OEE System - Data and Analytics - Reports. Complete details of the Overall Equipment Effectiveness. OEE (Overall Equipment Effectiveness) is the gold standard for measuring manufacturing productivity.

It identifies the percentage of manufacturing time that is truly productive. An OEE score of 100% means you are manufacturing only Good Parts, as fast as possible, with no Stop Time. In the language of OEE that means 100% Quality (only Good Parts), 100% Performance (as fast as possible), and 100% Availability (no Stop Time).

Software designed and developed by Werardt Systemss Pvt. Ltd. For more information please contact Mr. Satish Nande, Director. Email business@werardt.com or CALL +91 9011092405

Published in: Data & Analytics
  • Be the first to comment

OEE System - Overall Equipment Effectiveness

  1. 1. OEE System Developed By: Werardt Systemss Pvt. Ltd.
  2. 2. Loss Type Figures Planned Hours Scheduled Hours Planned Stoppages Available Hours Performance Hours Performance Losses Effective Hours Quality Losses Legal Offs Availability Losses Losses or Wastages Top Level Figures Planned Stoppage Figures Loss Head Figures An Overview
  3. 3. KDR OEE Summary K-Brg Report An Overview A-Rate P-Rate Q-Rate OEE
  4. 4. Production Losses & OEE So Stoppages & Wastages will be – 1. Planned Stoppages 2. Availability Losses 3. Performance Losses 4. Quality Losses Planned Hours Scheduled Hours Planned Stoppages Available Hours Performance Hours Performance Losses Effective Hours Quality Losses Legal Offs Availability Losses Losses or Wastages
  5. 5. SrNo Loss Heads Loss Groups Loss Types 1 Availability Losses D Time AL:Maintenance:Electrical 2 AL:Maintenance:Mechanical 3 AL:Maintenance:Spindle Service 4 Missing Resources AL:Maintenance:System 5 AL:Material :Shared Operation 6 AL:Material :Supplier 7 AL:Operator Loss 8 Resetting AL:Resetting 9 Tooling AL:Tooling Loss 10 AL:Wheel Change 11 Performance Losses Speed Loss PL:CT Loss 12 Process Adjustment PL:Machine Adjustment 13 PL:Startup Loss 14 Quality Loss Time lost in producing Rejected pieces Loss Classification
  6. 6. SrNo Planned Stoppages 1 Zero Set plan 2 Planned Maintenance 3 Scheduled TPM 4 Project (Upgradation/Installation) 5 Major Maintenance 6 NPD (New Product Development) Planned Stoppages
  7. 7. OEE is calculated from the day wise Production data, where – Scheduled Hours = Planned Hours - Planned Stoppage Hours Available Hours = Scheduled Hours - Availability Loss Hours Performance Hours = (Produced_Qty X STD Cycle_Time) / 3600 OEE Computation A-Rate = Available Hours Scheduled Hours P-Rate = Performance Hours Available Hours Q-Rate = Produced Qty. – Rejected Qty. Produced Qty. OEE = A-Rate x P-Rate x Q-Rate
  8. 8. The OEE System Login There are 3 Roles of users who can log into the system – 1. Management Role – These users can view across all Divisions & Channels, 2. Division Role – These users can view across all Channels in their Division(s), and 3. Channel Role – These users can view related to their Channel(s) ROLES
  9. 9. The Various Menu Options Note: On every chart or table format report, you can download its Image or export it to Excel
  10. 10. The OEE Reports
  11. 11. The OEE Reports Note: You can view these charts Quarter-wise, Month-wise in a Quarter or Date-wise in a month 
  12. 12. … Contd. You can Download the charts Image by pressing this button
  13. 13. Key Data Reports
  14. 14. Channel KDR Report
  15. 15. OEE Summary Report
  16. 16. K-Brg Report Note: Though this is only Page 1, you can see the totals on every page 
  17. 17. K-Brg Report • Here we are computing based on Actual Okayed Qty, • We are considering Scheduled Hours for the computations, • So the K-Brg figure is – IF I am producing ‘X’ Qty in the Scheduled hours – then how much would I have produced in 24 Hours?
  18. 18. Loss Analysis Reports
  19. 19. Loss-Head Analysis
  20. 20. Loss-Head Analysis … Contd.
  21. 21. Loss-Group Analysis (Losses)
  22. 22. Loss-Group Analysis … Contd. … 1 Losses Downtime wise
  23. 23. Loss-Group Analysis … Contd. … 2 Losses Frequency wise
  24. 24. Loss-Group Analysis (Planned Stoppages)
  25. 25. Loss-Group Analysis … Contd. … 1 Planned Stoppages Downtime wise
  26. 26. Loss-Group Analysis … Contd. … 2 Planned Stoppages Frequency wise
  27. 27. Loss Type Analysis
  28. 28. Loss Type Analysis … Contd. … 1 Downtime wise
  29. 29. Loss Type Analysis … Contd. … 2 Frequency wise
  30. 30. Machine-wise Loss Analysis
  31. 31. Machine-wise Loss Analysis … Contd. … 1 Downtime wise
  32. 32. Machine-wise Loss Analysis … Contd. … 2 Frequency wise
  33. 33. Thank You Werardt Systemss Pvt. Ltd. Satish Nande Email business@werardt.com CALL +91 9011092405

×