  1. 1. Bar BendingBar Bending ScheduleSchedule
  2. 2. CONTENT  Introduction  B B S for different reinforced concrete structures  Measurement of bending dimensions  Do’s and Don'ts  Typical bar bending schedule  Codes , specifications and standards  Introduction  B B S for different reinforced concrete structures  Measurement of bending dimensions  Do’s and Don'ts  Typical bar bending schedule  Codes , specifications and standards
  3. 3. Bar Bending Schedule  Member identification  Bar mark  Type of steel  Diameter of bar  Length of each bar  Number of members  Number of bars in each member  Total number of bars  Total length  Shape code  Bending dimensions  Member identification  Bar mark  Type of steel  Diameter of bar  Length of each bar  Number of members  Number of bars in each member  Total number of bars  Total length  Shape code  Bending dimensions
  4. 4. BBS for RC Beams
  5. 5. BBS for RC Slabs
  6. 6. BBS for Columns and walls
  7. 7. Measurement of bending dimensions Bent-up Bar h 45o h h2 Additional Length = 0.414 h Total Length = L + 0.414 h L
  8. 8. Do’s and Don’ts  Proper accuracy  Provide cover to rein  Location of holes  Bars >36mm shall not bundled  Welding is not permitted at bends  Proper accuracy  Provide cover to rein  Location of holes  Bars >36mm shall not bundled  Welding is not permitted at bends
  9. 9. Typical BBS Calculation Example: Prepare bar bending schedule for the given beam. Clear cover = 40 mm 2-#10 #10 @ 180 c/c 2-#20 +1- #15 4000 570 2-#20 228 Longitudinal Section 1-# 15
  10. 10. Bar Bending Schedule (contd…) Example: Prepare bar bending schedule for the given beam. Clear cover = 40 mm 2-#10 (H-1) #10 @ 180 c/c 228 375 1-# 15 2-#20 (M-2) (M-1) (S-1) Cross Section
  11. 11. Bar Bending Schedule (contd…) Example: M-1 M-1 = 4000 + 2 x 228 – 2 x 40 + 2 x (18 x 20) = 5096 M-2h = 375 – 2 x 40 – 2 x 10 – 2 (15/2) = 260 M-2h = 375 – 2 x 40 – 2 x 10 – 2 (15/2) = 260 h M-2 = 4000 + 2 x 228 – 2 x 40 + (0.414 x 260) x 2 = 5091 H-1 H-1 = 4000 + 2 x 228 – 2 x 40 = 4376
  12. 12. Bar Bending Schedule (contd…) Example: Prepare bar bending schedule for the given beam. Clear cover = 40 mm Shear stirrups Number of Bars = 4000 / 180 +1 = 24 Round-up a a = 375 – 2 x 40 – 10 = 285 mm bb = 228– 2 x 40 – 10 =138 mm Total length of S-1 = 2 (138 + 285 + 18 x 10) = 1206 mm
  13. 13. Bar Bending Schedule Serial # Bar Designation Number of Bars Length of one Bar (m) Dia of bar Weight of Steel Bars Shape of Bar #10 #15 #20 1 M-1 2 5.096 20 24 2 M-2 1 4.591 15 7.2 3 H-1 2 4.376 10 6.9 4 S-1 24 1.206 10 22.7 1.05 Σ 31.1 7.6 25.2 Total Weight = 64 kg 4376 4376 4376 285138
  14. 14. CODES , SPECIFICATIONS & STANDARDS  IS:2502-1963  IS:1893-2000  SP:34  IS:456  International standard ISO:4066-1977 some websites which are proving Bar Bending Schedule Software. 1. www.eigen-tech.com/cs.html 2. www.rgsrebar.com/rebar.aspx 3. www.ensoftindia.com/prod_barbe que.htm 4. www.steelpac.co.uk/design/steelp ac_rdm... 5. www.cadsglobal.com 6. www.supercivilcd.com 7. www.technocad.co.za 8. www.BendingSchedule.com 9. www.structural- engineering.fsnet.co.uk... 10. www.continuousbeamanalysis.c om  IS:2502-1963  IS:1893-2000  SP:34  IS:456  International standard ISO:4066-1977 some websites which are proving Bar Bending Schedule Software. 1. www.eigen-tech.com/cs.html 2. www.rgsrebar.com/rebar.aspx 3. www.ensoftindia.com/prod_barbe que.htm 4. www.steelpac.co.uk/design/steelp ac_rdm... 5. www.cadsglobal.com 6. www.supercivilcd.com 7. www.technocad.co.za 8. www.BendingSchedule.com 9. www.structural- engineering.fsnet.co.uk... 10. www.continuousbeamanalysis.c om

×