Benchmarking Project Health:
Enhancing Confidence, Assuring Delivery
An exploration of the practical application of Risk and Cost
audit models to benchmark project (and business) health
and improve forecast cost and schedule out-turn
Project Controls Expo – 18th Nov 2014
Emirates Stadium, London
© QinetiQ Limited 2014 QinetiQ Proprietary
2
About the Speakers
Steve Elwell BSc (Hons) MBA
Director: Strategic Advisory Services
Steve is a highly experienced director who has built a strong reputation for
implementing complex programmes that involve significant change. He has
considerable defence acquisition experience, having managed programmes across a
range of industries. He specialises in development of output-based models and
economic modelling solutions focused on continuous performance improvement.
Mark Lee BSc MBA CEng MIET MIMechE MCMI
Head of Profession (Risk & Programme Assurance): Strategic Advisory Services
Mark’s risk and project management experience spans Maritime, Air, Land and
Weapons. His career has taken him across Europe and as far afield as Canada, India
and Australia. Mark leads a team of risk, project and programme management
specialists and is QinetiQ’s lead practitioner in Risk Maturity Assessment.
© QinetiQ Limited 2014 QinetiQ Proprietary
3
Objectives
1. Introduce the principles of risk and cost maturity assessment
• Why a mature approach is important to cost (and schedule) control
2. Explore and explain the QinetiQ Maturity Models
• Context and history: development of the models
• Construct and scope
• Why these particular models offers advantage to projects and businesses
• How they are applied in practice to benchmark projects and organisations
3. Demonstrate the value of QinetiQ’s Maturity Models in application
• Summary case examples from Defence and Oil & Gas
© QinetiQ Limited 2014 QinetiQ Proprietary
• Formed in 2001 from Defence Evaluation and Research Agency (DERA)
• FTSE 250 - £1.3bn market capitalisation
• 6,233 people worldwide, with ~1,100 specialists in weapons and testing
• Member of The 5% Club – investing in graduates and apprentices
• 37 sites across the UK – from Cape Wrath to Shoeburyness
• 95% of QinetiQ’s UK employees hold national security clearance
• 25 year Long Term Partnering Agreement (LTPA) with MOD, signed in 2006
• Empire Test Pilots’ School (ETPS) – training flight test professionals for 70 years
• More than 1,500 patents granted, 1,000 patents pending
• 75 years of test and evaluation at Aberporth, Wales
4
© QinetiQ Limited 2014 QinetiQ Proprietary
StrategicAdvisory
Services
5
Procurement
Advisory Services
Commerce Decisions (AWARDTM)
BusinessAnalysis
CostEngineering
Risk&Programme
Assurance
Requirements
Acceptance
ThroughLifeServices
© QinetiQ Limited 2014 QinetiQ Proprietary
6
Why is Risk and Cost Maturity Important?
Examples of ‘Failed’ Commercial Projects
Scottish Parliament
Forecast: £10-40m and 2001 opening
Actual: £414m and 2004 opening
Thermae Bath Spa
Forecast: £13m and 2002 opening
Actual: £45m and 2006 opening
Source: Wikimedia.org
Source: Wikipedia.org
© QinetiQ Limited 2014 QinetiQ Proprietary
7
Why is Risk and Cost Maturity Important?
Audit Evidence from Defence
Source data: NAO Major Projects Report 2013
700
600
500
400
300
200
100
0
£m
Ships Combat Air Submarines Helicopters Air Support Information Land ISTAR Weapons
Systems Support Equipment
0 0
Defence – average cost growth across all 73 projects in the ships, combat air and submarine sectors
Average cost over-run = £18m per project
© QinetiQ Limited 2014 QinetiQ Proprietary
8
Why is Risk and Cost Maturity Important?
Avoiding the News Headlines!
“BBC Chief Technology Officer sacked over failed
£100m Digital Media Initiative”
“A major £12m scheme to
digitise patient records has so
far failed to deliver and is now
expected to cost the Health
Department double its original
budget, according to the Public
Accounts Committee”
“Canadian provincial health officials fire
prime contractor after the firm missed 3
years of deadlines and failed to deliver the
province’s flagship online medical registry”
“Sacked bursar loses claim for unfair dismissal
over school’s £2.5m expansion project”
“Environment Minister demoted after bungled $2.4bn home insulation fiasco”
Source: Pressgazette.co.uk
© QinetiQ Limited 2014 QinetiQ Proprietary
9
Why Does This Happen?
Dealing with Uncertainty
All projects have uncertainties and changing variables, arising from …
• Budget changes
• Schedule changes
• Requirement changes
• Omissions and errors
• Failure to tackle risk at source
• Things that “just go wrong”
“…… because as we know, there are known knowns; there are things we know we know.
We also know there are known unknowns; that is to say we know there are some things
we do not know. But there are also unknown unknowns - the ones we don't know we
don't know” Donald Rumsfeld
Source: Wikimedia.org
© QinetiQ Limited 2014 QinetiQ Proprietary
QinetiQ Risk Maturity Model (QRMM)
A Brief History …
• Developed by QinetiQ (1999) to improve confidence by objectively assessing risk management
maturity
• Referenced to and compliant with
― MOD’s Acquisition Operating Framework (AOF)
― Project risk management best practice – APM Project Risk Analysis and Management (PRAM) Guide
― Combined Code (‘Turnbull Guidance’) for UK Corporate Governance – Financial Reporting Council
• Proven capability and value in application over 15 years
― Over £75bn of Defence projects/programmes (across all domains) assessed … and counting
― Also deployed in Oil & Gas (FTSE 100 multi-national), Rail and Manufacturing
• QinetiQ analysis of NAO Major Projects Reports has indicated that RMM can
― Increase confidence in project success through improved cost/schedule adherence
― Deliver forecast improvement in schedule and cost out-turn on major projects
11
© QinetiQ Limited 2014 QinetiQ Proprietary
Control of Risk Management Maturity
Schedule Impact – QinetiQ Analysis of NAO Data
Current Schedule Performance vs Original Forecast of MOD Top 20 Major Projects
41%
46%
114%
47%
32%
51%
63%
54% 53%
42%
75%
8%
10%
0% 0% 0%
11%
0%
0%
20%
40%
60%
80%
100%
120%
Typhoon(Nov-87)
StingRay(May-95)
NimrodMRA4(Jul-96)
AstuteClassSub(Mar-
97)
A400M(May-00)
Type45Destroyer(Jul-
00)
SupportVehicle(Nov-01)
NGLAAW(May-02)
Terrier(Jul-02)
NavalEHF/SHFSat
Comms(Aug-03)
Soothsayer(Aug-03)
MTADS(Sep-04)
Watchkeeper(Jul-05)
Falcon(Mar-06)
Merlin(Mar-06)
FutureLynx(Jun-06)
AdvancedJetTrainer
(Aug-06)
TyphoonFuture
Capability(Jan-07)
Scheduleoverrunas%oforiginalforecast
Risk Maturity Uncontrolled Risk Maturity @ Level 3+
Forecast schedule
overrun calculated from
the summary of post-
Main Gate projects in
NAO Major Projects
Reports
Many factors affect
projects, but those with
risk maturity applied at
all CADMID stages are
more aware of issues and
have mitigations in place
to respond to those risks
Major projects from the
NAO reports with risk
maturity applied are
statistically less likely to
experience schedule
overruns
Schedule Performance vs Original Forecast of MOD Major Projects
Source data: NAO Major Projects Reports
12
Average schedule
over-run = 56%
Average schedule
over-run = 4%
© QinetiQ Limited 2014 QinetiQ Proprietary
Control of Risk Management Maturity
Cost Impact – QinetiQ Analysis of NAO Data
Forecast cost overrun
calculated from the
summary of post-Main
Gate projects in NAO
Major Projects Reports
Projects with Risk
Maturity applied
experience less budget
volatility (overspend or
underspend), compared
with projects whose level
of risk maturity is
uncontrolled
Current Schedule Performance vs Original Forecast of MOD Top 20 Major Projects
-21%
28%
48%
0%
29%
-7%
-18%
6%
-26%
42%
-7%
-1%
-5%
-1%
1%
-5%
-2%
-30%
-20%
-10%
0%
10%
20%
30%
40%
50%
Typhoon(Nov-87)
StingRay(May-95)
NimrodMRA4(Jul-96)
AstuteClassSub(Mar-
97)
A400M(May-00)
Type45Destroyer(Jul-
00)
SupportVehicle(Nov-01)
NGLAAW(May-02)
Terrier(Jul-02)
NavalEHF/SHFSat
Comms(Aug-03)
Soothsayer(Aug-03)
MTADS(Sep-04)
Watchkeeper(Jul-05)
Falcon(Mar-06)
Merlin(Mar-06)
FutureLynx(Jun-06)
AdvancedJetTrainer
(Aug-06)
TyphoonFuture
Capability(Jan-07)
Currentoverspendas%oforiginalforecast
Risk Maturity Uncontrolled Risk Maturity @ Level 3+
Budget Performance vs Original Forecast of MOD Major Projects
Source data: NAO Major Projects Reports
13
Average cost
overspend = 8%
Average cost
underspend = 3%
© QinetiQ Limited 2014 QinetiQ Proprietary
QRMM as an Enabler to Better Project Management
• Assesses and benchmarks the quality and consistency of risk management implementation
• Improves confidence in the ability to predict and deliver against schedule and cost
• Establishes an independent, objective and evidence-based baseline measure of risk maturity
• Identifies strengths and weaknesses in risk management process and its enablers
• Supports formulation of a prioritised ‘roadmap’ of improvement actions against the baseline
• Supports identification of common issues across projects, to help tackle risk at source
• Facilitates sharing of good practice within and across business units
• Builds confidence in the quality of underpinning data (e.g. for Business Cases)
• Scalable: applicable at all levels, at all points in the project/business lifecycle
• Can be used to support supplier assessment
14
© QinetiQ Limited 2014 QinetiQ Proprietary
QRMM Construct – Top Level Output
Risk Maturity Assessment
Stakeholders Risk
Identification
Risk Analysis Risk
Mitigation
Project
Management
Culture
Current
Maturity
Potential
Improvement
Level 4 -
Natural
Level 3 -
Normalised
Level 2 -
Novice
Level 1 -
Naive
“An organisation is only as strong as its weakest element”
16
© QinetiQ Limited 2014 QinetiQ Proprietary
QRMM in Application
Empirical Assessment Process
Review
Documentary
Evidence Audit
Conduct RMA
Workshop
Analyse and
Report Results
Implement
Improvement Plan
RMA Benchmark
(Level 1 to 4)
Periodic re-assessment against current benchmark
17
© QinetiQ Limited 2014 QinetiQ Proprietary
QRMM in Application
Example Analysis Outputs
Stakeholders
Risk Identification
Risk Analysis
Risk Responses
Project Management
Culture
Category1 Category2
Level 1 Level 2 Level 3 Level 4
Level of maturity after
20
© QinetiQ Limited 2014 QinetiQ Proprietary
QRMM in Application
Case Examples from Defence – Case 1
• Portfolio of 4 projects, with QinetiQ contracted by MOD to
− Formulate and deliver a formal Risk Improvement Programme: April-Aug 2011
− Conduct a repeat RMA in February 2014 to identify current baseline and improvements
• April 2011 status of each project
− Project A – in-service project undergoing contract change, with risk transfer to industry
− Project B – mature equipment, in-service until ~2020, with industry managing risk
− Project C – in Assessment Phase (AP) [due to be placed on contract in 2014]
− Project D – complex international project, in AP [cleared MOD Main Gate in 2014]
Project Measured RMA
April 2011
Measured RMA
July 2011
Measured RMA
February 2014
Forecast RMA
Project A Level 1 Level 2 Level 2 Level 3
Project B Level 3 Level 3 Level 3 Level 4
Project C Level 1 Level 2 Level 3 Level 3
Project D Level 1 Level 2 Level 4 Level 4
21
© QinetiQ Limited 2014 QinetiQ Proprietary
QRMM in Application
Case Examples from Defence – Case 1
Perspective Number of Projects at Each Level – Feb ‘14
Level 2 Level 3 Level 4
Stakeholders √ √ √ √
Risk Identification √ √ √ √
Risk Analysis √ √ √ √
Risk Responses √ √ √ √
Project Management √ √ √ √
Culture √ √ √ √
• February 2014 forward improvement plans, focused to achieve
— Project A: from high L2 (almost L3) to weak L3 in 3 months, consolidating to a firm L3
— Project B: from high L3 to a weak L4, consolidating to a firm L4 through secondary actions
— Project C: from weak L3 (with risk of slipping back to L2) to a firm L3
— Project D: from weak L4 (risk of slipping back to L3) to a firm L4
• A good example of where focused MOD effort, and periodic RMA, can enhance risk execution
22
© QinetiQ Limited 2014 QinetiQ Proprietary
Current Schedule Performance vs Original Forecast of MOD Top 20 Major Projects
-21%
28%
48%
0%
29%
-7%
-18%
6%
-26%
42%
-7%
-1%
-5%
-1%
1%
-5%
-2%
-30%
-20%
-10%
0%
10%
20%
30%
40%
50%
Typhoon(Nov-87)
StingRay(May-95)
NimrodMRA4(Jul-96)
AstuteClassSub(Mar-
97)
A400M(May-00)
Type45Destroyer(Jul-
00)
SupportVehicle(Nov-01)
NGLAAW(May-02)
Terrier(Jul-02)
NavalEHF/SHFSat
Comms(Aug-03)
Soothsayer(Aug-03)
MTADS(Sep-04)
Watchkeeper(Jul-05)
Falcon(Mar-06)
Merlin(Mar-06)
FutureLynx(Jun-06)
AdvancedJetTrainer
(Aug-06)
TyphoonFuture
Capability(Jan-07)
Currentoverspendas%oforiginalforecast
Risk Maturity Uncontrolled Risk Maturity @ Level 3+
QRMM in Application
Case Examples from Defence – Case 2 (MOD 1*)
Stakeholders
Risk Identification
Risk Analysis
Risk Responses
Project Management
Culture
Category1 Category2
Level 1 Level 2 Level 3 Level 4
Level of maturity after
• Level 1 across all 6 perspectives – the worst ever RMA score recorded by QinetiQ!
• Risk improvement roadmap established to target
— Level 2 in 3 months (22 actions)
— Level 3 in a further 9 months (16 actions)
Source: MoD
23
© QinetiQ Limited 2014 QinetiQ Proprietary
QRMM in Application
Case Examples from Defence – Case 2 (MOD 1*)
• Improvements were not implemented, due to
— Lack of capacity within MOD to implement the plan
— Conflicting demands and changing priorities
— Ongoing organisational uncertainty
— Realisation that implementation of improvements at 1* level would be insufficient
• QinetiQ was then requested to
— Formulate a transformation programme covering the 2* group (4 x 1* units)
— Develop and roll-out improvements to enhance risk and cost management and control
• What happened next?
• MOD secured stakeholder buy-in to implement the ~18 month transformation programme
• In-FY underspend was secured to fund the initial phase
• Other areas developed an interest in improving their risk and cost maturity
• A good example of where a localised RMA can uncover a need for wider risk/cost improvement
Source: MoD
24
© QinetiQ Limited 2014 QinetiQ Proprietary
QRMM in Application
Example Transformation Programme – Benefits Realisation
Forecast Risk
Maturity
(left-hand scale)
Phase 1 Phase 3Phase 2
Potential for Schedule/Cost
Overrun
(right-hand scale)
Naïve (Level 1)
 Risk process flawed
 No real value-add
Novice (Level 2)
 Risk process influencing decisions
 Risk process adding value
 Improving performance against objectives
 Some process/implementation weaknesses
 Potential for significant unrealised benefits
Normalised (Level 3)
 Risk process formalised
 Process implemented systematically
 Effective risk responses executed
 Sources of uncertainty under control
 Significant value-add
Natural (Level 4)
 Risk process informing
strategic choices
 Sources of uncertainty
managed systematically
 Risk culture conducive to
maximising outcomes
Level 1
Level 4
Level 3
Level 2
RiskMaturityLevel
0-10%
100%+
60-99%
11-
60%
Schedule/CostOverrun
(asa%ofbaselineschedule/budget)
25
© QinetiQ Limited 2014 QinetiQ Proprietary
QRMM in Application
Case Example from Oil & Gas
• 2011: FTSE 100 Oil & Gas multi-national approached QinetiQ to pilot an RMA on a UK project
• QinetiQ amended the RMA framework Q&A set to reflect O&G-specific language
− Underlying model and algorithms were unchanged
• The pilot was conducted on the UK project
− Identified that lack of risk disclosure from the JV partner was a significant threat
− RMA was extremely well received by the client organisation
− Actions to address the shortfalls were apparently not progressed
− There were serious repercussions for both JV partners
• A good example where failure to address risk maturity shortfalls can impact business health
• What happened next?
− QinetiQ undertook a further RMA on an operation in Asia, on completion of the UK pilot
− The Asia RMA identified significant pockets of good practice to share across the company
− QinetiQ was requested to develop a new corporate Cost & Schedule Risk Analysis standard
Source: Wikipedia.org
26
© QinetiQ Limited 2014 QinetiQ Proprietary
QinetiQ Cost Engineering Health Check (CEHC)
• Developed by QinetiQ as its second maturity assessment tool (following the success of the
QRMM)
− Reflecting the need to enhance confidence in the quality and accuracy of cost estimates
− Recognising that poor quality cost estimates can undermine reasoned decision-making
− Addressing the desire to benchmark cost engineering capability against peer organisations
− Reflecting the increased emphasis on robust cost management in austerity
“ The Cost Engineering Healthcheck (CEHC) was a professionally facilitated workshop
and the results will guide the future direction of capability development for the cost
community in the EACE Working Group”
David Lewis – European Aerospace Cost Engineering (EACE) Chairman
27
© QinetiQ Limited 2014 QinetiQ Proprietary
CEHC Construct – Top Level Output
Cost Engineering Health Check
Data Tools People Processes Culture Stakeholders
Categories
Level
Naive
Novice
Optimised
Natural
Normalised
Identification of weak categories
29
© QinetiQ Limited 2014 QinetiQ Proprietary
CEHC in Application
Case Example - Comparisons Between Defence and Space
0%
20%
40%
60%
80%
100%
Naïve Novice Normalised Natural Optimised
Respondants
SCAF
EACE
Software Estimating
The space community would
seem to be more mature in the
ability to estimate software
costs compared to the defence
community
Both groups could benefit from
more activity in this area to
increase their maturity
30
© QinetiQ Limited 2014 QinetiQ Proprietary
CEHC in Application
Case Example - Comparisons Between Defence and Space
0%
20%
40%
60%
80%
100%
Naïve Novice Normalised Natural Optimised
Respondants
SCAF
EACE
Application of Multiple Estimating Methodologies
The space community could learn from the defence cost
community in how to apply alternative cost estimating
methodologies (analytical, parametric and analogous) to
increase confidence in the outputs they generate
32
© QinetiQ Limited 2014 QinetiQ Proprietary
CEHC in Application
Benefits
• Assesses the quality and consistency of cost engineering implementation
• Provides evidence of weaknesses in the cost engineering capability of an organisation
• Establishes a focus for cost engineering improvement, either alone or as part of a wider
change initiative
• Delivers improved capability in
− The ability to forecast acquisition and support/ownership costs
− The understanding of costs and their impact across the enterprise
− Alignment and coherency … and the ability to identify and share good practice
• Enhances confidence
− For decision-makers, that their decisions are based on credible and justifiable financial
information
− In the robustness, accuracy and reliability of cost estimates
− In the ability of cost estimates to withstand financial scrutiny and audit
− In the potential for a project or business to increase its competitive edge and deliver more for
less
33
© QinetiQ Limited 2014 QinetiQ Proprietary
Summary
1. Introduce the principles and importance of risk and cost maturity assessment
− There is inherent uncertainty in all projects, programmes and businesses
− Formalised risk and cost management help us understand and respond to uncertainty
− Control of risk and cost maturity is a key enabler to good project management
2. Explore QinetiQ Risk Maturity Model (QRMM) and Cost Engineering Healthcheck (CEHC)
− Audits and benchmarks project health and focuses improvement initiatives
− Enhances confidence in the likelihood of an out-turn to schedule and within budget
− Enables us to more confidently establish our risk appetite and inform strategic choice
3. Demonstrate value of QRMM and CEHC in application
− Case 1 – focused improvement and periodic re-assessment enhanced project control
− Case 2 – localised RMA can trigger wider imperative to enhance risk management
− Case 3 – failure to address risk maturity improvement can impact business health
− Case 4 – use of CEHC to compare cost engineering maturity across industries
Source: Pressgazette.co.uk
34
© QinetiQ Limited 2014 QinetiQ Proprietary
www.QinetiQ.com

More Related Content

Similar to Benchmarking Project Health with Risk and Cost Models

Generic slides: AMEC in the Middle East, Africa and CIS
Generic slides: AMEC in the Middle East, Africa and CISGeneric slides: AMEC in the Middle East, Africa and CIS
Generic slides: AMEC in the Middle East, Africa and CISZhenya85
 
The ORE Catapult and Future Opportunities,David Arnold,Technology strategy Board
The ORE Catapult and Future Opportunities,David Arnold,Technology strategy BoardThe ORE Catapult and Future Opportunities,David Arnold,Technology strategy Board
The ORE Catapult and Future Opportunities,David Arnold,Technology strategy BoardInvest Northern Ireland
 
Intertek - Industry Services
Intertek - Industry ServicesIntertek - Industry Services
Intertek - Industry Servicesogonzalez1997
 
Introduction to the Revised UK Offshore Safety Legislation as Impacted by the...
Introduction to the Revised UK Offshore Safety Legislation as Impacted by the...Introduction to the Revised UK Offshore Safety Legislation as Impacted by the...
Introduction to the Revised UK Offshore Safety Legislation as Impacted by the...Lloyd's Register Energy
 
DLV2000 Press Event Presentation_RMEDIA
DLV2000 Press Event Presentation_RMEDIADLV2000 Press Event Presentation_RMEDIA
DLV2000 Press Event Presentation_RMEDIARichard Goins
 
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo
 
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
4 sarah nightingale decc offshore wind seminar 18 19  march 20144 sarah nightingale decc offshore wind seminar 18 19  march 2014
4 sarah nightingale decc offshore wind seminar 18 19 march 2014NaturalEngland
 
Detailed Resume For Bryan Hill Oct 09
Detailed Resume For Bryan Hill Oct 09Detailed Resume For Bryan Hill Oct 09
Detailed Resume For Bryan Hill Oct 09Bryan_Hill
 
SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...
SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...
SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...Diego Berazategui
 
Allan g hardy cv feb 2020_master
Allan g hardy cv feb 2020_masterAllan g hardy cv feb 2020_master
Allan g hardy cv feb 2020_masterAllan Hardy
 
Intertek - Industry Services 2013
Intertek - Industry Services 2013Intertek - Industry Services 2013
Intertek - Industry Services 2013ogonzalez1997
 
Partnering to deliver an integrated programme at AWE presented by AWE, 23 Nov...
Partnering to deliver an integrated programme at AWE presented by AWE, 23 Nov...Partnering to deliver an integrated programme at AWE presented by AWE, 23 Nov...
Partnering to deliver an integrated programme at AWE presented by AWE, 23 Nov...Association for Project Management
 
MaC Group Renewables Corporate Presentation January 2015 Printable
MaC Group Renewables Corporate Presentation January 2015 PrintableMaC Group Renewables Corporate Presentation January 2015 Printable
MaC Group Renewables Corporate Presentation January 2015 PrintableGrant Greatrex
 
Develop Training brochure.PDF
Develop Training brochure.PDFDevelop Training brochure.PDF
Develop Training brochure.PDFMichael Bentil
 

Similar to Benchmarking Project Health with Risk and Cost Models (20)

HRM Pesentation
HRM PesentationHRM Pesentation
HRM Pesentation
 
Generic slides: AMEC in the Middle East, Africa and CIS
Generic slides: AMEC in the Middle East, Africa and CISGeneric slides: AMEC in the Middle East, Africa and CIS
Generic slides: AMEC in the Middle East, Africa and CIS
 
The ORE Catapult and Future Opportunities,David Arnold,Technology strategy Board
The ORE Catapult and Future Opportunities,David Arnold,Technology strategy BoardThe ORE Catapult and Future Opportunities,David Arnold,Technology strategy Board
The ORE Catapult and Future Opportunities,David Arnold,Technology strategy Board
 
Intertek - Industry Services
Intertek - Industry ServicesIntertek - Industry Services
Intertek - Industry Services
 
Introduction to the Revised UK Offshore Safety Legislation as Impacted by the...
Introduction to the Revised UK Offshore Safety Legislation as Impacted by the...Introduction to the Revised UK Offshore Safety Legislation as Impacted by the...
Introduction to the Revised UK Offshore Safety Legislation as Impacted by the...
 
William masson 2016-cv_a
William masson 2016-cv_aWilliam masson 2016-cv_a
William masson 2016-cv_a
 
DLV2000 Press Event Presentation_RMEDIA
DLV2000 Press Event Presentation_RMEDIADLV2000 Press Event Presentation_RMEDIA
DLV2000 Press Event Presentation_RMEDIA
 
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
 
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
4 sarah nightingale decc offshore wind seminar 18 19  march 20144 sarah nightingale decc offshore wind seminar 18 19  march 2014
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
 
Investor Day
Investor DayInvestor Day
Investor Day
 
Detailed Resume For Bryan Hill Oct 09
Detailed Resume For Bryan Hill Oct 09Detailed Resume For Bryan Hill Oct 09
Detailed Resume For Bryan Hill Oct 09
 
SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...
SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...
SME Opportunity Guide for Australian LNG Operations and Maintenance Contracti...
 
EPPM Presentation_Final
EPPM Presentation_FinalEPPM Presentation_Final
EPPM Presentation_Final
 
Allan g hardy cv feb 2020_master
Allan g hardy cv feb 2020_masterAllan g hardy cv feb 2020_master
Allan g hardy cv feb 2020_master
 
Intertek - Industry Services 2013
Intertek - Industry Services 2013Intertek - Industry Services 2013
Intertek - Industry Services 2013
 
Partnering to deliver an integrated programme at AWE presented by AWE, 23 Nov...
Partnering to deliver an integrated programme at AWE presented by AWE, 23 Nov...Partnering to deliver an integrated programme at AWE presented by AWE, 23 Nov...
Partnering to deliver an integrated programme at AWE presented by AWE, 23 Nov...
 
MaC Group Renewables Corporate Presentation January 2015 Printable
MaC Group Renewables Corporate Presentation January 2015 PrintableMaC Group Renewables Corporate Presentation January 2015 Printable
MaC Group Renewables Corporate Presentation January 2015 Printable
 
Portfolio, programme and project risk (Peter Campbell)
Portfolio, programme and project risk (Peter Campbell)Portfolio, programme and project risk (Peter Campbell)
Portfolio, programme and project risk (Peter Campbell)
 
ML-MT4572 - Safak (2)
ML-MT4572 - Safak (2)ML-MT4572 - Safak (2)
ML-MT4572 - Safak (2)
 
Develop Training brochure.PDF
Develop Training brochure.PDFDevelop Training brochure.PDF
Develop Training brochure.PDF
 

More from Project Controls Expo

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureProject Controls Expo
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Project Controls Expo
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Project Controls Expo
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Project Controls Expo
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Project Controls Expo
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...Project Controls Expo
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Project Controls Expo
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Project Controls Expo
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...Project Controls Expo
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Project Controls Expo
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Controls Expo
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...Project Controls Expo
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Project Controls Expo
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Project Controls Expo
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Project Controls Expo
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Project Controls Expo
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...Project Controls Expo
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...Project Controls Expo
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Project Controls Expo
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Project Controls Expo
 

More from Project Controls Expo (20)

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and future
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
 

Recently uploaded

Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxaryanv1753
 
The Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationThe Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationNathan Young
 
Engaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptxEngaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptxAsifArshad8
 
Genshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptxGenshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptxJohnree4
 
Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Escort Service
 
Early Modern Spain. All about this period
Early Modern Spain. All about this periodEarly Modern Spain. All about this period
Early Modern Spain. All about this periodSaraIsabelJimenez
 
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.KathleenAnnCordero2
 
Chizaram's Women Tech Makers Deck. .pptx
Chizaram's Women Tech Makers Deck.  .pptxChizaram's Women Tech Makers Deck.  .pptx
Chizaram's Women Tech Makers Deck. .pptxogubuikealex
 
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.comSaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.comsaastr
 
SBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSebastiano Panichella
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxmavinoikein
 
miladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptxmiladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptxCarrieButtitta
 
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC  - NANOTECHNOLOGYPHYSICS PROJECT BY MSC  - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC - NANOTECHNOLOGYpruthirajnayak525
 
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRRINDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRRsarwankumar4524
 
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRachelAnnTenibroAmaz
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringSebastiano Panichella
 
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power
 
Quality by design.. ppt for RA (1ST SEM
Quality by design.. ppt for  RA (1ST SEMQuality by design.. ppt for  RA (1ST SEM
Quality by design.. ppt for RA (1ST SEMCharmi13
 
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...Henrik Hanke
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSebastiano Panichella
 

Recently uploaded (20)

Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptx
 
The Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationThe Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism Presentation
 
Engaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptxEngaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptx
 
Genshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptxGenshin Impact PPT Template by EaTemp.pptx
Genshin Impact PPT Template by EaTemp.pptx
 
Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170
 
Early Modern Spain. All about this period
Early Modern Spain. All about this periodEarly Modern Spain. All about this period
Early Modern Spain. All about this period
 
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
 
Chizaram's Women Tech Makers Deck. .pptx
Chizaram's Women Tech Makers Deck.  .pptxChizaram's Women Tech Makers Deck.  .pptx
Chizaram's Women Tech Makers Deck. .pptx
 
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.comSaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
 
SBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation Track
 
Work Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptxWork Remotely with Confluence ACE 2.pptx
Work Remotely with Confluence ACE 2.pptx
 
miladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptxmiladyskindiseases-200705210221 2.!!pptx
miladyskindiseases-200705210221 2.!!pptx
 
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC  - NANOTECHNOLOGYPHYSICS PROJECT BY MSC  - NANOTECHNOLOGY
PHYSICS PROJECT BY MSC - NANOTECHNOLOGY
 
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRRINDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
 
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
 
The 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software EngineeringThe 3rd Intl. Workshop on NL-based Software Engineering
The 3rd Intl. Workshop on NL-based Software Engineering
 
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
 
Quality by design.. ppt for RA (1ST SEM
Quality by design.. ppt for  RA (1ST SEMQuality by design.. ppt for  RA (1ST SEM
Quality by design.. ppt for RA (1ST SEM
 
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
 

Benchmarking Project Health with Risk and Cost Models

  • 1. © QinetiQ Limited 2014 QinetiQ Proprietary Benchmarking Project Health: Enhancing Confidence, Assuring Delivery An exploration of the practical application of Risk and Cost audit models to benchmark project (and business) health and improve forecast cost and schedule out-turn Project Controls Expo – 18th Nov 2014 Emirates Stadium, London
  • 2. © QinetiQ Limited 2014 QinetiQ Proprietary 2 About the Speakers Steve Elwell BSc (Hons) MBA Director: Strategic Advisory Services Steve is a highly experienced director who has built a strong reputation for implementing complex programmes that involve significant change. He has considerable defence acquisition experience, having managed programmes across a range of industries. He specialises in development of output-based models and economic modelling solutions focused on continuous performance improvement. Mark Lee BSc MBA CEng MIET MIMechE MCMI Head of Profession (Risk & Programme Assurance): Strategic Advisory Services Mark’s risk and project management experience spans Maritime, Air, Land and Weapons. His career has taken him across Europe and as far afield as Canada, India and Australia. Mark leads a team of risk, project and programme management specialists and is QinetiQ’s lead practitioner in Risk Maturity Assessment.
  • 3. © QinetiQ Limited 2014 QinetiQ Proprietary 3 Objectives 1. Introduce the principles of risk and cost maturity assessment • Why a mature approach is important to cost (and schedule) control 2. Explore and explain the QinetiQ Maturity Models • Context and history: development of the models • Construct and scope • Why these particular models offers advantage to projects and businesses • How they are applied in practice to benchmark projects and organisations 3. Demonstrate the value of QinetiQ’s Maturity Models in application • Summary case examples from Defence and Oil & Gas
  • 4. © QinetiQ Limited 2014 QinetiQ Proprietary • Formed in 2001 from Defence Evaluation and Research Agency (DERA) • FTSE 250 - £1.3bn market capitalisation • 6,233 people worldwide, with ~1,100 specialists in weapons and testing • Member of The 5% Club – investing in graduates and apprentices • 37 sites across the UK – from Cape Wrath to Shoeburyness • 95% of QinetiQ’s UK employees hold national security clearance • 25 year Long Term Partnering Agreement (LTPA) with MOD, signed in 2006 • Empire Test Pilots’ School (ETPS) – training flight test professionals for 70 years • More than 1,500 patents granted, 1,000 patents pending • 75 years of test and evaluation at Aberporth, Wales 4
  • 5. © QinetiQ Limited 2014 QinetiQ Proprietary StrategicAdvisory Services 5 Procurement Advisory Services Commerce Decisions (AWARDTM) BusinessAnalysis CostEngineering Risk&Programme Assurance Requirements Acceptance ThroughLifeServices
  • 6. © QinetiQ Limited 2014 QinetiQ Proprietary 6 Why is Risk and Cost Maturity Important? Examples of ‘Failed’ Commercial Projects Scottish Parliament Forecast: £10-40m and 2001 opening Actual: £414m and 2004 opening Thermae Bath Spa Forecast: £13m and 2002 opening Actual: £45m and 2006 opening Source: Wikimedia.org Source: Wikipedia.org
  • 7. © QinetiQ Limited 2014 QinetiQ Proprietary 7 Why is Risk and Cost Maturity Important? Audit Evidence from Defence Source data: NAO Major Projects Report 2013 700 600 500 400 300 200 100 0 £m Ships Combat Air Submarines Helicopters Air Support Information Land ISTAR Weapons Systems Support Equipment 0 0 Defence – average cost growth across all 73 projects in the ships, combat air and submarine sectors Average cost over-run = £18m per project
  • 8. © QinetiQ Limited 2014 QinetiQ Proprietary 8 Why is Risk and Cost Maturity Important? Avoiding the News Headlines! “BBC Chief Technology Officer sacked over failed £100m Digital Media Initiative” “A major £12m scheme to digitise patient records has so far failed to deliver and is now expected to cost the Health Department double its original budget, according to the Public Accounts Committee” “Canadian provincial health officials fire prime contractor after the firm missed 3 years of deadlines and failed to deliver the province’s flagship online medical registry” “Sacked bursar loses claim for unfair dismissal over school’s £2.5m expansion project” “Environment Minister demoted after bungled $2.4bn home insulation fiasco” Source: Pressgazette.co.uk
  • 9. © QinetiQ Limited 2014 QinetiQ Proprietary 9 Why Does This Happen? Dealing with Uncertainty All projects have uncertainties and changing variables, arising from … • Budget changes • Schedule changes • Requirement changes • Omissions and errors • Failure to tackle risk at source • Things that “just go wrong” “…… because as we know, there are known knowns; there are things we know we know. We also know there are known unknowns; that is to say we know there are some things we do not know. But there are also unknown unknowns - the ones we don't know we don't know” Donald Rumsfeld Source: Wikimedia.org
  • 10. © QinetiQ Limited 2014 QinetiQ Proprietary QinetiQ Risk Maturity Model (QRMM) A Brief History … • Developed by QinetiQ (1999) to improve confidence by objectively assessing risk management maturity • Referenced to and compliant with ― MOD’s Acquisition Operating Framework (AOF) ― Project risk management best practice – APM Project Risk Analysis and Management (PRAM) Guide ― Combined Code (‘Turnbull Guidance’) for UK Corporate Governance – Financial Reporting Council • Proven capability and value in application over 15 years ― Over £75bn of Defence projects/programmes (across all domains) assessed … and counting ― Also deployed in Oil & Gas (FTSE 100 multi-national), Rail and Manufacturing • QinetiQ analysis of NAO Major Projects Reports has indicated that RMM can ― Increase confidence in project success through improved cost/schedule adherence ― Deliver forecast improvement in schedule and cost out-turn on major projects 11
  • 11. © QinetiQ Limited 2014 QinetiQ Proprietary Control of Risk Management Maturity Schedule Impact – QinetiQ Analysis of NAO Data Current Schedule Performance vs Original Forecast of MOD Top 20 Major Projects 41% 46% 114% 47% 32% 51% 63% 54% 53% 42% 75% 8% 10% 0% 0% 0% 11% 0% 0% 20% 40% 60% 80% 100% 120% Typhoon(Nov-87) StingRay(May-95) NimrodMRA4(Jul-96) AstuteClassSub(Mar- 97) A400M(May-00) Type45Destroyer(Jul- 00) SupportVehicle(Nov-01) NGLAAW(May-02) Terrier(Jul-02) NavalEHF/SHFSat Comms(Aug-03) Soothsayer(Aug-03) MTADS(Sep-04) Watchkeeper(Jul-05) Falcon(Mar-06) Merlin(Mar-06) FutureLynx(Jun-06) AdvancedJetTrainer (Aug-06) TyphoonFuture Capability(Jan-07) Scheduleoverrunas%oforiginalforecast Risk Maturity Uncontrolled Risk Maturity @ Level 3+ Forecast schedule overrun calculated from the summary of post- Main Gate projects in NAO Major Projects Reports Many factors affect projects, but those with risk maturity applied at all CADMID stages are more aware of issues and have mitigations in place to respond to those risks Major projects from the NAO reports with risk maturity applied are statistically less likely to experience schedule overruns Schedule Performance vs Original Forecast of MOD Major Projects Source data: NAO Major Projects Reports 12 Average schedule over-run = 56% Average schedule over-run = 4%
  • 12. © QinetiQ Limited 2014 QinetiQ Proprietary Control of Risk Management Maturity Cost Impact – QinetiQ Analysis of NAO Data Forecast cost overrun calculated from the summary of post-Main Gate projects in NAO Major Projects Reports Projects with Risk Maturity applied experience less budget volatility (overspend or underspend), compared with projects whose level of risk maturity is uncontrolled Current Schedule Performance vs Original Forecast of MOD Top 20 Major Projects -21% 28% 48% 0% 29% -7% -18% 6% -26% 42% -7% -1% -5% -1% 1% -5% -2% -30% -20% -10% 0% 10% 20% 30% 40% 50% Typhoon(Nov-87) StingRay(May-95) NimrodMRA4(Jul-96) AstuteClassSub(Mar- 97) A400M(May-00) Type45Destroyer(Jul- 00) SupportVehicle(Nov-01) NGLAAW(May-02) Terrier(Jul-02) NavalEHF/SHFSat Comms(Aug-03) Soothsayer(Aug-03) MTADS(Sep-04) Watchkeeper(Jul-05) Falcon(Mar-06) Merlin(Mar-06) FutureLynx(Jun-06) AdvancedJetTrainer (Aug-06) TyphoonFuture Capability(Jan-07) Currentoverspendas%oforiginalforecast Risk Maturity Uncontrolled Risk Maturity @ Level 3+ Budget Performance vs Original Forecast of MOD Major Projects Source data: NAO Major Projects Reports 13 Average cost overspend = 8% Average cost underspend = 3%
  • 13. © QinetiQ Limited 2014 QinetiQ Proprietary QRMM as an Enabler to Better Project Management • Assesses and benchmarks the quality and consistency of risk management implementation • Improves confidence in the ability to predict and deliver against schedule and cost • Establishes an independent, objective and evidence-based baseline measure of risk maturity • Identifies strengths and weaknesses in risk management process and its enablers • Supports formulation of a prioritised ‘roadmap’ of improvement actions against the baseline • Supports identification of common issues across projects, to help tackle risk at source • Facilitates sharing of good practice within and across business units • Builds confidence in the quality of underpinning data (e.g. for Business Cases) • Scalable: applicable at all levels, at all points in the project/business lifecycle • Can be used to support supplier assessment 14
  • 14. © QinetiQ Limited 2014 QinetiQ Proprietary QRMM Construct – Top Level Output Risk Maturity Assessment Stakeholders Risk Identification Risk Analysis Risk Mitigation Project Management Culture Current Maturity Potential Improvement Level 4 - Natural Level 3 - Normalised Level 2 - Novice Level 1 - Naive “An organisation is only as strong as its weakest element” 16
  • 15. © QinetiQ Limited 2014 QinetiQ Proprietary QRMM in Application Empirical Assessment Process Review Documentary Evidence Audit Conduct RMA Workshop Analyse and Report Results Implement Improvement Plan RMA Benchmark (Level 1 to 4) Periodic re-assessment against current benchmark 17
  • 16. © QinetiQ Limited 2014 QinetiQ Proprietary QRMM in Application Example Analysis Outputs Stakeholders Risk Identification Risk Analysis Risk Responses Project Management Culture Category1 Category2 Level 1 Level 2 Level 3 Level 4 Level of maturity after 20
  • 17. © QinetiQ Limited 2014 QinetiQ Proprietary QRMM in Application Case Examples from Defence – Case 1 • Portfolio of 4 projects, with QinetiQ contracted by MOD to − Formulate and deliver a formal Risk Improvement Programme: April-Aug 2011 − Conduct a repeat RMA in February 2014 to identify current baseline and improvements • April 2011 status of each project − Project A – in-service project undergoing contract change, with risk transfer to industry − Project B – mature equipment, in-service until ~2020, with industry managing risk − Project C – in Assessment Phase (AP) [due to be placed on contract in 2014] − Project D – complex international project, in AP [cleared MOD Main Gate in 2014] Project Measured RMA April 2011 Measured RMA July 2011 Measured RMA February 2014 Forecast RMA Project A Level 1 Level 2 Level 2 Level 3 Project B Level 3 Level 3 Level 3 Level 4 Project C Level 1 Level 2 Level 3 Level 3 Project D Level 1 Level 2 Level 4 Level 4 21
  • 18. © QinetiQ Limited 2014 QinetiQ Proprietary QRMM in Application Case Examples from Defence – Case 1 Perspective Number of Projects at Each Level – Feb ‘14 Level 2 Level 3 Level 4 Stakeholders √ √ √ √ Risk Identification √ √ √ √ Risk Analysis √ √ √ √ Risk Responses √ √ √ √ Project Management √ √ √ √ Culture √ √ √ √ • February 2014 forward improvement plans, focused to achieve — Project A: from high L2 (almost L3) to weak L3 in 3 months, consolidating to a firm L3 — Project B: from high L3 to a weak L4, consolidating to a firm L4 through secondary actions — Project C: from weak L3 (with risk of slipping back to L2) to a firm L3 — Project D: from weak L4 (risk of slipping back to L3) to a firm L4 • A good example of where focused MOD effort, and periodic RMA, can enhance risk execution 22
  • 19. © QinetiQ Limited 2014 QinetiQ Proprietary Current Schedule Performance vs Original Forecast of MOD Top 20 Major Projects -21% 28% 48% 0% 29% -7% -18% 6% -26% 42% -7% -1% -5% -1% 1% -5% -2% -30% -20% -10% 0% 10% 20% 30% 40% 50% Typhoon(Nov-87) StingRay(May-95) NimrodMRA4(Jul-96) AstuteClassSub(Mar- 97) A400M(May-00) Type45Destroyer(Jul- 00) SupportVehicle(Nov-01) NGLAAW(May-02) Terrier(Jul-02) NavalEHF/SHFSat Comms(Aug-03) Soothsayer(Aug-03) MTADS(Sep-04) Watchkeeper(Jul-05) Falcon(Mar-06) Merlin(Mar-06) FutureLynx(Jun-06) AdvancedJetTrainer (Aug-06) TyphoonFuture Capability(Jan-07) Currentoverspendas%oforiginalforecast Risk Maturity Uncontrolled Risk Maturity @ Level 3+ QRMM in Application Case Examples from Defence – Case 2 (MOD 1*) Stakeholders Risk Identification Risk Analysis Risk Responses Project Management Culture Category1 Category2 Level 1 Level 2 Level 3 Level 4 Level of maturity after • Level 1 across all 6 perspectives – the worst ever RMA score recorded by QinetiQ! • Risk improvement roadmap established to target — Level 2 in 3 months (22 actions) — Level 3 in a further 9 months (16 actions) Source: MoD 23
  • 20. © QinetiQ Limited 2014 QinetiQ Proprietary QRMM in Application Case Examples from Defence – Case 2 (MOD 1*) • Improvements were not implemented, due to — Lack of capacity within MOD to implement the plan — Conflicting demands and changing priorities — Ongoing organisational uncertainty — Realisation that implementation of improvements at 1* level would be insufficient • QinetiQ was then requested to — Formulate a transformation programme covering the 2* group (4 x 1* units) — Develop and roll-out improvements to enhance risk and cost management and control • What happened next? • MOD secured stakeholder buy-in to implement the ~18 month transformation programme • In-FY underspend was secured to fund the initial phase • Other areas developed an interest in improving their risk and cost maturity • A good example of where a localised RMA can uncover a need for wider risk/cost improvement Source: MoD 24
  • 21. © QinetiQ Limited 2014 QinetiQ Proprietary QRMM in Application Example Transformation Programme – Benefits Realisation Forecast Risk Maturity (left-hand scale) Phase 1 Phase 3Phase 2 Potential for Schedule/Cost Overrun (right-hand scale) Naïve (Level 1)  Risk process flawed  No real value-add Novice (Level 2)  Risk process influencing decisions  Risk process adding value  Improving performance against objectives  Some process/implementation weaknesses  Potential for significant unrealised benefits Normalised (Level 3)  Risk process formalised  Process implemented systematically  Effective risk responses executed  Sources of uncertainty under control  Significant value-add Natural (Level 4)  Risk process informing strategic choices  Sources of uncertainty managed systematically  Risk culture conducive to maximising outcomes Level 1 Level 4 Level 3 Level 2 RiskMaturityLevel 0-10% 100%+ 60-99% 11- 60% Schedule/CostOverrun (asa%ofbaselineschedule/budget) 25
  • 22. © QinetiQ Limited 2014 QinetiQ Proprietary QRMM in Application Case Example from Oil & Gas • 2011: FTSE 100 Oil & Gas multi-national approached QinetiQ to pilot an RMA on a UK project • QinetiQ amended the RMA framework Q&A set to reflect O&G-specific language − Underlying model and algorithms were unchanged • The pilot was conducted on the UK project − Identified that lack of risk disclosure from the JV partner was a significant threat − RMA was extremely well received by the client organisation − Actions to address the shortfalls were apparently not progressed − There were serious repercussions for both JV partners • A good example where failure to address risk maturity shortfalls can impact business health • What happened next? − QinetiQ undertook a further RMA on an operation in Asia, on completion of the UK pilot − The Asia RMA identified significant pockets of good practice to share across the company − QinetiQ was requested to develop a new corporate Cost & Schedule Risk Analysis standard Source: Wikipedia.org 26
  • 23. © QinetiQ Limited 2014 QinetiQ Proprietary QinetiQ Cost Engineering Health Check (CEHC) • Developed by QinetiQ as its second maturity assessment tool (following the success of the QRMM) − Reflecting the need to enhance confidence in the quality and accuracy of cost estimates − Recognising that poor quality cost estimates can undermine reasoned decision-making − Addressing the desire to benchmark cost engineering capability against peer organisations − Reflecting the increased emphasis on robust cost management in austerity “ The Cost Engineering Healthcheck (CEHC) was a professionally facilitated workshop and the results will guide the future direction of capability development for the cost community in the EACE Working Group” David Lewis – European Aerospace Cost Engineering (EACE) Chairman 27
  • 24. © QinetiQ Limited 2014 QinetiQ Proprietary CEHC Construct – Top Level Output Cost Engineering Health Check Data Tools People Processes Culture Stakeholders Categories Level Naive Novice Optimised Natural Normalised Identification of weak categories 29
  • 25. © QinetiQ Limited 2014 QinetiQ Proprietary CEHC in Application Case Example - Comparisons Between Defence and Space 0% 20% 40% 60% 80% 100% Naïve Novice Normalised Natural Optimised Respondants SCAF EACE Software Estimating The space community would seem to be more mature in the ability to estimate software costs compared to the defence community Both groups could benefit from more activity in this area to increase their maturity 30
  • 26. © QinetiQ Limited 2014 QinetiQ Proprietary CEHC in Application Case Example - Comparisons Between Defence and Space 0% 20% 40% 60% 80% 100% Naïve Novice Normalised Natural Optimised Respondants SCAF EACE Application of Multiple Estimating Methodologies The space community could learn from the defence cost community in how to apply alternative cost estimating methodologies (analytical, parametric and analogous) to increase confidence in the outputs they generate 32
  • 27. © QinetiQ Limited 2014 QinetiQ Proprietary CEHC in Application Benefits • Assesses the quality and consistency of cost engineering implementation • Provides evidence of weaknesses in the cost engineering capability of an organisation • Establishes a focus for cost engineering improvement, either alone or as part of a wider change initiative • Delivers improved capability in − The ability to forecast acquisition and support/ownership costs − The understanding of costs and their impact across the enterprise − Alignment and coherency … and the ability to identify and share good practice • Enhances confidence − For decision-makers, that their decisions are based on credible and justifiable financial information − In the robustness, accuracy and reliability of cost estimates − In the ability of cost estimates to withstand financial scrutiny and audit − In the potential for a project or business to increase its competitive edge and deliver more for less 33
  • 28. © QinetiQ Limited 2014 QinetiQ Proprietary Summary 1. Introduce the principles and importance of risk and cost maturity assessment − There is inherent uncertainty in all projects, programmes and businesses − Formalised risk and cost management help us understand and respond to uncertainty − Control of risk and cost maturity is a key enabler to good project management 2. Explore QinetiQ Risk Maturity Model (QRMM) and Cost Engineering Healthcheck (CEHC) − Audits and benchmarks project health and focuses improvement initiatives − Enhances confidence in the likelihood of an out-turn to schedule and within budget − Enables us to more confidently establish our risk appetite and inform strategic choice 3. Demonstrate value of QRMM and CEHC in application − Case 1 – focused improvement and periodic re-assessment enhanced project control − Case 2 – localised RMA can trigger wider imperative to enhance risk management − Case 3 – failure to address risk maturity improvement can impact business health − Case 4 – use of CEHC to compare cost engineering maturity across industries Source: Pressgazette.co.uk 34
  • 29. © QinetiQ Limited 2014 QinetiQ Proprietary www.QinetiQ.com