Solar-Assisted EV Charging Update

  1. 1. Solar-Assisted EV Charging Update TDEC Conference Kingsport, Tennessee March 13, 2013
  2. 2. ORNL is DOE’s largest science and energy laboratory $1.65B budget World’s most intense neutron source 4,400 employees World-class research reactor 3,000 research guests annually $500M modernization investment Nation’s largest materials research portfolio Most powerful open scientific computing facility Nation’s most diverse energy portfolio Managing billion-dollar U.S. ITER project 2 Green Economy 1302
  3. 3. 3 Managed by UT-Battelle for the U.S. Department of Energy 3 Managed by UT-Battelle for the U.S. Department of Energy Solar-Assisted EV Charging Project •  In August 2009, ORNL was awarded $6.8 million for the installation of solar-assisted EV charging stations in Tennessee. This was part of a larger DOE grant to Ecotality for the deployment of EV charging stations in five states •  The grant to ORNL required a 50/50 cost share match from regional partners. The majority of the cost share has been, or will be met, by the State of Tennessee, TVA, EPRI, and Nissan. •  The final part of the cost share match is the State of Tennessee project. •  We have also enjoyed great partnerships and in-kind support from the cities, distributors, and universities with whom we have worked.
  4. 4. 4 Managed by UT-Battelle for the U.S. Department of Energy 4 Managed by UT-Battelle for the U.S. Department of Energy Levels of EV Charging Voltage AC/DC Time for Full Leaf Charge (24 kwh) Range Level 1 110 AC ~20 hours 4-5 miles per hour of charging Level 2 220 AC ~7 hours 12 miles per hour of charging Fast Charger 480 DC 30 minutes (for 80% charge) 80 miles per half- hour of charging
  5. 5. 5 Managed by UT-Battelle for the U.S. Department of Energy 5 Managed by UT-Battelle for the U.S. Department of Energy Levels of EV Charging Level 2DC Fast Charger
  6. 6. 6 Managed by UT-Battelle for the U.S. Department of Energy 6 Managed by UT-Battelle for the U.S. Department of Energy Regional Solar-Covered ParkingProject Components 2.0 kw of solar per parking space Electric vehicle Charging system (EVSE) Level 2 External battery Grid connection
  7. 7. 7 Managed by UT-Battelle for the U.S. Department of Energy 7 Managed by UT-Battelle for the U.S. Department of Energy Locations of Solar-Assisted Charging in Tennessee 10 stations in Memphis 22 stations 10 stations 30 stations at Nissan 25 stations at ORNL 22 Stations Knoxville and UTK 6 stations at EPRI Original map overlays by Ecotality
  8. 8. 8 Managed by UT-Battelle for the U.S. Department of Energy 8 Managed by UT-Battelle for the U.S. Department of Energy ORNL: 25 Solar charging stations
  9. 9. 9 Managed by UT-Battelle for the U.S. Department of Energy 9 Managed by UT-Battelle for the U.S. Department of Energy Completed Installations ORNL/EPRI Level 2 charges 12 kW solar PV array 30 kWh battery bank EPRI Installation 6-solar assisted stations 2 Clipper Creek level 2 chargers 2 EVSE LLC level 2 chargers 2 Eaton level 2 chargers ORNL Installation 25-solar assisted stations http://ExtWebApps.ornl.gov/PVEV_ext Blink level 2 chargers 47 kW solar PV array 60 kWh battery bank
  10. 10. 10 Managed by UT-Battelle for the U.S. Department of Energy 10 Managed by UT-Battelle for the U.S. Department of Energy Nissan HQ Solar-Assisted EV Charging Station, Franklin, TN
  11. 11. 11 Managed by UT-Battelle for the U.S. Department of Energy 11 Managed by UT-Battelle for the U.S. Department of Energy Completed Installations NISSAN Blink level 2 chargers 19kW solar PV array 24 kWh battery bank Franklin 18-solar assisted stationsSmyrna, Administration Building 9-solar assisted stations AeroViro -nment level 2 chargers 38 kW solar PV array 24 kWh battery bank
  12. 12. 12 Managed by UT-Battelle for the U.S. Department of Energy 12 Managed by UT-Battelle for the U.S. Department of Energy Completed Installation Nissan: 3 solar assisted stations Blink level 2 chargers 6.5 kW solar PV array 24 kWh battery bank Battery Plant, Smyrna
  13. 13. 13 Managed by UT-Battelle for the U.S. Department of Energy 13 Managed by UT-Battelle for the U.S. Department of Energy Completed Installation Nashville: 8 solar assisted stations Blink level 2 chargers 17.2 kW solar PV array 13 kWh battery bank LP Field – Sports Authority
  14. 14. 14 Managed by UT-Battelle for the U.S. Department of Energy 14 Managed by UT-Battelle for the U.S. Department of Energy UT Agriculture Campus Completed Installation UT-Knoxville: 6 solar assisted stations Blink level 2 chargers 14.4 kW solar PV array 10 kWh battery bank
  15. 15. 15 Managed by UT-Battelle for the U.S. Department of Energy 15 Managed by UT-Battelle for the U.S. Department of Energy University of Tennessee, Knoxville: 12 solar-assisted charging stations Blink level 2 chargers 14.4 kW solar PV arrays 10 kWh battery banks
  16. 16. 16 Managed by UT-Battelle for the U.S. Department of Energy 16 Managed by UT-Battelle for the U.S. Department of Energy Civic Coliseum, Knoxville: 6 solar-assisted charging stations Blink level 2 chargers 14.4 kW solar PV array 6.7 kWh battery bank Solar panelsRibbon cutting, September 2012
  17. 17. 17 Managed by UT-Battelle for the U.S. Department of Energy 17 Managed by UT-Battelle for the U.S. Department of Energy Blink level 2 chargers 10 kW solar PV array 8.4 kWh battery bank Solar panels location Market Square Garage, Knoxville: 4 solar-assisted charging stations Charging station
  18. 18. 18 Managed by UT-Battelle for the U.S. Department of Energy 18 Managed by UT-Battelle for the U.S. Department of Energy State Of Tennessee Site Nashville: 4 solar-assisted charging stations Blink level 2 chargers 8.6 kW solar PV array 6.7 kWh battery bank 4th and Harrison
  19. 19. 19 Managed by UT-Battelle for the U.S. Department of Energy 19 Managed by UT-Battelle for the U.S. Department of Energy Completed Installation Vanderbilt University: 10 solar-assisted charging stations Eaton level 2 chargers 20 kW solar PV array 3 kWh battery bank
  20. 20. 20 Managed by UT-Battelle for the U.S. Department of Energy 20 Managed by UT-Battelle for the U.S. Department of Energy Completed Installation Chattanooga: 6 solar-assisted charging stations Eaton level 2 chargers 12 kW solar PV array 3.0 kWh battery bank Theater Group
  21. 21. 21 Managed by UT-Battelle for the U.S. Department of Energy 21 Managed by UT-Battelle for the U.S. Department of Energy Completed Installation Memphis: 10 solar assisted stations Eaton level 2 chargers 20 kW solar PV array 3.0 kWh battery bank Shelby Farms
  22. 22. 22 Managed by UT-Battelle for the U.S. Department of Energy 22 Managed by UT-Battelle for the U.S. Department of Energy ORNL,  Q3,  Leaf   0 50 100 150 200 250 0 10 20 30 40 50 60 70 80 90 100 Frequency Percentage of EV Battery Filled per Charge (%) Percentage of Nissan Leaf Battery Filled per Charge DATA ANALYSIS AT ORNL Drivers at ORNL tend to arrive with their Leaf batteries 40% depleted
  23. 23. 23 Managed by UT-Battelle for the U.S. Department of Energy 23 Managed by UT-Battelle for the U.S. Department of Energy Locations of DC Fast Chargers in Tennessee Existing Original map overlays by Ecotality
  24. 24. 24 Managed by UT-Battelle for the U.S. Department of Energy 24 Managed by UT-Battelle for the U.S. Department of Energy Locations of DC Fast Chargers in Tennessee Existing Future Original map overlays by Ecotality
  25. 25. 25 Managed by UT-Battelle for the U.S. Department of Energy 25 Managed by UT-Battelle for the U.S. Department of Energy Project Priorities •  Add DC Fast Charging along the I-40 corridor (to NC state line) •  Add DC Fast Charging in metropolitan areas •  Add Level 2 Charging in metropolitan areas

×