Successfully reported this slideshow.
We use your LinkedIn profile and activity data to personalize ads and to show you more relevant ads. You can change your ad preferences anytime.

Katerina Papalexandri, Country Manager Greece, TAP

63 views

Published on

Athens Energy Forum 2019 | Panel Discussion 4 - Update on Regional Midstream Developments

  • Be the first to comment

  • Be the first to like this

Katerina Papalexandri, Country Manager Greece, TAP

  1. 1. Construction Progress of the Trans Adriatic Pipeline (TAP): The project’s contribution to Greece and the Region Katerina Papalexandri TAP’s Country Manager for Greece Athens Energy Forum The Challenge for Stability in the Region Panel 4: Update on regional midstream developments Grand Hyatt, Athens, 28 January 2019
  2. 2. TAP, the European leg of the Southern Gas Corridor TAP Construction Progress – January 2019 Addressing energy challenges in Europe and enhancing energy security Potential: facilitating further interconnections Diameter: 48” onshore 36” offshore Operation: built-in physical reverse flow Capacity: can expand from 10bcm/a to 20 bcm/a Length: 878km (105km offshore)
  3. 3. Overall Construction Progress 520,000 tonnes steel weight 5 main marshalling yards 5,397 km³ trench excavation 878km (105km offshore) 48’’ onshore 36’’offshore Built-in physical reverse flow 10bcm/a 20bcm/a 2 compressor stations: 45MW each 55,000 line pipes inter- connection points In GR and ALB:  100% Right of Way (RoW) cleared and graded  97% pipes in the ground  89% RoW reinstated/being reinstated TAP Construction Progress – January 2019 TAP is 84.1% complete, including all engineering, procurement & construction (end December 2018)
  4. 4. Construction Progress: Albania 4 215 km 8 BVS & 1 landfall station 1 compressor station 13,000 line pipes Figures as of XX Fier Compressor Station on schedule All 215km of RoW cleared and graded Landfall works started TAP Construction Progress – January 2019 183km of route reinstated
  5. 5. Construction Progress: Italy 5 8 km 1 pipeline receiving terminal 670 line pipes 1.5 km micro tunnel Digging the micro-tunnel pit Olive trees temporarily moved Works in the micro-tunnel area TAP Construction Progress – January 2019
  6. 6. 500km of land reinstated: ~90% 100% of pipeline welded CS in Kipoi under construction All ~550km of RoW cleared & entire pipeline strung Construction Progress: Greece 6 550 km 22 block valve stations 1 compressor station 32,000 line pipes Figures as of mid-January 2019 TAP Construction Progress – January 2019
  7. 7. TAP’s legacy in Greece: Multiple benefits 7 Financial & developmental; strategic & geopolitical; technological; socio-environmental; cultural €1.4 bn. in goods/services from ~800 companies Use & upgrade of Northern Greek ports €32 mil. in CSR programme Accommodation services at 70 hotels Protecting Cultural HeritageEmployment (~3,500), technology & expertise TAP Construction Progress – January 2019
  8. 8. @tap_pipeline Trans Adriatic Pipeline GR www.tap-ag.gr Re-instated area, activities resume. Municipality of Doxato, Drama. Kilometre point 206 of TAP’s route Thank you for your attention!

×