January 2016
SITE C CLEAN ENERGY PROJECT
INFORMATION SHEET
ABOUT SITE C
The Site C Clean Energy Project (Site C) will be a third dam and hydroelectric generating station on the
Peace River in northeast B.C.
Site C is being built to help meet
B.C.’s long-term electricity needs.
It will provide 1,100 megawatts of
capacity, and produce about 5,100
gigawatt hours of electricity each
year — enough energy to power
the equivalent of about 450,000
homes per year.
The Site C project received
environmental approvals from the
federal and provincial
governments in October 2014. In
December 2014, the project
received approval from the
provincial government to proceed
to construction. Once built, Site C will be a source of clean, reliable and affordable electricity for more than
100 years.
Key Project Components
Construction of the Site C project started in summer 2015, with completion scheduled in 2024. Project
components include:
 Access roads and a temporary construction access bridge across the river at the dam site.
 A worker accommodation camp at the dam site.
 Upgrades to 240, 269, 271 and Old Fort Roads.
 The realignment of six segments of Highway 29.
 Two temporary cofferdams across the river to allow for construction of the earthfill dam.
 Two new 500 kilovolt transmission lines connecting Site C to the existing Peace Canyon Substation,
along an existing right-of-way.
 Shoreline protection at Hudson’s Hope, including updates to D.A. Thomas Road.
 An 800-metre roller-compacted concrete buttress to improve foundation stability and seismic protection.
 An earthfill dam, approximately 1,050 metres long and 60 metres high above the riverbed.
 A generating station with six 183 MW generating units, and spillways.
 An 83-kilometre-long reservoir that will be, on average, two to three times the width of the current river.
ABOUT SITE C
2
PO Box 2218
Vancouver BC V6B 3W2
Toll-free: 1 877 217 0777
Email: sitec@bchydro.com
www.sitecproject.com
Project Benefits
The construction and operation of the Site C project will provide significant economic, community and
environmental benefits for B.C.
 Significant increases to GDP during construction: $3.2 billion to provincial GDP, including $130
million in regional GDP.
 Thousands of jobs: Approximately 10,000 person-years of direct employment during construction;
33,000 person-years of employment in total.
 Helps meet future electricity demand: Firm energy that can be relied upon to meet electricity needs
throughout the year, and much-needed dependable capacity to meet peak instantaneous demand.
 Local government revenues: $40 million in tax revenues to local governments during construction; $2
million in revenue from grants-in-lieu and school taxes during operations.
 Community benefits: $2.4 million annually to the Peace River Regional District and its member
communities for 70 years as part of a Regional Legacy Benefits Agreement. In addition, Community
Agreements have been reached with Chetwynd and Taylor, and discussions are continuing with other
communities.
 Benefits for Aboriginal groups: Advancing opportunities for Aboriginal groups through capacity-
building and procurement, and negotiating impact benefit agreements, where appropriate.
 Lower costs and more predictable rates: Lower, more predictable costs for customers than other
energy options. The independent Joint Review Panel found that “…in the long term, Site C would
produce less expensive power than any alternative.”
 Clean energy: Among the lowest greenhouse gas emissions, per gigawatt hour, compared to other
resource options.
 Builds on existing resources: Uses water already stored behind the W.A.C. Bennett Dam to generate
about 35 per cent of the energy with only five per cent of the reservoir area.
 Integration of renewables: As a dependable and flexible resource, Site C will help integrate intermittent
renewables by quickly increasing or decreasing generation to match the output of intermittent resources
(e.g., wind, run-of-river hydro).
A Cost-Effective Resource Option
Site C has an estimated capital cost of $8.3 billion. This includes construction and development costs,
inflation, interest during construction, mitigation, First Nations accommodation and a significant contingency.
In addition, there is a $440 million project reserve held by the provincial government to protect against
unforeseen circumstances.
The project cost estimate has undergone extensive independent reviews. KPMG concluded that the
methodology used for the cost estimate and construction of the financial model was reasonable and
appropriate. An independent panel of contractors found that the estimate is sufficient for the proposed scope
and schedule of the project.
The Independent Joint Review panel found that “Site C, after an initial burst of expenditure, would lock in low
rates for many decades, and would produce fewer greenhouse gas emissions per unit of energy than any
source save nuclear.”

More Related Content

What's hot

Power Sector In Bangladesh
Power Sector In BangladeshPower Sector In Bangladesh
Power Sector In BangladeshSayanton Vhaduri
 
Decarbonising UK Energy
Decarbonising UK EnergyDecarbonising UK Energy
Decarbonising UK Energyliammacuaid
 
Plans for Egypt's First Coal-Fired Power Plant
Plans for Egypt's First Coal-Fired Power PlantPlans for Egypt's First Coal-Fired Power Plant
Plans for Egypt's First Coal-Fired Power PlantHussain al Nowais
 
Third renewable energy auction 2021
Third renewable energy auction 2021Third renewable energy auction 2021
Third renewable energy auction 2021ProColombia
 
Energy Sector of Bangladesh
Energy Sector of Bangladesh Energy Sector of Bangladesh
Energy Sector of Bangladesh Md. Rasadul Islam
 
Hydro Power Harnessing priyank
Hydro Power Harnessing priyankHydro Power Harnessing priyank
Hydro Power Harnessing priyankPRIYANK JAIN
 
Energy, Nuclear & Sustainable Power: Christopher Bowes, Nabarro
Energy, Nuclear & Sustainable Power: Christopher Bowes, NabarroEnergy, Nuclear & Sustainable Power: Christopher Bowes, Nabarro
Energy, Nuclear & Sustainable Power: Christopher Bowes, NabarroPlace North West
 
CAP and the Navajo Generating Station
CAP and the Navajo Generating StationCAP and the Navajo Generating Station
CAP and the Navajo Generating Stationen3pro
 
Michigan Energy Forum - Renewable Energy on Brownfields and Landfills - June ...
Michigan Energy Forum - Renewable Energy on Brownfields and Landfills - June ...Michigan Energy Forum - Renewable Energy on Brownfields and Landfills - June ...
Michigan Energy Forum - Renewable Energy on Brownfields and Landfills - June ...AnnArborSPARK
 
Power and energy sector of bangladesh abdullahil mamun, dba, iiuc
Power and energy sector of bangladesh  abdullahil mamun, dba, iiucPower and energy sector of bangladesh  abdullahil mamun, dba, iiuc
Power and energy sector of bangladesh abdullahil mamun, dba, iiucAbdullahil Mamun
 
On line seminar_1-problem to be addressed
On line seminar_1-problem to be addressedOn line seminar_1-problem to be addressed
On line seminar_1-problem to be addressedSHAREPROJECT
 
1509 IRENA-ADFD Project Facility presentation
1509 IRENA-ADFD Project Facility presentation1509 IRENA-ADFD Project Facility presentation
1509 IRENA-ADFD Project Facility presentationIRENAslides
 
Gcc renewable energy sector opportunity analysis
Gcc renewable energy sector opportunity analysisGcc renewable energy sector opportunity analysis
Gcc renewable energy sector opportunity analysisRajesh Sarma
 
Howdy Partner!: Heartland Expressway Association
Howdy Partner!: Heartland Expressway AssociationHowdy Partner!: Heartland Expressway Association
Howdy Partner!: Heartland Expressway AssociationPorts-To-Plains Blog
 

What's hot (20)

Power Sector In Bangladesh
Power Sector In BangladeshPower Sector In Bangladesh
Power Sector In Bangladesh
 
Decarbonising UK Energy
Decarbonising UK EnergyDecarbonising UK Energy
Decarbonising UK Energy
 
Psmp 2010
Psmp 2010Psmp 2010
Psmp 2010
 
Plans for Egypt's First Coal-Fired Power Plant
Plans for Egypt's First Coal-Fired Power PlantPlans for Egypt's First Coal-Fired Power Plant
Plans for Egypt's First Coal-Fired Power Plant
 
Third renewable energy auction 2021
Third renewable energy auction 2021Third renewable energy auction 2021
Third renewable energy auction 2021
 
Energy Sector of Bangladesh
Energy Sector of Bangladesh Energy Sector of Bangladesh
Energy Sector of Bangladesh
 
Hydro Power Harnessing priyank
Hydro Power Harnessing priyankHydro Power Harnessing priyank
Hydro Power Harnessing priyank
 
Energy Sector Opportunity Sheet_ December 2018
Energy Sector Opportunity Sheet_ December 2018Energy Sector Opportunity Sheet_ December 2018
Energy Sector Opportunity Sheet_ December 2018
 
Energy, Nuclear & Sustainable Power: Christopher Bowes, Nabarro
Energy, Nuclear & Sustainable Power: Christopher Bowes, NabarroEnergy, Nuclear & Sustainable Power: Christopher Bowes, Nabarro
Energy, Nuclear & Sustainable Power: Christopher Bowes, Nabarro
 
CAP and the Navajo Generating Station
CAP and the Navajo Generating StationCAP and the Navajo Generating Station
CAP and the Navajo Generating Station
 
Achieving a Healthy Low-Carbon Economy in Minnesota
Achieving a Healthy Low-Carbon Economy in MinnesotaAchieving a Healthy Low-Carbon Economy in Minnesota
Achieving a Healthy Low-Carbon Economy in Minnesota
 
Michigan Energy Forum - Renewable Energy on Brownfields and Landfills - June ...
Michigan Energy Forum - Renewable Energy on Brownfields and Landfills - June ...Michigan Energy Forum - Renewable Energy on Brownfields and Landfills - June ...
Michigan Energy Forum - Renewable Energy on Brownfields and Landfills - June ...
 
Power and energy sector of bangladesh abdullahil mamun, dba, iiuc
Power and energy sector of bangladesh  abdullahil mamun, dba, iiucPower and energy sector of bangladesh  abdullahil mamun, dba, iiuc
Power and energy sector of bangladesh abdullahil mamun, dba, iiuc
 
Gcc renewable power
Gcc renewable powerGcc renewable power
Gcc renewable power
 
On line seminar_1-problem to be addressed
On line seminar_1-problem to be addressedOn line seminar_1-problem to be addressed
On line seminar_1-problem to be addressed
 
1509 IRENA-ADFD Project Facility presentation
1509 IRENA-ADFD Project Facility presentation1509 IRENA-ADFD Project Facility presentation
1509 IRENA-ADFD Project Facility presentation
 
Gcc renewable energy sector opportunity analysis
Gcc renewable energy sector opportunity analysisGcc renewable energy sector opportunity analysis
Gcc renewable energy sector opportunity analysis
 
energy of bhutan
energy of bhutanenergy of bhutan
energy of bhutan
 
Power Bangladesh Expo
Power Bangladesh ExpoPower Bangladesh Expo
Power Bangladesh Expo
 
Howdy Partner!: Heartland Expressway Association
Howdy Partner!: Heartland Expressway AssociationHowdy Partner!: Heartland Expressway Association
Howdy Partner!: Heartland Expressway Association
 

Similar to Info Sheet - About Site C - January 2016_1

Preliminary plans for pumped storage at Columbia Gorge
Preliminary plans for pumped storage at Columbia GorgePreliminary plans for pumped storage at Columbia Gorge
Preliminary plans for pumped storage at Columbia GorgeNate Sandvig
 
Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...
Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...
Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...Clean Coalition
 
Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...
Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...
Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...Clean Coalition
 
Quaid‑e‑Azam Solar Park 1.pptx
Quaid‑e‑Azam Solar Park 1.pptxQuaid‑e‑Azam Solar Park 1.pptx
Quaid‑e‑Azam Solar Park 1.pptxFarooqCheema7
 
DOW Public Meeting Slides 2.5.20
DOW Public Meeting Slides 2.5.20DOW Public Meeting Slides 2.5.20
DOW Public Meeting Slides 2.5.20Heritage Wind
 
Is pumped storage on the ropes in the US?
Is pumped storage on the ropes in the US?Is pumped storage on the ropes in the US?
Is pumped storage on the ropes in the US?Nate Sandvig
 
Presentation project miel_ii
Presentation project miel_iiPresentation project miel_ii
Presentation project miel_iiProColombia
 
Energy Landscape Analysis - Texas.pdf
Energy Landscape Analysis - Texas.pdfEnergy Landscape Analysis - Texas.pdf
Energy Landscape Analysis - Texas.pdfAhmadAlkayraan
 
USACE Update - Colonel Lars Zetterstrom
USACE Update - Colonel Lars ZetterstromUSACE Update - Colonel Lars Zetterstrom
USACE Update - Colonel Lars ZetterstromTWCA
 
03/05: State Department Approval of Keystone XL Pipeline
03/05: State Department Approval of Keystone XL Pipeline03/05: State Department Approval of Keystone XL Pipeline
03/05: State Department Approval of Keystone XL Pipelineartba
 
Canada’s electricity sector reform priyank jain
Canada’s electricity sector reform priyank jainCanada’s electricity sector reform priyank jain
Canada’s electricity sector reform priyank jainPRIYANK JAIN
 
Mexico Group April 2014 with NADBank
Mexico Group April 2014 with NADBank Mexico Group April 2014 with NADBank
Mexico Group April 2014 with NADBank ftaedu
 
HVC Market: An Explainer on Widening Applications
HVC Market: An Explainer on Widening Applications HVC Market: An Explainer on Widening Applications
HVC Market: An Explainer on Widening Applications Mattdixon45
 
Tiger 2013 Awards
Tiger 2013 AwardsTiger 2013 Awards
Tiger 2013 AwardsRoar Media
 
Advancing Wisconsin's Clean Energy Future: 2014 & Beyond
Advancing Wisconsin's Clean Energy Future: 2014 & BeyondAdvancing Wisconsin's Clean Energy Future: 2014 & Beyond
Advancing Wisconsin's Clean Energy Future: 2014 & BeyondShahla Werner
 
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...Graeme Donaldson
 

Similar to Info Sheet - About Site C - January 2016_1 (20)

Preliminary plans for pumped storage at Columbia Gorge
Preliminary plans for pumped storage at Columbia GorgePreliminary plans for pumped storage at Columbia Gorge
Preliminary plans for pumped storage at Columbia Gorge
 
IMG_0002
IMG_0002IMG_0002
IMG_0002
 
Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...
Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...
Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...
 
Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...
Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...
Goleta Load Pocket Community Microgrid: Renewables-driven Resilience for the ...
 
Quaid‑e‑Azam Solar Park 1.pptx
Quaid‑e‑Azam Solar Park 1.pptxQuaid‑e‑Azam Solar Park 1.pptx
Quaid‑e‑Azam Solar Park 1.pptx
 
DOW Public Meeting Slides 2.5.20
DOW Public Meeting Slides 2.5.20DOW Public Meeting Slides 2.5.20
DOW Public Meeting Slides 2.5.20
 
Is pumped storage on the ropes in the US?
Is pumped storage on the ropes in the US?Is pumped storage on the ropes in the US?
Is pumped storage on the ropes in the US?
 
Canada Infrastructure Report 2019-2020
Canada Infrastructure Report 2019-2020Canada Infrastructure Report 2019-2020
Canada Infrastructure Report 2019-2020
 
Presentation project miel_ii
Presentation project miel_iiPresentation project miel_ii
Presentation project miel_ii
 
Energy Landscape Analysis - Texas.pdf
Energy Landscape Analysis - Texas.pdfEnergy Landscape Analysis - Texas.pdf
Energy Landscape Analysis - Texas.pdf
 
USACE Update - Colonel Lars Zetterstrom
USACE Update - Colonel Lars ZetterstromUSACE Update - Colonel Lars Zetterstrom
USACE Update - Colonel Lars Zetterstrom
 
03/05: State Department Approval of Keystone XL Pipeline
03/05: State Department Approval of Keystone XL Pipeline03/05: State Department Approval of Keystone XL Pipeline
03/05: State Department Approval of Keystone XL Pipeline
 
OmanPower&Water2017_Brochure-2
OmanPower&Water2017_Brochure-2OmanPower&Water2017_Brochure-2
OmanPower&Water2017_Brochure-2
 
Canada’s electricity sector reform priyank jain
Canada’s electricity sector reform priyank jainCanada’s electricity sector reform priyank jain
Canada’s electricity sector reform priyank jain
 
Mexico Group April 2014 with NADBank
Mexico Group April 2014 with NADBank Mexico Group April 2014 with NADBank
Mexico Group April 2014 with NADBank
 
HVC Market: An Explainer on Widening Applications
HVC Market: An Explainer on Widening Applications HVC Market: An Explainer on Widening Applications
HVC Market: An Explainer on Widening Applications
 
Tiger 2013 Awards
Tiger 2013 AwardsTiger 2013 Awards
Tiger 2013 Awards
 
Copia de case guri dam_venezuela (1)
Copia de case guri dam_venezuela (1)Copia de case guri dam_venezuela (1)
Copia de case guri dam_venezuela (1)
 
Advancing Wisconsin's Clean Energy Future: 2014 & Beyond
Advancing Wisconsin's Clean Energy Future: 2014 & BeyondAdvancing Wisconsin's Clean Energy Future: 2014 & Beyond
Advancing Wisconsin's Clean Energy Future: 2014 & Beyond
 
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
 

Info Sheet - About Site C - January 2016_1

  • 1. -more- January 2016 SITE C CLEAN ENERGY PROJECT INFORMATION SHEET ABOUT SITE C The Site C Clean Energy Project (Site C) will be a third dam and hydroelectric generating station on the Peace River in northeast B.C. Site C is being built to help meet B.C.’s long-term electricity needs. It will provide 1,100 megawatts of capacity, and produce about 5,100 gigawatt hours of electricity each year — enough energy to power the equivalent of about 450,000 homes per year. The Site C project received environmental approvals from the federal and provincial governments in October 2014. In December 2014, the project received approval from the provincial government to proceed to construction. Once built, Site C will be a source of clean, reliable and affordable electricity for more than 100 years. Key Project Components Construction of the Site C project started in summer 2015, with completion scheduled in 2024. Project components include:  Access roads and a temporary construction access bridge across the river at the dam site.  A worker accommodation camp at the dam site.  Upgrades to 240, 269, 271 and Old Fort Roads.  The realignment of six segments of Highway 29.  Two temporary cofferdams across the river to allow for construction of the earthfill dam.  Two new 500 kilovolt transmission lines connecting Site C to the existing Peace Canyon Substation, along an existing right-of-way.  Shoreline protection at Hudson’s Hope, including updates to D.A. Thomas Road.  An 800-metre roller-compacted concrete buttress to improve foundation stability and seismic protection.  An earthfill dam, approximately 1,050 metres long and 60 metres high above the riverbed.  A generating station with six 183 MW generating units, and spillways.  An 83-kilometre-long reservoir that will be, on average, two to three times the width of the current river.
  • 2. ABOUT SITE C 2 PO Box 2218 Vancouver BC V6B 3W2 Toll-free: 1 877 217 0777 Email: sitec@bchydro.com www.sitecproject.com Project Benefits The construction and operation of the Site C project will provide significant economic, community and environmental benefits for B.C.  Significant increases to GDP during construction: $3.2 billion to provincial GDP, including $130 million in regional GDP.  Thousands of jobs: Approximately 10,000 person-years of direct employment during construction; 33,000 person-years of employment in total.  Helps meet future electricity demand: Firm energy that can be relied upon to meet electricity needs throughout the year, and much-needed dependable capacity to meet peak instantaneous demand.  Local government revenues: $40 million in tax revenues to local governments during construction; $2 million in revenue from grants-in-lieu and school taxes during operations.  Community benefits: $2.4 million annually to the Peace River Regional District and its member communities for 70 years as part of a Regional Legacy Benefits Agreement. In addition, Community Agreements have been reached with Chetwynd and Taylor, and discussions are continuing with other communities.  Benefits for Aboriginal groups: Advancing opportunities for Aboriginal groups through capacity- building and procurement, and negotiating impact benefit agreements, where appropriate.  Lower costs and more predictable rates: Lower, more predictable costs for customers than other energy options. The independent Joint Review Panel found that “…in the long term, Site C would produce less expensive power than any alternative.”  Clean energy: Among the lowest greenhouse gas emissions, per gigawatt hour, compared to other resource options.  Builds on existing resources: Uses water already stored behind the W.A.C. Bennett Dam to generate about 35 per cent of the energy with only five per cent of the reservoir area.  Integration of renewables: As a dependable and flexible resource, Site C will help integrate intermittent renewables by quickly increasing or decreasing generation to match the output of intermittent resources (e.g., wind, run-of-river hydro). A Cost-Effective Resource Option Site C has an estimated capital cost of $8.3 billion. This includes construction and development costs, inflation, interest during construction, mitigation, First Nations accommodation and a significant contingency. In addition, there is a $440 million project reserve held by the provincial government to protect against unforeseen circumstances. The project cost estimate has undergone extensive independent reviews. KPMG concluded that the methodology used for the cost estimate and construction of the financial model was reasonable and appropriate. An independent panel of contractors found that the estimate is sufficient for the proposed scope and schedule of the project. The Independent Joint Review panel found that “Site C, after an initial burst of expenditure, would lock in low rates for many decades, and would produce fewer greenhouse gas emissions per unit of energy than any source save nuclear.”