Sean Cody, P.Eng
640 Nelson Road | Campbell River, BC V9H 1T7 | 250-231-3453 | seanhcody@gmail.com
CONSTRUCTION PROJECT MANAGER • CIVIL ENGINEER
Professional Engineer offering 10+ years of international experience as both a Project Manager and
Senior Field Engineer specializing in heavy civil, design-build infrastructure projects of more than $350
million. Experience from project concept through commissioning and completion; project controls;
contract administration and change management; risk management; Joint Venture partnerships;
cross-cultural and cross-functional team management of 250+ fulltime craft/staff employees.
Expertise in:
 Heavy Civil construction of Hydroelectric Power Infrastructure
 All civil works including complex cast-in-place concrete, tunneling, earthworks, infrastructure, etc.
 Design-Build Public Private Partnerships (P3)
LEADERSHIP/CHARACTER
 Manager of 250+ fulltime craft/staff employees
 Excellent business acumen
 Take-charge attitude which thrives in high pressure, multi-priority environment
 Strong/creative communicator and long-term relationship builder
 Aecon Future Leader (selected by Aecon Senior Leadership Executive Committee)
 Alkoomi Safety Leadership graduate; co-chair of Joint Health & Safety Committees
 Volunteer hockey coach of inner-city youth; varsity captain; golfer (8-handicap)
GLOBAL WORK EXPERIENCE
 Remote South, Central and North America (Venezuela, Peru, Mexico, Belize, Canada, Alaska)
 Advanced oral and written Spanish competencies
SOFTWARE PROFICIENCIES
 Primavera (P6) Professional Project Management Software
 SAP/CPM end-to-end Enterprise Resource Planning Software
 Microsoft Office Suite including Microsoft Project
 AutoCAD
PROFESSIONAL LICENSES
Professional Engineer – Province of British Columbia, Canada May 2012 – Present
Association of Professional Engineers and Geoscientist of British Columbia
Engineer in Training (EIT) – Massachusetts April 2008 – Present
NCEES Fundamentals of Engineering Exam – Passed
EDUCATION
Ivey Business School of Western University October 2013 – May 2016
London, ON Canada
Aecon Future Leaders Program
McGill University Graduated June 2006
Montreal, QC Canada
Bachelor of Engineering (Civil); Management (Minor)
PROFESSIONAL EXPERIENCE • MAJOR PROJECT HISTORY
Aecon Group Inc. – Toronto ON – Heavy Civil/Infrastructure Group (December 2011 – Present)
1. Assistant Project Manager – John Hart Generating Station Replacement Project ($1.1 billion)
Campbell River, BC Canada (July 2015 – Present)
$381 million P3 Design-Build Contract (Civil Works) – Aecon/SNC Lavalin Joint Venture
 Manage and collaborate with Construction Manager, General Superintendent, Project
Superintendents, Project Engineer, Field Engineers and subcontractors in construction of new
intake (under existing dam), underground powerhouse (3 units/132 MW), power tunnel and
tailrace tunnel (1 mile x 30 ft diameter); develop team environment with dynamic
communication where work is accomplished in an efficient, profitable and safe manner
 Establish and maintain strong relationships with Aecon Executives, Joint Venture partners,
client, owner groups, agencies, subcontractors, unions (project labour agreements), First
Nations, other shareholders, etc. and develop long-term partnerships with client base
 Supervise up to 250+ fulltime staff/craft union employees including hiring,
promotion/development and dismissal including semi-annual performance reviews
 Demonstrate sound judgement in escalating issues up chain of command
 Collaborate with off-site (Vancouver) design group to ensure design deliverables meet
budget/schedule and opportunities for value engineering are capitalized on
 Manage civil works schedule to comply with overall project schedule
 Strong command of contract/subcontract administration including high level change
management and risk management
 Forecast project revenue/costs to ensure project and corporate profitability goals are met;
present details of to-date and forecasted revenue/costs to Joint Venture board members
 Ensure accurate project tracking for continuous and measurable improvement
 Manage quarterly review of Risk and Contingency Registers
 Foster a site safety culture that supports corporate safety initiatives/goals and keeps those
working for and around the project safe
 Co-chair of Joint Health and Safety Committee
 Attend client/owner coordination meetings both at project site and in Vancouver
 Provide support for project proposals (future work)
 Present teleconference updates to company Vice Presidents and Executives
 Ensure compliance with all Aecon policies and procedures
2. Project Manager – Waneta Expansion Project ($900 million)
Trail, BC Canada (June 2014 – Feb. 2016)
$356 million Design-Build Contract (Civil Works) – Aecon/SNC Lavalin Joint Venture
In addition to responsibilities above:
 Managed remaining project works (~$42 million in cost) to successful early completion and
maximized shared revenue bonus opportunity; completion margin above objective
 Managed project close-out with client and subcontractor relationships in good standing
 Supervised up to 200+ fulltime staff/craft employees including hiring, dismissal and completion
of performance reviews with staff
 Led monthly Board Meetings between Joint Venture partners
 Led monthly mass safety meetings and onsite annual Aecon Safety Week initiatives
3. Senior Field Engineer – Waneta Expansion Project – Trail, BC (Dec. 2011 – June 2014)
$356 million Design-Build Contract (Civil Works) – Aecon/SNC Lavalin Joint Venture
 Managed up to 50 fulltime staff/craft employees on various project components
 Managed complex construction of powerhouse north wall
 Managed all shoring/falsework materials and erection on site including certification of all site-
wide falsework prior to concrete placement
 Managed tunnel transition and steel liner construction including formwork installation and
management of concrete placement
 Managed subcontractor for mechanical gates and guides installation
 Prepared job hazard analyses (JHAs) for all work areas under my supervision
 Prepared project schedules for Construction Manager approval
 Procured materials for areas under my supervision including rebar and miscellaneous metals
 Tracked costs and quantities for work areas under my supervision
 Accountable at monthly cost report meetings for work areas under my supervision
Knight Piesold Ltd. – Vancouver, BC Canada (September 2008 – December 2011)
1. Staff Engineer/Site Manager – Geotechnical Site Investigations – $250,000 to $4 million
Venezuela, Peru, Mexico, Alaska, British Columbia (October 2010 – December 2011)
 Managed drilling and geology crews (up to 12 staff/craft workers) for geotechnical and
geomechanical site investigations of various mining and hydroelectric projects
 Managed from design basis through progress meetings and final deliverables to client
 Data collection including logging of geotechnical drill core, hydraulic Lugeon testing as well as
installation of inclinometers and vibrating wire/standpipe piezometers
 Coordinated daily helicopter travel to/from remote drill sites
2. Staff Engineer/On-Site Design Representative – East Toba & Montrose Hydro Projects
$12 million, Toba Inlet, BC Canada (February 2009 – October 2010)
 Lead on-site design representative and liaison between senior design engineers (Vancouver)
and site construction managers
 QA for all civil components for construction of powerhouses, intakes and penstocks for both
projects including commissioning
 Prepared daily and monthly client QA reports
 Compiled final design and construction reports for both projects
 Managed up to 4 fulltime staff engineers
3. Staff Engineer/On-Site Design Representative – Upper Stave & Lamont Hydro Projects
$8 million, Stave Lake, BC Canada (September 2008 – January 2009)
 Assistant on-site design representative and liaison between senior design engineers
(Vancouver) and site construction managers
 Assisted in QA for all civil components (powerhouses, intakes and penstocks)
Pinnacle Site Contractors – Buzzards Bay, MA (July 2006 – August 2008)
1. Estimator (up to $2 million value) & Project Manager (up to $50,000 value)
Various Civil Projects including subdivision development, new home construction, road
construction and demolition throughout Southeastern Massachusetts and Rhode Island
 Assisted in construction management of subdivision development including road construction, lot
development, water/sewer/drainage infrastructure, landscaping and irrigation
 Permit applications and liaison with town agencies and boards of health
 Attended various networking events/initiatives to build clientele
 Quantity takeoffs of all civil project components
 Bid preparation for projects up to $2 million
REFERENCES AVAILABLE UPON REQUEST

More Related Content

What's hot

PMR Career Experience 2016
PMR Career Experience 2016PMR Career Experience 2016
PMR Career Experience 2016Pedro Rosario
 
shane Reynolds - CV Worley Parsons
shane Reynolds - CV Worley Parsonsshane Reynolds - CV Worley Parsons
shane Reynolds - CV Worley ParsonsShane Reynolds
 
B L ELKINS BOOKS 032415[1]
B L ELKINS BOOKS 032415[1]B L ELKINS BOOKS 032415[1]
B L ELKINS BOOKS 032415[1]Brian Elkins
 
Resume of ken hagan. 1
Resume of ken hagan. 1Resume of ken hagan. 1
Resume of ken hagan. 1Kenny Hagan
 
RRozek Project List 9 20 15
RRozek Project List 9 20 15RRozek Project List 9 20 15
RRozek Project List 9 20 15Roman Rozek
 
CEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final ProjectCEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final ProjectAllen Green
 
Resume 2014 without cover letter short
Resume 2014 without cover letter shortResume 2014 without cover letter short
Resume 2014 without cover letter shortLaya Hague
 
Erik D resume for Project Manager position
Erik D resume for Project Manager positionErik D resume for Project Manager position
Erik D resume for Project Manager positionErik Slaughter
 
William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro PE
 
CV 160105 Paul Magee
CV 160105 Paul MageeCV 160105 Paul Magee
CV 160105 Paul MageePaul Magee
 
Ghassan Hamati CV April 2016
Ghassan Hamati CV April 2016Ghassan Hamati CV April 2016
Ghassan Hamati CV April 2016Ghassan Hamati∴
 
J hay resume final res 2014 v dp
J hay resume final res 2014 v dpJ hay resume final res 2014 v dp
J hay resume final res 2014 v dpJonathan Hay
 
JJ Permuy Res80
JJ Permuy Res80JJ Permuy Res80
JJ Permuy Res80JJPermuy
 
Brian Rich's Resume & Portfolio
Brian Rich's Resume & PortfolioBrian Rich's Resume & Portfolio
Brian Rich's Resume & PortfolioBrian Rich
 
Civil_Structural Engineer, Graham Chambers, December 2015
Civil_Structural Engineer, Graham Chambers, December 2015Civil_Structural Engineer, Graham Chambers, December 2015
Civil_Structural Engineer, Graham Chambers, December 2015Graham Chambers
 
Reda Freiha Final Draft.doc28-Nov. 2016
Reda Freiha Final Draft.doc28-Nov. 2016Reda Freiha Final Draft.doc28-Nov. 2016
Reda Freiha Final Draft.doc28-Nov. 2016Ray Freiha
 

What's hot (20)

PMR Career Experience 2016
PMR Career Experience 2016PMR Career Experience 2016
PMR Career Experience 2016
 
shane Reynolds - CV Worley Parsons
shane Reynolds - CV Worley Parsonsshane Reynolds - CV Worley Parsons
shane Reynolds - CV Worley Parsons
 
B L ELKINS BOOKS 032415[1]
B L ELKINS BOOKS 032415[1]B L ELKINS BOOKS 032415[1]
B L ELKINS BOOKS 032415[1]
 
Logan McDowell Resume
Logan McDowell ResumeLogan McDowell Resume
Logan McDowell Resume
 
William Adams CV_N1_Jan 2016
William Adams CV_N1_Jan 2016William Adams CV_N1_Jan 2016
William Adams CV_N1_Jan 2016
 
Resume of ken hagan. 1
Resume of ken hagan. 1Resume of ken hagan. 1
Resume of ken hagan. 1
 
RRozek Project List 9 20 15
RRozek Project List 9 20 15RRozek Project List 9 20 15
RRozek Project List 9 20 15
 
CEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final ProjectCEM455 CONSTRUCTION Final Project
CEM455 CONSTRUCTION Final Project
 
Resume 2014 without cover letter short
Resume 2014 without cover letter shortResume 2014 without cover letter short
Resume 2014 without cover letter short
 
Erik D resume for Project Manager position
Erik D resume for Project Manager positionErik D resume for Project Manager position
Erik D resume for Project Manager position
 
Philip Kwiatkowski Resume
Philip Kwiatkowski ResumePhilip Kwiatkowski Resume
Philip Kwiatkowski Resume
 
William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro - 4pResumeM1
William Faoro - 4pResumeM1
 
CV 160105 Paul Magee
CV 160105 Paul MageeCV 160105 Paul Magee
CV 160105 Paul Magee
 
Ghassan Hamati CV April 2016
Ghassan Hamati CV April 2016Ghassan Hamati CV April 2016
Ghassan Hamati CV April 2016
 
CM Resume
CM Resume CM Resume
CM Resume
 
J hay resume final res 2014 v dp
J hay resume final res 2014 v dpJ hay resume final res 2014 v dp
J hay resume final res 2014 v dp
 
JJ Permuy Res80
JJ Permuy Res80JJ Permuy Res80
JJ Permuy Res80
 
Brian Rich's Resume & Portfolio
Brian Rich's Resume & PortfolioBrian Rich's Resume & Portfolio
Brian Rich's Resume & Portfolio
 
Civil_Structural Engineer, Graham Chambers, December 2015
Civil_Structural Engineer, Graham Chambers, December 2015Civil_Structural Engineer, Graham Chambers, December 2015
Civil_Structural Engineer, Graham Chambers, December 2015
 
Reda Freiha Final Draft.doc28-Nov. 2016
Reda Freiha Final Draft.doc28-Nov. 2016Reda Freiha Final Draft.doc28-Nov. 2016
Reda Freiha Final Draft.doc28-Nov. 2016
 

Viewers also liked

Viewers also liked (15)

ErinFreedmanResume2015
ErinFreedmanResume2015ErinFreedmanResume2015
ErinFreedmanResume2015
 
Erwin Reid Resume 2016-10
Erwin Reid Resume 2016-10Erwin Reid Resume 2016-10
Erwin Reid Resume 2016-10
 
DAVE ERREY RESUME INFOGRAPHIC
DAVE ERREY RESUME INFOGRAPHICDAVE ERREY RESUME INFOGRAPHIC
DAVE ERREY RESUME INFOGRAPHIC
 
Larry Querin resume 30Jan15 x
Larry Querin  resume 30Jan15 xLarry Querin  resume 30Jan15 x
Larry Querin resume 30Jan15 x
 
Dave Worth's 2016 resume
Dave Worth's 2016 resumeDave Worth's 2016 resume
Dave Worth's 2016 resume
 
Liza Alexander_Resume
Liza Alexander_ResumeLiza Alexander_Resume
Liza Alexander_Resume
 
RESUME- NEW 2014
RESUME- NEW 2014RESUME- NEW 2014
RESUME- NEW 2014
 
Todd W. Smith - Senior Sales & Marketing Professional Resume
Todd W. Smith - Senior Sales & Marketing Professional ResumeTodd W. Smith - Senior Sales & Marketing Professional Resume
Todd W. Smith - Senior Sales & Marketing Professional Resume
 
YN_CL_Resume_upd_NYNJ
YN_CL_Resume_upd_NYNJYN_CL_Resume_upd_NYNJ
YN_CL_Resume_upd_NYNJ
 
Resume - Ken Wong -20141217
Resume - Ken Wong -20141217Resume - Ken Wong -20141217
Resume - Ken Wong -20141217
 
PejmanFerdowsianResume
PejmanFerdowsianResumePejmanFerdowsianResume
PejmanFerdowsianResume
 
David Popowich Resume
David Popowich ResumeDavid Popowich Resume
David Popowich Resume
 
Toronto, ON Resume for Linkedin, 1-4-17
Toronto, ON Resume for Linkedin, 1-4-17Toronto, ON Resume for Linkedin, 1-4-17
Toronto, ON Resume for Linkedin, 1-4-17
 
S11 resume book
S11 resume bookS11 resume book
S11 resume book
 
SivaRasiah - Resume [Sept 2016]
SivaRasiah - Resume [Sept 2016]SivaRasiah - Resume [Sept 2016]
SivaRasiah - Resume [Sept 2016]
 

Similar to Experienced Civil Engineer and Construction Project Manager

Seperak, R_CSA_07044.DOC16
Seperak, R_CSA_07044.DOC16Seperak, R_CSA_07044.DOC16
Seperak, R_CSA_07044.DOC16Randy Seperak
 
Raymond Guo 2016
Raymond Guo 2016Raymond Guo 2016
Raymond Guo 2016Raymond Guo
 
Chee Wong - CV DEC2016
Chee Wong - CV DEC2016Chee Wong - CV DEC2016
Chee Wong - CV DEC2016Chee Wong
 
Wicker, L.W. July 2016
Wicker, L.W. July 2016Wicker, L.W. July 2016
Wicker, L.W. July 2016Larry Wicker
 
Mark Koenig Resume 8_16_16
Mark Koenig Resume 8_16_16Mark Koenig Resume 8_16_16
Mark Koenig Resume 8_16_16Mark Koenig
 
Ed resume 2017.docx current
Ed resume   2017.docx currentEd resume   2017.docx current
Ed resume 2017.docx currentEdward Budney
 
Dale Buzzelli Resume
Dale Buzzelli ResumeDale Buzzelli Resume
Dale Buzzelli ResumeDale Buzzelli
 
Moayad c.v version 3
Moayad c.v version 3Moayad c.v version 3
Moayad c.v version 3Moayad Qblawi
 
Steve Miller CV 2017
Steve Miller CV 2017Steve Miller CV 2017
Steve Miller CV 2017Steven Miller
 
Richard Kildea. CV October 2016
Richard Kildea. CV October 2016Richard Kildea. CV October 2016
Richard Kildea. CV October 2016Richard Kildea
 
Dominic daughtrey resume & cert
Dominic daughtrey resume & certDominic daughtrey resume & cert
Dominic daughtrey resume & certDOMINIC DAUGHTREY
 
Smith, Simon- Resume - Master
Smith, Simon- Resume - MasterSmith, Simon- Resume - Master
Smith, Simon- Resume - Mastersimon smith
 

Similar to Experienced Civil Engineer and Construction Project Manager (20)

Seperak, R_CSA_07044.DOC16
Seperak, R_CSA_07044.DOC16Seperak, R_CSA_07044.DOC16
Seperak, R_CSA_07044.DOC16
 
Bill resume
Bill resumeBill resume
Bill resume
 
Jack Oldrin RS2
Jack Oldrin RS2Jack Oldrin RS2
Jack Oldrin RS2
 
Raymond Guo 2016
Raymond Guo 2016Raymond Guo 2016
Raymond Guo 2016
 
Chee Wong - CV DEC2016
Chee Wong - CV DEC2016Chee Wong - CV DEC2016
Chee Wong - CV DEC2016
 
Wicker, L.W. July 2016
Wicker, L.W. July 2016Wicker, L.W. July 2016
Wicker, L.W. July 2016
 
Mark Koenig Resume 8_16_16
Mark Koenig Resume 8_16_16Mark Koenig Resume 8_16_16
Mark Koenig Resume 8_16_16
 
CV PM-KJH
CV PM-KJHCV PM-KJH
CV PM-KJH
 
Ed resume 2017.docx current
Ed resume   2017.docx currentEd resume   2017.docx current
Ed resume 2017.docx current
 
Dale Buzzelli Resume
Dale Buzzelli ResumeDale Buzzelli Resume
Dale Buzzelli Resume
 
Moayad c.v version 3
Moayad c.v version 3Moayad c.v version 3
Moayad c.v version 3
 
PathakA Resume
PathakA ResumePathakA Resume
PathakA Resume
 
Steve Miller CV 2017
Steve Miller CV 2017Steve Miller CV 2017
Steve Miller CV 2017
 
Steven schoenknecht 2 6 13
Steven schoenknecht 2 6 13Steven schoenknecht 2 6 13
Steven schoenknecht 2 6 13
 
Erin Kingston - CV
Erin Kingston - CVErin Kingston - CV
Erin Kingston - CV
 
Richard Kildea. CV October 2016
Richard Kildea. CV October 2016Richard Kildea. CV October 2016
Richard Kildea. CV October 2016
 
Christopher Persson CV
Christopher Persson CVChristopher Persson CV
Christopher Persson CV
 
Dominic daughtrey resume & cert
Dominic daughtrey resume & certDominic daughtrey resume & cert
Dominic daughtrey resume & cert
 
Smith, Simon- Resume - Master
Smith, Simon- Resume - MasterSmith, Simon- Resume - Master
Smith, Simon- Resume - Master
 
Ezekiel Robles Resume
Ezekiel Robles ResumeEzekiel Robles Resume
Ezekiel Robles Resume
 

Experienced Civil Engineer and Construction Project Manager

  • 1. Sean Cody, P.Eng 640 Nelson Road | Campbell River, BC V9H 1T7 | 250-231-3453 | seanhcody@gmail.com CONSTRUCTION PROJECT MANAGER • CIVIL ENGINEER Professional Engineer offering 10+ years of international experience as both a Project Manager and Senior Field Engineer specializing in heavy civil, design-build infrastructure projects of more than $350 million. Experience from project concept through commissioning and completion; project controls; contract administration and change management; risk management; Joint Venture partnerships; cross-cultural and cross-functional team management of 250+ fulltime craft/staff employees. Expertise in:  Heavy Civil construction of Hydroelectric Power Infrastructure  All civil works including complex cast-in-place concrete, tunneling, earthworks, infrastructure, etc.  Design-Build Public Private Partnerships (P3) LEADERSHIP/CHARACTER  Manager of 250+ fulltime craft/staff employees  Excellent business acumen  Take-charge attitude which thrives in high pressure, multi-priority environment  Strong/creative communicator and long-term relationship builder  Aecon Future Leader (selected by Aecon Senior Leadership Executive Committee)  Alkoomi Safety Leadership graduate; co-chair of Joint Health & Safety Committees  Volunteer hockey coach of inner-city youth; varsity captain; golfer (8-handicap) GLOBAL WORK EXPERIENCE  Remote South, Central and North America (Venezuela, Peru, Mexico, Belize, Canada, Alaska)  Advanced oral and written Spanish competencies SOFTWARE PROFICIENCIES  Primavera (P6) Professional Project Management Software  SAP/CPM end-to-end Enterprise Resource Planning Software  Microsoft Office Suite including Microsoft Project  AutoCAD PROFESSIONAL LICENSES Professional Engineer – Province of British Columbia, Canada May 2012 – Present Association of Professional Engineers and Geoscientist of British Columbia Engineer in Training (EIT) – Massachusetts April 2008 – Present NCEES Fundamentals of Engineering Exam – Passed EDUCATION Ivey Business School of Western University October 2013 – May 2016 London, ON Canada Aecon Future Leaders Program McGill University Graduated June 2006 Montreal, QC Canada Bachelor of Engineering (Civil); Management (Minor)
  • 2. PROFESSIONAL EXPERIENCE • MAJOR PROJECT HISTORY Aecon Group Inc. – Toronto ON – Heavy Civil/Infrastructure Group (December 2011 – Present) 1. Assistant Project Manager – John Hart Generating Station Replacement Project ($1.1 billion) Campbell River, BC Canada (July 2015 – Present) $381 million P3 Design-Build Contract (Civil Works) – Aecon/SNC Lavalin Joint Venture  Manage and collaborate with Construction Manager, General Superintendent, Project Superintendents, Project Engineer, Field Engineers and subcontractors in construction of new intake (under existing dam), underground powerhouse (3 units/132 MW), power tunnel and tailrace tunnel (1 mile x 30 ft diameter); develop team environment with dynamic communication where work is accomplished in an efficient, profitable and safe manner  Establish and maintain strong relationships with Aecon Executives, Joint Venture partners, client, owner groups, agencies, subcontractors, unions (project labour agreements), First Nations, other shareholders, etc. and develop long-term partnerships with client base  Supervise up to 250+ fulltime staff/craft union employees including hiring, promotion/development and dismissal including semi-annual performance reviews  Demonstrate sound judgement in escalating issues up chain of command  Collaborate with off-site (Vancouver) design group to ensure design deliverables meet budget/schedule and opportunities for value engineering are capitalized on  Manage civil works schedule to comply with overall project schedule  Strong command of contract/subcontract administration including high level change management and risk management  Forecast project revenue/costs to ensure project and corporate profitability goals are met; present details of to-date and forecasted revenue/costs to Joint Venture board members  Ensure accurate project tracking for continuous and measurable improvement  Manage quarterly review of Risk and Contingency Registers  Foster a site safety culture that supports corporate safety initiatives/goals and keeps those working for and around the project safe  Co-chair of Joint Health and Safety Committee  Attend client/owner coordination meetings both at project site and in Vancouver  Provide support for project proposals (future work)  Present teleconference updates to company Vice Presidents and Executives  Ensure compliance with all Aecon policies and procedures 2. Project Manager – Waneta Expansion Project ($900 million) Trail, BC Canada (June 2014 – Feb. 2016) $356 million Design-Build Contract (Civil Works) – Aecon/SNC Lavalin Joint Venture In addition to responsibilities above:  Managed remaining project works (~$42 million in cost) to successful early completion and maximized shared revenue bonus opportunity; completion margin above objective  Managed project close-out with client and subcontractor relationships in good standing  Supervised up to 200+ fulltime staff/craft employees including hiring, dismissal and completion of performance reviews with staff  Led monthly Board Meetings between Joint Venture partners  Led monthly mass safety meetings and onsite annual Aecon Safety Week initiatives
  • 3. 3. Senior Field Engineer – Waneta Expansion Project – Trail, BC (Dec. 2011 – June 2014) $356 million Design-Build Contract (Civil Works) – Aecon/SNC Lavalin Joint Venture  Managed up to 50 fulltime staff/craft employees on various project components  Managed complex construction of powerhouse north wall  Managed all shoring/falsework materials and erection on site including certification of all site- wide falsework prior to concrete placement  Managed tunnel transition and steel liner construction including formwork installation and management of concrete placement  Managed subcontractor for mechanical gates and guides installation  Prepared job hazard analyses (JHAs) for all work areas under my supervision  Prepared project schedules for Construction Manager approval  Procured materials for areas under my supervision including rebar and miscellaneous metals  Tracked costs and quantities for work areas under my supervision  Accountable at monthly cost report meetings for work areas under my supervision Knight Piesold Ltd. – Vancouver, BC Canada (September 2008 – December 2011) 1. Staff Engineer/Site Manager – Geotechnical Site Investigations – $250,000 to $4 million Venezuela, Peru, Mexico, Alaska, British Columbia (October 2010 – December 2011)  Managed drilling and geology crews (up to 12 staff/craft workers) for geotechnical and geomechanical site investigations of various mining and hydroelectric projects  Managed from design basis through progress meetings and final deliverables to client  Data collection including logging of geotechnical drill core, hydraulic Lugeon testing as well as installation of inclinometers and vibrating wire/standpipe piezometers  Coordinated daily helicopter travel to/from remote drill sites 2. Staff Engineer/On-Site Design Representative – East Toba & Montrose Hydro Projects $12 million, Toba Inlet, BC Canada (February 2009 – October 2010)  Lead on-site design representative and liaison between senior design engineers (Vancouver) and site construction managers  QA for all civil components for construction of powerhouses, intakes and penstocks for both projects including commissioning  Prepared daily and monthly client QA reports  Compiled final design and construction reports for both projects  Managed up to 4 fulltime staff engineers 3. Staff Engineer/On-Site Design Representative – Upper Stave & Lamont Hydro Projects $8 million, Stave Lake, BC Canada (September 2008 – January 2009)  Assistant on-site design representative and liaison between senior design engineers (Vancouver) and site construction managers  Assisted in QA for all civil components (powerhouses, intakes and penstocks)
  • 4. Pinnacle Site Contractors – Buzzards Bay, MA (July 2006 – August 2008) 1. Estimator (up to $2 million value) & Project Manager (up to $50,000 value) Various Civil Projects including subdivision development, new home construction, road construction and demolition throughout Southeastern Massachusetts and Rhode Island  Assisted in construction management of subdivision development including road construction, lot development, water/sewer/drainage infrastructure, landscaping and irrigation  Permit applications and liaison with town agencies and boards of health  Attended various networking events/initiatives to build clientele  Quantity takeoffs of all civil project components  Bid preparation for projects up to $2 million REFERENCES AVAILABLE UPON REQUEST