Given data
Total Production per Day = 400 Parts
Shift Hours = 8 Hrs
Product Weight =30 lb
Product Dimensions = 48” ×60” × 5”
01. Cycle Time
Cycle time =
Time
No of Parts
=
8×60
400
Cycle time = 1.2 Mints/Part
02. Equipment Used In the Facility
A. Pick and Place Robot: Two robots are used in the facility. One of them takes the semi
finished product from the warehouse and places on the conveyor belt. Another one picks
the finished product at the end of conveyer belt places on the industrial truck.
The Motoman CR45 is the first robot on the market to combine environmentally clean
functions with a 45lb handling capability
Brand: Motoman
Model: CR45
3
B. Conveyers
 Rolls: This are used in between the conveyor belts to transfer product from one
conveyor to another conveyor and it works on the principle of gravity
 Belt: A belt conveyor is a system of pulleys with a long loop of fabric or other
material stretched between them. Usually at least one of the pulleys is motorized to
pull the belt along with it. The product flows on the belt in entire facility from initial
part to final product.
Model: TL Heavy duty Horizontal Belt with 52’ width × 120’ length
Brand: Gilmore Kramer
C. Cranes: overhead bridge cranes with 2 ton capacity and 60 ft of span are used to load the
products to the truck at second tier supplier and unload from the truck at first tier
supplier.
Brand: Engineered material handling
Model: ELV 2
D. Industrial Truck: Industrial trucks are used to move materials over variable paths
towards the loading and unloading point.
Brand: Vestil
Model: Electric Power Pallet Truck Ept-2796-45 27x96 Forks
E. Truck: The function of the truck is to transport the product from supplier tier two to
supplier tier one
4
Brand: FORD
Model: F350
03. Cost of the Equipment
Equipment Quantity Actual Cost Total Cost
Rolls 1 $3205 $3205
Belts 3 $3623.07 $10869.21
Pick and Place Robot 2 $3,499.95 $6999.9
Cranes 2 $6000 $12000
Industrial Truck 3 $8,569.00 $25707
Truck 2 $23,995 $47990
04. Employees in the Facility
Position No of Required
Employees
Annual Average
Salary
Total Salary
President 1 $1,98,482 $1,98,482
Vice president HR 1 $1,76,152 $1,76,152
Total Cost of Equipment = $1, 06,771.1
5
Vice president
Manufacturing
1 $1,29,195 $1,29,195
Vice president
Engineering
1 $1,58,818 $1,58,818
Vice President
Marketing
1 $1,38,889 $1,38,889
Production Manager 1 $89,190 $89,190
Assembly Manager 1 $82,260 $82,260
Testing Manager 1 $72,964 $72,964
Project Manager 1 $1,13,963 $1,13,963
Assembly Engineer 4 $68,025 $2,72,100
Mechanical Engineer 4 $80,580 $3,22,320
Electronics Engineer 4 $88,661 $3,54,644
Software Engineer 4 $93,350 $3,73,400
Senior Engineers 4 $1,07,099 $4,28,396
Assistant Engineers 4 $64,008 $2,56,032
Supervisors 8 $52000 $4,16,000
Technicians 15 $54,759 $8,21,385
Workers 25 $43,409 $10,85,225
Total 81 $54, 89,415
6
05. Facility Layout
Fig_01. Layout of the Facility With 10% of Office Area
7
06. Rental Price for the Facility
Location: Denver, Colorado
Average Rate per Sq ft = $9.00
The Facility Area = 75000 Sq Ft
Total Rental Cost Per Year =75000×9
Total Rental Cost of the Facility Per Year = $6, 75,000
8
07. Total Annual Expenses
Total Cost of Equipment = $1, 06,771.1
Interest Rate of Bank loan on Equipment = 6%
Yearly expenses to pay for the bank (including Interest), a =
1,06,771.1
20
+0.06(1, 06,771.1)
(a)= $11,744.82/ year
Utility expenses / Month =$10,000
Utility expenses / Year (b) = $1, 20,000
Annual Employees salaries (c) = $54, 89,415
Annual Rent of the facility (d) =$6, 75,000
Total Annual Expenses = a+b+c+d
=11, 744.82+1, 20,000+54, 89,415+6, 75,000
Total Annual Expenses =$62,96,159.82
Total Expenses for 20 Years = $7, 55, 53, 917.84
9
Fig_02. Cash Flow diagram for 20 Years

More Related Content

What's hot

Case study 1 greetings inc. job order costing MANAGERIAL ACCOUNTING
Case study 1 greetings inc. job order costing MANAGERIAL ACCOUNTINGCase study 1 greetings inc. job order costing MANAGERIAL ACCOUNTING
Case study 1 greetings inc. job order costing MANAGERIAL ACCOUNTINGNatasha Zulkifli
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line BalancingAlan Wei Teck
 
Machines
MachinesMachines
Machinesmsarely
 
Cost Sheet of Bakery 2016(Accounting)
Cost Sheet of Bakery 2016(Accounting)Cost Sheet of Bakery 2016(Accounting)
Cost Sheet of Bakery 2016(Accounting)Prinson Rodrigues
 
Labour EFFICIENCY VARIANCE
Labour  EFFICIENCY VARIANCELabour  EFFICIENCY VARIANCE
Labour EFFICIENCY VARIANCEVivekGarg134
 
Practice topic 9 - answers (1)
Practice   topic 9 - answers (1)Practice   topic 9 - answers (1)
Practice topic 9 - answers (1)IrfanKhan679364
 
Modification and Optimization of IVD 800 - Final Review
Modification and Optimization of IVD 800 - Final ReviewModification and Optimization of IVD 800 - Final Review
Modification and Optimization of IVD 800 - Final Reviewskvcet
 
Spin plan for 80s combed yarn
Spin plan for 80s combed yarnSpin plan for 80s combed yarn
Spin plan for 80s combed yarnSwaraz Mollick
 
14 2 Use This One Work And Machines
14 2 Use This One Work And Machines14 2 Use This One Work And Machines
14 2 Use This One Work And Machinesrobtownsend
 
Machining simulation poster
Machining simulation posterMachining simulation poster
Machining simulation posterVarun Singh
 
Cost Accounting for an imaginary dairy company
Cost Accounting for an imaginary dairy companyCost Accounting for an imaginary dairy company
Cost Accounting for an imaginary dairy companyvaravindkulasekhar
 
PT scope of supply 201610
PT scope of supply 201610PT scope of supply 201610
PT scope of supply 201610Michael Schuler
 

What's hot (18)

Week 5
Week 5Week 5
Week 5
 
Case study 1 greetings inc. job order costing MANAGERIAL ACCOUNTING
Case study 1 greetings inc. job order costing MANAGERIAL ACCOUNTINGCase study 1 greetings inc. job order costing MANAGERIAL ACCOUNTING
Case study 1 greetings inc. job order costing MANAGERIAL ACCOUNTING
 
Abc classic pen
Abc classic penAbc classic pen
Abc classic pen
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line Balancing
 
Machines
MachinesMachines
Machines
 
Cost Sheet of Bakery 2016(Accounting)
Cost Sheet of Bakery 2016(Accounting)Cost Sheet of Bakery 2016(Accounting)
Cost Sheet of Bakery 2016(Accounting)
 
Labour EFFICIENCY VARIANCE
Labour  EFFICIENCY VARIANCELabour  EFFICIENCY VARIANCE
Labour EFFICIENCY VARIANCE
 
Practice topic 9 - answers (1)
Practice   topic 9 - answers (1)Practice   topic 9 - answers (1)
Practice topic 9 - answers (1)
 
Modification and Optimization of IVD 800 - Final Review
Modification and Optimization of IVD 800 - Final ReviewModification and Optimization of IVD 800 - Final Review
Modification and Optimization of IVD 800 - Final Review
 
Spin plan for 80s combed yarn
Spin plan for 80s combed yarnSpin plan for 80s combed yarn
Spin plan for 80s combed yarn
 
Workload balancing
Workload balancingWorkload balancing
Workload balancing
 
14 2 Use This One Work And Machines
14 2 Use This One Work And Machines14 2 Use This One Work And Machines
14 2 Use This One Work And Machines
 
Cost sheet
Cost sheetCost sheet
Cost sheet
 
5case
5case5case
5case
 
Machining simulation poster
Machining simulation posterMachining simulation poster
Machining simulation poster
 
Cost Accounting for an imaginary dairy company
Cost Accounting for an imaginary dairy companyCost Accounting for an imaginary dairy company
Cost Accounting for an imaginary dairy company
 
Sfm product pricing problem
Sfm product pricing problemSfm product pricing problem
Sfm product pricing problem
 
PT scope of supply 201610
PT scope of supply 201610PT scope of supply 201610
PT scope of supply 201610
 

Viewers also liked

Managing your digital presence as a PRODUCT (project management isn't enough)
Managing your digital presence as a PRODUCT (project management isn't enough)Managing your digital presence as a PRODUCT (project management isn't enough)
Managing your digital presence as a PRODUCT (project management isn't enough)David Hobbs Consulting
 
Reunión 1º infantil
Reunión 1º infantilReunión 1º infantil
Reunión 1º infantilLeire Olleta
 
How to become a privacy-Ninja : 3 first steps
How to become a privacy-Ninja : 3 first stepsHow to become a privacy-Ninja : 3 first steps
How to become a privacy-Ninja : 3 first stepsKim Elmose
 
Tipo de textos expositivos
Tipo de textos expositivosTipo de textos expositivos
Tipo de textos expositivosPoly Astete
 
Quản Trị Nhân Sự
Quản Trị Nhân SựQuản Trị Nhân Sự
Quản Trị Nhân SựT.H. Y.P
 
Residential Electricity Pricing in Canada v1.0
Residential Electricity Pricing in Canada v1.0Residential Electricity Pricing in Canada v1.0
Residential Electricity Pricing in Canada v1.0Richard Ford
 
Webinar – From Product Fixes to Customer Success – The Key is Connected Support
Webinar – From Product Fixes to Customer Success – The Key is Connected SupportWebinar – From Product Fixes to Customer Success – The Key is Connected Support
Webinar – From Product Fixes to Customer Success – The Key is Connected SupportSupport.com
 
COMO CONSEGUIR LO QUE QUIERES: Donde quieres llegar
COMO CONSEGUIR LO QUE QUIERES: Donde quieres llegarCOMO CONSEGUIR LO QUE QUIERES: Donde quieres llegar
COMO CONSEGUIR LO QUE QUIERES: Donde quieres llegarSergio Aparicio Pérez
 
Screening Commercial Aviation Passengers in the Aftermath of September 11, 2001
Screening Commercial Aviation Passengers in the Aftermath of September 11, 2001Screening Commercial Aviation Passengers in the Aftermath of September 11, 2001
Screening Commercial Aviation Passengers in the Aftermath of September 11, 2001Laura Albert
 
Densification: Infill, Norway
Densification: Infill, NorwayDensification: Infill, Norway
Densification: Infill, NorwayNordic Innovation
 
Sergio's projects F-M 2015
Sergio's projects F-M 2015Sergio's projects F-M 2015
Sergio's projects F-M 2015Sergio Jaramillo
 
Should a football team run or pass? A linear programming approach to game theory
Should a football team run or pass? A linear programming approach to game theoryShould a football team run or pass? A linear programming approach to game theory
Should a football team run or pass? A linear programming approach to game theoryLaura Albert
 
Joffreys Coffee & Tea Company Social Media Marketing Case Study
Joffreys Coffee & Tea Company Social Media Marketing Case StudyJoffreys Coffee & Tea Company Social Media Marketing Case Study
Joffreys Coffee & Tea Company Social Media Marketing Case StudyAdam Singer
 
SSD Newsletter 2016
SSD Newsletter 2016SSD Newsletter 2016
SSD Newsletter 2016Justin Bell
 

Viewers also liked (19)

Coaching de equipos
Coaching de equiposCoaching de equipos
Coaching de equipos
 
Managing your digital presence as a PRODUCT (project management isn't enough)
Managing your digital presence as a PRODUCT (project management isn't enough)Managing your digital presence as a PRODUCT (project management isn't enough)
Managing your digital presence as a PRODUCT (project management isn't enough)
 
Reunión 1º infantil
Reunión 1º infantilReunión 1º infantil
Reunión 1º infantil
 
Cosméticos
CosméticosCosméticos
Cosméticos
 
How to become a privacy-Ninja : 3 first steps
How to become a privacy-Ninja : 3 first stepsHow to become a privacy-Ninja : 3 first steps
How to become a privacy-Ninja : 3 first steps
 
Tipo de textos expositivos
Tipo de textos expositivosTipo de textos expositivos
Tipo de textos expositivos
 
Creative commons
Creative commonsCreative commons
Creative commons
 
Quản Trị Nhân Sự
Quản Trị Nhân SựQuản Trị Nhân Sự
Quản Trị Nhân Sự
 
Residential Electricity Pricing in Canada v1.0
Residential Electricity Pricing in Canada v1.0Residential Electricity Pricing in Canada v1.0
Residential Electricity Pricing in Canada v1.0
 
Webinar – From Product Fixes to Customer Success – The Key is Connected Support
Webinar – From Product Fixes to Customer Success – The Key is Connected SupportWebinar – From Product Fixes to Customer Success – The Key is Connected Support
Webinar – From Product Fixes to Customer Success – The Key is Connected Support
 
Linux
LinuxLinux
Linux
 
COMO CONSEGUIR LO QUE QUIERES: Donde quieres llegar
COMO CONSEGUIR LO QUE QUIERES: Donde quieres llegarCOMO CONSEGUIR LO QUE QUIERES: Donde quieres llegar
COMO CONSEGUIR LO QUE QUIERES: Donde quieres llegar
 
Screening Commercial Aviation Passengers in the Aftermath of September 11, 2001
Screening Commercial Aviation Passengers in the Aftermath of September 11, 2001Screening Commercial Aviation Passengers in the Aftermath of September 11, 2001
Screening Commercial Aviation Passengers in the Aftermath of September 11, 2001
 
Densification: Infill, Norway
Densification: Infill, NorwayDensification: Infill, Norway
Densification: Infill, Norway
 
Sergio's projects F-M 2015
Sergio's projects F-M 2015Sergio's projects F-M 2015
Sergio's projects F-M 2015
 
Should a football team run or pass? A linear programming approach to game theory
Should a football team run or pass? A linear programming approach to game theoryShould a football team run or pass? A linear programming approach to game theory
Should a football team run or pass? A linear programming approach to game theory
 
Octubre 1
Octubre 1Octubre 1
Octubre 1
 
Joffreys Coffee & Tea Company Social Media Marketing Case Study
Joffreys Coffee & Tea Company Social Media Marketing Case StudyJoffreys Coffee & Tea Company Social Media Marketing Case Study
Joffreys Coffee & Tea Company Social Media Marketing Case Study
 
SSD Newsletter 2016
SSD Newsletter 2016SSD Newsletter 2016
SSD Newsletter 2016
 

Similar to SAMA_RAGAVA REDDY

PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8 sho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8  sho...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8  sho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8 sho...Aquamarine Emerald
 
Body karnaphuli-report for interne
Body karnaphuli-report for interneBody karnaphuli-report for interne
Body karnaphuli-report for interneahad003
 
CIM report - final
CIM report - finalCIM report - final
CIM report - finalPraveen S R
 
1. (TCO 2) An example of a period cost is (Points 5)       ins.docx
1. (TCO 2) An example of a period cost is (Points  5)       ins.docx1. (TCO 2) An example of a period cost is (Points  5)       ins.docx
1. (TCO 2) An example of a period cost is (Points 5)       ins.docxhyacinthshackley2629
 
Industrial plants and safety project
Industrial plants and safety projectIndustrial plants and safety project
Industrial plants and safety projectNikoZurabishvili
 
Tpm implementation oee increment
Tpm implementation oee incrementTpm implementation oee increment
Tpm implementation oee incrementVinoth Axus
 
Acct 434 week 4 midterm exam(uophelp)
Acct 434 week 4 midterm exam(uophelp)Acct 434 week 4 midterm exam(uophelp)
Acct 434 week 4 midterm exam(uophelp)user3443
 
customer relation management presentation roadmap what is known and
customer relation management presentation roadmap  what is known andcustomer relation management presentation roadmap  what is known and
customer relation management presentation roadmap what is known andMohamadIbrahim86
 
Gents shirts and trousers pankaj taywade
Gents shirts and trousers  pankaj taywadeGents shirts and trousers  pankaj taywade
Gents shirts and trousers pankaj taywadeANIKET KULKARNI
 
2010 IIE/Rockwell Student Simulation Competition
2010 IIE/Rockwell Student Simulation Competition2010 IIE/Rockwell Student Simulation Competition
2010 IIE/Rockwell Student Simulation CompetitionJin-yong Yim
 
IRJET- Design and Development of Corn Chaff Peeling Machine
IRJET- Design and Development of Corn Chaff Peeling MachineIRJET- Design and Development of Corn Chaff Peeling Machine
IRJET- Design and Development of Corn Chaff Peeling MachineIRJET Journal
 
Report on Industrial attachment with HBL
Report on Industrial attachment with HBLReport on Industrial attachment with HBL
Report on Industrial attachment with HBLMd Rahamat Ullah
 

Similar to SAMA_RAGAVA REDDY (20)

Act 333
Act 333Act 333
Act 333
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8 sho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8  sho...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8  sho...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A) Lecture 8 sho...
 
Body karnaphuli-report for interne
Body karnaphuli-report for interneBody karnaphuli-report for interne
Body karnaphuli-report for interne
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM Report
CIM ReportCIM Report
CIM Report
 
Company Presentation.pptx
Company Presentation.pptxCompany Presentation.pptx
Company Presentation.pptx
 
1. (TCO 2) An example of a period cost is (Points 5)       ins.docx
1. (TCO 2) An example of a period cost is (Points  5)       ins.docx1. (TCO 2) An example of a period cost is (Points  5)       ins.docx
1. (TCO 2) An example of a period cost is (Points 5)       ins.docx
 
Costs (3).pptx
Costs (3).pptxCosts (3).pptx
Costs (3).pptx
 
Industrial plants and safety project
Industrial plants and safety projectIndustrial plants and safety project
Industrial plants and safety project
 
Tpm implementation oee increment
Tpm implementation oee incrementTpm implementation oee increment
Tpm implementation oee increment
 
Acct 434 week 4 midterm exam(uophelp)
Acct 434 week 4 midterm exam(uophelp)Acct 434 week 4 midterm exam(uophelp)
Acct 434 week 4 midterm exam(uophelp)
 
customer relation management presentation roadmap what is known and
customer relation management presentation roadmap  what is known andcustomer relation management presentation roadmap  what is known and
customer relation management presentation roadmap what is known and
 
Gents shirts and trousers pankaj taywade
Gents shirts and trousers  pankaj taywadeGents shirts and trousers  pankaj taywade
Gents shirts and trousers pankaj taywade
 
Riv2
Riv2Riv2
Riv2
 
UNIT 3 PPCE.pptx
UNIT 3 PPCE.pptxUNIT 3 PPCE.pptx
UNIT 3 PPCE.pptx
 
2010 IIE/Rockwell Student Simulation Competition
2010 IIE/Rockwell Student Simulation Competition2010 IIE/Rockwell Student Simulation Competition
2010 IIE/Rockwell Student Simulation Competition
 
IRJET- Design and Development of Corn Chaff Peeling Machine
IRJET- Design and Development of Corn Chaff Peeling MachineIRJET- Design and Development of Corn Chaff Peeling Machine
IRJET- Design and Development of Corn Chaff Peeling Machine
 
Final adu
Final aduFinal adu
Final adu
 
Report on Industrial attachment with HBL
Report on Industrial attachment with HBLReport on Industrial attachment with HBL
Report on Industrial attachment with HBL
 

SAMA_RAGAVA REDDY

  • 1. 1
  • 2. 2 Given data Total Production per Day = 400 Parts Shift Hours = 8 Hrs Product Weight =30 lb Product Dimensions = 48” ×60” × 5” 01. Cycle Time Cycle time = Time No of Parts = 8×60 400 Cycle time = 1.2 Mints/Part 02. Equipment Used In the Facility A. Pick and Place Robot: Two robots are used in the facility. One of them takes the semi finished product from the warehouse and places on the conveyor belt. Another one picks the finished product at the end of conveyer belt places on the industrial truck. The Motoman CR45 is the first robot on the market to combine environmentally clean functions with a 45lb handling capability Brand: Motoman Model: CR45
  • 3. 3 B. Conveyers  Rolls: This are used in between the conveyor belts to transfer product from one conveyor to another conveyor and it works on the principle of gravity  Belt: A belt conveyor is a system of pulleys with a long loop of fabric or other material stretched between them. Usually at least one of the pulleys is motorized to pull the belt along with it. The product flows on the belt in entire facility from initial part to final product. Model: TL Heavy duty Horizontal Belt with 52’ width × 120’ length Brand: Gilmore Kramer C. Cranes: overhead bridge cranes with 2 ton capacity and 60 ft of span are used to load the products to the truck at second tier supplier and unload from the truck at first tier supplier. Brand: Engineered material handling Model: ELV 2 D. Industrial Truck: Industrial trucks are used to move materials over variable paths towards the loading and unloading point. Brand: Vestil Model: Electric Power Pallet Truck Ept-2796-45 27x96 Forks E. Truck: The function of the truck is to transport the product from supplier tier two to supplier tier one
  • 4. 4 Brand: FORD Model: F350 03. Cost of the Equipment Equipment Quantity Actual Cost Total Cost Rolls 1 $3205 $3205 Belts 3 $3623.07 $10869.21 Pick and Place Robot 2 $3,499.95 $6999.9 Cranes 2 $6000 $12000 Industrial Truck 3 $8,569.00 $25707 Truck 2 $23,995 $47990 04. Employees in the Facility Position No of Required Employees Annual Average Salary Total Salary President 1 $1,98,482 $1,98,482 Vice president HR 1 $1,76,152 $1,76,152 Total Cost of Equipment = $1, 06,771.1
  • 5. 5 Vice president Manufacturing 1 $1,29,195 $1,29,195 Vice president Engineering 1 $1,58,818 $1,58,818 Vice President Marketing 1 $1,38,889 $1,38,889 Production Manager 1 $89,190 $89,190 Assembly Manager 1 $82,260 $82,260 Testing Manager 1 $72,964 $72,964 Project Manager 1 $1,13,963 $1,13,963 Assembly Engineer 4 $68,025 $2,72,100 Mechanical Engineer 4 $80,580 $3,22,320 Electronics Engineer 4 $88,661 $3,54,644 Software Engineer 4 $93,350 $3,73,400 Senior Engineers 4 $1,07,099 $4,28,396 Assistant Engineers 4 $64,008 $2,56,032 Supervisors 8 $52000 $4,16,000 Technicians 15 $54,759 $8,21,385 Workers 25 $43,409 $10,85,225 Total 81 $54, 89,415
  • 6. 6 05. Facility Layout Fig_01. Layout of the Facility With 10% of Office Area
  • 7. 7 06. Rental Price for the Facility Location: Denver, Colorado Average Rate per Sq ft = $9.00 The Facility Area = 75000 Sq Ft Total Rental Cost Per Year =75000×9 Total Rental Cost of the Facility Per Year = $6, 75,000
  • 8. 8 07. Total Annual Expenses Total Cost of Equipment = $1, 06,771.1 Interest Rate of Bank loan on Equipment = 6% Yearly expenses to pay for the bank (including Interest), a = 1,06,771.1 20 +0.06(1, 06,771.1) (a)= $11,744.82/ year Utility expenses / Month =$10,000 Utility expenses / Year (b) = $1, 20,000 Annual Employees salaries (c) = $54, 89,415 Annual Rent of the facility (d) =$6, 75,000 Total Annual Expenses = a+b+c+d =11, 744.82+1, 20,000+54, 89,415+6, 75,000 Total Annual Expenses =$62,96,159.82 Total Expenses for 20 Years = $7, 55, 53, 917.84
  • 9. 9 Fig_02. Cash Flow diagram for 20 Years