill-modellierung
Slideshare webinar 2017-02-22_pm_skill-modellierung
 
Agile, klassisch oder hybrid: Welche Projektmanagement-Methode ust die Richtige?
Agile, klassisch oder hybrid: Welche Projektmanagement-Methode ust die Richtige?Agile, klassisch oder hybrid: Welche Projektmanagement-Methode ust die Richtige?
Agile, klassisch oder hybrid: Welche Projektmanagement-Methode ust die Richtige?
 
11 Argumente für ein Projekt, Ressourcen- und Portfoliomanagement System
11 Argumente für ein Projekt, Ressourcen- und Portfoliomanagement System11 Argumente für ein Projekt, Ressourcen- und Portfoliomanagement System
11 Argumente für ein Projekt, Ressourcen- und Portfoliomanagement System
 
TPG TeamManager App
TPG TeamManager AppTPG TeamManager App
TPG TeamManager App
 
Ausblick auf die zukunft des pmo slideshare
Ausblick auf die zukunft des pmo   slideshareAusblick auf die zukunft des pmo   slideshare
Ausblick auf die zukunft des pmo slideshare
 
Projekte und Portfolios mit Reports steuern - sinnvolle und nötige Berichte
Projekte und Portfolios mit Reports steuern - sinnvolle und nötige BerichteProjekte und Portfolios mit Reports steuern - sinnvolle und nötige Berichte
Projekte und Portfolios mit Reports steuern - sinnvolle und nötige Berichte
 
TPG PSLink - Integration of Financial and Project Data (Integration of Micros...
TPG PSLink - Integration of Financial and Project Data (Integration of Micros...TPG PSLink - Integration of Financial and Project Data (Integration of Micros...
TPG PSLink - Integration of Financial and Project Data (Integration of Micros...
 
Case Study Vaillant: Multi-Projektmanagement mit MS Project und SAP integration
Case Study Vaillant: Multi-Projektmanagement mit MS Project und SAP integrationCase Study Vaillant: Multi-Projektmanagement mit MS Project und SAP integration
Case Study Vaillant: Multi-Projektmanagement mit MS Project und SAP integration
 

Recently uploaded

How to Check CNIC Information Online with Pakdata cf
How to Check CNIC Information Online with Pakdata cfHow to Check CNIC Information Online with Pakdata cf
How to Check CNIC Information Online with Pakdata cfdanishmna97
 
Introduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDMIntroduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDMKumar Satyam
 
CORS (Kitworks Team Study 양다윗 발표자료 240510)
CORS (Kitworks Team Study 양다윗 발표자료 240510)CORS (Kitworks Team Study 양다윗 발표자료 240510)
CORS (Kitworks Team Study 양다윗 발표자료 240510)Wonjun Hwang
 
2024 May Patch Tuesday
2024 May Patch Tuesday2024 May Patch Tuesday
2024 May Patch TuesdayIvanti
 
Portal Kombat : extension du réseau de propagande russe
Portal Kombat : extension du réseau de propagande russePortal Kombat : extension du réseau de propagande russe
Portal Kombat : extension du réseau de propagande russe中 央社
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontologyjohnbeverley2021
 
Cyber Insurance - RalphGilot - Embry-Riddle Aeronautical University.pptx
Cyber Insurance - RalphGilot - Embry-Riddle Aeronautical University.pptxCyber Insurance - RalphGilot - Embry-Riddle Aeronautical University.pptx
Cyber Insurance - RalphGilot - Embry-Riddle Aeronautical University.pptxMasterG
 
Generative AI Use Cases and Applications.pdf
Generative AI Use Cases and Applications.pdfGenerative AI Use Cases and Applications.pdf
Generative AI Use Cases and Applications.pdfalexjohnson7307
 
Easier, Faster, and More Powerful – Notes Document Properties Reimagined
Easier, Faster, and More Powerful – Notes Document Properties ReimaginedEasier, Faster, and More Powerful – Notes Document Properties Reimagined
Easier, Faster, and More Powerful – Notes Document Properties Reimaginedpanagenda
 
Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider  Progress from Awareness to Implementation.pptxTales from a Passkey Provider  Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider Progress from Awareness to Implementation.pptxFIDO Alliance
 
ADP Passwordless Journey Case Study.pptx
ADP Passwordless Journey Case Study.pptxADP Passwordless Journey Case Study.pptx
ADP Passwordless Journey Case Study.pptxFIDO Alliance
 
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)Samir Dash
 
JavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuideJavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuidePixlogix Infotech
 
الأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهلهالأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهلهMohamed Sweelam
 
Working together SRE & Platform Engineering
Working together SRE & Platform EngineeringWorking together SRE & Platform Engineering
Working together SRE & Platform EngineeringMarcus Vechiato
 
Google I/O Extended 2024 Warsaw
Google I/O Extended 2024 WarsawGoogle I/O Extended 2024 Warsaw
Google I/O Extended 2024 WarsawGDSC PJATK
 
Continuing Bonds Through AI: A Hermeneutic Reflection on Thanabots
Continuing Bonds Through AI: A Hermeneutic Reflection on ThanabotsContinuing Bonds Through AI: A Hermeneutic Reflection on Thanabots
Continuing Bonds Through AI: A Hermeneutic Reflection on ThanabotsLeah Henrickson
 
Design Guidelines for Passkeys 2024.pptx
Design Guidelines for Passkeys 2024.pptxDesign Guidelines for Passkeys 2024.pptx
Design Guidelines for Passkeys 2024.pptxFIDO Alliance
 
WebAssembly is Key to Better LLM Performance
WebAssembly is Key to Better LLM PerformanceWebAssembly is Key to Better LLM Performance
WebAssembly is Key to Better LLM PerformanceSamy Fodil
 

Recently uploaded (20)

How to Check CNIC Information Online with Pakdata cf
How to Check CNIC Information Online with Pakdata cfHow to Check CNIC Information Online with Pakdata cf
How to Check CNIC Information Online with Pakdata cf
 
Introduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDMIntroduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDM
 
CORS (Kitworks Team Study 양다윗 발표자료 240510)
CORS (Kitworks Team Study 양다윗 발표자료 240510)CORS (Kitworks Team Study 양다윗 발표자료 240510)
CORS (Kitworks Team Study 양다윗 발표자료 240510)
 
2024 May Patch Tuesday
2024 May Patch Tuesday2024 May Patch Tuesday
2024 May Patch Tuesday
 
Portal Kombat : extension du réseau de propagande russe
Portal Kombat : extension du réseau de propagande russePortal Kombat : extension du réseau de propagande russe
Portal Kombat : extension du réseau de propagande russe
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontology
 
Overview of Hyperledger Foundation
Overview of Hyperledger FoundationOverview of Hyperledger Foundation
Overview of Hyperledger Foundation
 
Cyber Insurance - RalphGilot - Embry-Riddle Aeronautical University.pptx
Cyber Insurance - RalphGilot - Embry-Riddle Aeronautical University.pptxCyber Insurance - RalphGilot - Embry-Riddle Aeronautical University.pptx
Cyber Insurance - RalphGilot - Embry-Riddle Aeronautical University.pptx
 
Generative AI Use Cases and Applications.pdf
Generative AI Use Cases and Applications.pdfGenerative AI Use Cases and Applications.pdf
Generative AI Use Cases and Applications.pdf
 
Easier, Faster, and More Powerful – Notes Document Properties Reimagined
Easier, Faster, and More Powerful – Notes Document Properties ReimaginedEasier, Faster, and More Powerful – Notes Document Properties Reimagined
Easier, Faster, and More Powerful – Notes Document Properties Reimagined
 
Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider  Progress from Awareness to Implementation.pptxTales from a Passkey Provider  Progress from Awareness to Implementation.pptx
Tales from a Passkey Provider Progress from Awareness to Implementation.pptx
 
ADP Passwordless Journey Case Study.pptx
ADP Passwordless Journey Case Study.pptxADP Passwordless Journey Case Study.pptx
ADP Passwordless Journey Case Study.pptx
 
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
AI+A11Y 11MAY2024 HYDERBAD GAAD 2024 - HelloA11Y (11 May 2024)
 
JavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuideJavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate Guide
 
الأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهلهالأمن السيبراني - ما لا يسع للمستخدم جهله
الأمن السيبراني - ما لا يسع للمستخدم جهله
 
Working together SRE & Platform Engineering
Working together SRE & Platform EngineeringWorking together SRE & Platform Engineering
Working together SRE & Platform Engineering
 
Google I/O Extended 2024 Warsaw
Google I/O Extended 2024 WarsawGoogle I/O Extended 2024 Warsaw
Google I/O Extended 2024 Warsaw
 
Continuing Bonds Through AI: A Hermeneutic Reflection on Thanabots
Continuing Bonds Through AI: A Hermeneutic Reflection on ThanabotsContinuing Bonds Through AI: A Hermeneutic Reflection on Thanabots
Continuing Bonds Through AI: A Hermeneutic Reflection on Thanabots
 
Design Guidelines for Passkeys 2024.pptx
Design Guidelines for Passkeys 2024.pptxDesign Guidelines for Passkeys 2024.pptx
Design Guidelines for Passkeys 2024.pptx
 
WebAssembly is Key to Better LLM Performance
WebAssembly is Key to Better LLM PerformanceWebAssembly is Key to Better LLM Performance
WebAssembly is Key to Better LLM Performance
 

Case Study Alfmeier Präzision SE - English

  • 1. INDUSTRY Automotive DEPARTMENT Precision Engineering SOLUTION Microsoft Project Server TPG PSLink TPG ProjectLink Integrated Project Management Solution:Even complex projects on time and on budget SMALL THINGS SET LARGE ONES IN MOTION Precision engineering company Alfmeier Präzision SE refers to the tiny components it makes with the inspir- ing phrase: “Small things set large ones in motion”. Starting with small steps, a change of system supporting its project management organization has also moved the company forward, making it more efficient and competitive. A key component of the enterprise project manage- ment solution is the bidirectional data synchronization between SAP and Microsoft Project, making cost and re- source planning simpler and more accurate. Alfmeier Präzision SE is a global high-tech company serv- ing the automotive and other industries. With about 2000 employees worldwide, it is a recognized specialist in plastic injection molding and fluid systems as well as electronics, mechatronics and car seat solutions. The Fluid Systems business unit develops intelligent solu- tions for applications such as fuel supply, servo assistance, flap control, crank case ventilation as well as thermal man- agement. The Seat Comfort division focuses on a range of advanced solutions for car seats that adapt to the anatomy of the vehicle’s occupants. The company is headquartered in Treuchtlingen (Germany) and has subsidiaries in the USA, Mexico, Czech Republic, China and Korea. Case Study
  • 2. PATCHWORK OF DIFFERENT TOOLS With the implementation of SAP PS and other tools for project planning, the precision engineering company end- ed up using a plethora of different systems. Each project manager had their own preference. So if management wanted to know how a specific project – or even the over- all project cost – was progressing, they had to ask each project manager individually. This was a particularly complex undertaking in Alfmeier’s case as the company operates in multiple different coun- tries. Project managers would request and create projects in SAP PS, while documents produced by the teams dur- ing the course of the project work were in other formats, such as Word and Excel – particularly for cost estimates, proposal approvals and change requests. The staff entered their timesheet information in SAP and managers produced reports in Excel, PowerPoint, Access and Word as well as APIS and QlikView. This made it challenging to consolidate all the infor- mation as a basis for planning and decision-making. As each project manager was using his or her preferred planning and scheduling tool, there was no quick way to review the teams’ schedules and ensure optimal staff resource utilization. CENTRALIZE AND STREAMLINE PROJECT PLANNING Erich Taube, Head of Project Management Office (PMO) at Alfmeier Präzision SE, headed up a team tasked with finding a suitable solution for streamlining and stand- ardizing project planning processes. “With our fairly intensive use of Microsoft Office prod- ucts, we thought Microsoft Project Server would be the best fit, so we set about looking for potential partners,” says Erich Taube. Meeting specialists from TPG The Project Group, Erich Taube and his team were impressed by their experi- ence and their quick grasp of the project management situation at Alfmeier. The team drew up a matrix com- paring the offerings of the various providers, and TPG came out clearly on top. “But what really clinched it for TPG was their TPG PSLink product for bidirectional data synchronization between SAP and Microsoft Project Server, along with their ability to customize Microsoft Project Server to our needs,” adds Taube. CUSTOMIZED FUNCTIONALITY The first step was for everyone involved to get round a ta- ble and define the project’s specifications and goals. This was followed by the implementation of a test system to run alongside the production system on both the Micro- soft Project and SAP sides. The two teams worked together to implement over 100 user-defined fields in Microsoft Project, mainly SAP-relat- ed. Alfmeier staff ran a sample project through the sys- tems to test both sides, including the planning process as well as schedules and costs. TPG was then tasked with developing a custom function for Alfmeier’s project managers. “We wanted a profit- ability indicator, updated in real time, to enable project managers to see at a glance how profitable their projects were,” comments Erich Taube. That way, project staff could work with their familiar tool without needing any expertise in the use of SAP. TPG de- veloped the custom feature and implemented it together with the rest of the system. On the Alfmeier side, Erich Taube and his team facilitated user acceptance by organizing multiple training courses. They also designated individuals in the PMO who could in- tervene immediately in case of any problems in the field. In addition, the team supports several power users in the local offices who are able to help their colleagues quickly when queries arise. „What really clinched it for TPG was their TPG PSLink product for bidirectional data synchronization between SAP and Micro- soft Project Server.“
  • 3. “We’re really pleased with the new PPM system, as it standardizes the entire planning procedure. We’ve set up a project cockpit that enables us to see the status of every pro- ject at the click of a mouse.“ RESULT: PRODUCTION SYSTEM RUNNING WELL The production system has been running smoothly since May 2016 and supports all new projects. Although the previous system is still being used to support some older projects, it will gradually be retired once these projects are completed. Erich Taube believes this stage will be reached by the end of 2017. “We’re really pleased with the new Microsoft PPM sys- tem, as it standardizes the entire planning procedure. We’ve set up a project cockpit that enables us to see the status of every project at the click of a mouse,” Erich Taube says. The bidirectional synchronization between Microsoft Project and SAP, based on TPG PSLink, is also running sat- isfactorily. It sends project information, WBS elements and planned costs from Project Server to SAP; and actu- al costs, profitability information and resource updates from SAP to Project Server. TPG ProjectLink is used for multi-level scheduling. As a Microsoft Project Server extension, this product enables cross-project links. These are used for large-scale com- ponents handled in a master plan and several sub-plans. The master plan contains the requirements which the sub-project managers have to observe. The information from the sub-plans is reported back to the masterplan (see figure on the next page). The Company: Alfmeier Präzision SE is a global manufac- turer of precision system solutions using valves, actuators, pumps, and controllers. Based in Treuchtlingen (Germa- ny) and with a global workforce of about 2,000 employees world-wide, its core competencies include plastic tech- nology, electronics, mechatronics, fluid tech-nology and industrial solutions. Alfmeier is a leading supplier to the automotive industry as well as medical technology and other sectors. The Challenge: The company’s project managers were all using a mix of different project management solutions, in- cluding a variety of Microsoft Office applications. If a man- ager wanted an overview of project costs, he or she had to ask each project manager individually. This made cost and resource planning, as well as scheduling and reporting, difficult and time consuming. The Solution: The project management solution is based on Microsoft Project Server, which TPG has customized with over 100 user-defined fields. As SAP is a central busi- ness solution at Alfmeier, the company has also imple- mented TPG PSLink to synchronize information between the project management and ERP systems. TPG Project- Link is used for multi-level scheduling in the case of large- scale components with multiple sub-projects. The Benefits: All aspects of project planning – including scheduling, resource planning, actual and planned costs, reporting and more – are significantly faster and more ef- ficient since the company has been using the enterprise project management solution. It has saved time and mon- ey through across-the-board project visibility and accel- erated reporting, while facilitating the firms’ capacity to complete even complex projects on time and on budget. SHORT PROJECT PROFILE
  • 4. www.theprojectgroup.com www.theprojectgroup.com/blog/en www.youtube.com/tpgtheprojectgroup www.twitter.com/tpg_com(@tpg_com) Copyright TPG The Project Group / All rights reserved 12/2017 (v1.0) BENEFITS OF THE NEW SOLUTION “The solution’s main benefit to our business is better and more efficient planning, which helps us ensure we complete our projects on time and on budget,” notes Erich Taube. “We also save a lot of time on reporting, as we no longer need to ask each project manager individually to pro- duce a report – we simply roll them all up together as everyone’s using the same system.” These reports com- pare actual costs, profitability information and complet- ed milestones. They also visualize the differences be- tween target and actual values with a traffic light display. Plus, the PMO is able to look into the workloads of project managers and teams, which also contributes to better plan- ning. Alfmeier has about 100 projects in the new system, of which approximately 60 are running in parallel. Around 80% of the projects comprise 300-350 tasks. “The larger ones can have up to 1000 tasks, so the new enterprise project management solution is essential to help us ensure these complex projects are completed efficiently from a cost and resourcing point of view,” adds Taube. NEXT STEPS Erich Taube and his team are expanding usage of the pro- ject management system to more users – there are cur- rently around 35 people using Microsoft Project Client and 150 using Project Web App – while increasing the number of projects running on the system. “We’ve started with fairly small steps to ensure we got things right before extending it to a large group of us- ers,” concludes Erich Taube. “As we say at Alfmeier, it’s small things that set large ones in motion!”. SOLUTION PARTNER TPG The Project Group GmbH Destouchesstr. 68 80796 Munich / Germany Dr. Thomas Henkelmann Director Consulting Services Tel: +49 89 615 593 30 ThomasH@theprojectgroup.com www.theprojectgroup.com CLIENT Alfmeier Präzision SE Industriestraße 5 91757 Treuchtlingen / Germany Erich Taube PMO Leader Tel. +49 9142 / 70-0 Erich.Taube@Alfmeier.de www.alfmeier.de “We also save a lot of time on reporting, as we no longer need to ask each project manager individually to produce a report – we simply roll them all up together as everyone’s using the same system.” Multi-level scheduling with TPG ProjectLInk enables cross-project links to control sub-projects from a master project.