SlideShare a Scribd company logo
1 of 9
What’s new in PMBOK® Guide 6th
Edition
Document Objective: This document focuses on several key areas where the
concepts of PMBOK Guide 5th edition have been revised. It highlights the
changes in Knowledge Areas/Process Groups/Processes as per PMBOK®
Guide 6th Edition.
Background – The Project Management Institute (PMI)® performs a
“Role Delineation Study (RDS)” periodically, every 5 to 7 years . The goal
of this study is to identify what are the project managers around the
world doing in their current projects and the changing trends and
practices in project Management and it updates the content of the exam
as per the result of the study. After the most recent RDS, PMI now has a
list of tasks that the project managers perform, as well as the knowledge
and skills required for the job and upgraded the exam syllabus for PMP
certification and that is why there is an upgrade in PMBOK® Guide as
well which is the single most important publication by the PMI® for
PMP® Certification aspirants to study and prepare for the PMP® Exam.
PMBOK® 6th Edition
• The 6th edition of the Project Management Body of Knowledge
(PMBOK®) Guide was released in September 2017 and PMP®
certification exam format has been revised from March 26,
2018.
• There are several new sections included in the PMBOK® 6th
edition which are as per the changing trends and practices in
project management and they’re all packed into a 976-page
book, The PMBOK® Guide, 6th Edition.
• The most significant addition in PMBOK® 6th edition is a section
containing Agile Development. The Agile concept is
incorporated in all 10 knowledge areas. Each knowledge area
will contain a section entitled Approaches for Agile, Iterative
and Adaptive Environments, describing how these practices
integrate in project settings.
PMBOK® 6th Edition vs. PMBOK® 5th
Edition: What’s Changed?
• Changes in Process Groups
 The number of process groups remains the same in 5th and 6th edition.
• Changes In Knowledge Area
 Two Knowledge Areas names were changed to more closely reflect the work that is
done.
 Project Time Management was changed to Project Schedule Management to
reflect that the project schedule is defined and managed during the project,
whereas time is not managed.
 Both team resources and physical resources are addressed in the Sixth Edition.
Thus, the Knowledge Area Project Human Resource Management was changed
to Project Resource Management.
…as per PMBOK®
• Changes in the number of Processes
There are total 49 processes now in 6th edition as compared to 47
in 5th edition. One process was removed and three new processes
were added in 6th edition, to reflect changes in the way projects
are managed in practice. One process was moved between
Knowledge Areas. These changes are summarized below :
 Manage Project Knowledge —Added.
 Estimate Activity Resources —Moved to Project Resource
Management.
 Control Resources —Added.
 Implement Risk Responses —Added.
 Close Procurements —Eliminated.
…as per
PMBOK®
What’s Changed ? Continued...
• Changes in the name of existing processes
Several process names were changed to improve consistency across the processes
and to improve clarity. Research ndicates that project managers tend to monitor,
facilitate, and manage rather than control, particularly in processes that involve
interactions with people. Therefore, process names for Control Communications,
Control Risks, and Control Stakeholder Engagement were changed to Monitor
Communications, Monitor Risks, and Monitor Stakeholder Engagement. The list
below summarizes all the process name changes:
 Perform Quality Assurance (Section 8.2)—Changed to Manage Quality.
 Plan Human Resource Management (Section 9.1)—Changed to Plan Resource Management.
 Acquire Project Team (Section 9.2)—Changed to Acquire Resources.
 Develop Project Team (Section 9.3)—Changed to Develop Team.
 Manage Project Team (Section 9.4)—Changed to Manage Team.
 Control Communications (Section 10.3)—Changed to Monitor Communications
 Control Risks (Section 11.6)—Changed to Monitor Risks.
 Plan Stakeholder Management (Section 13.2)—Changed to Plan Stakeholder Engagement.
 Control Stakeholder Engagement (Section 13.4)—Changed to Monitor Stakeholder Engagement.
…as per PMBOK®
What’s Changed ? Continued...
• THE ROLE OF THE PROJECT MANAGER - New section in
6th Edition
This is a new section that outlines the project manager’s
role in the team. It includes information on the project
manager’s sphere of influence and competencies. PMI’s
Talent Triangle® is discussed with its emphasis on strategic
and business management skills, technical project
management skills, and leadership skills. Leadership styles
and personality are also discussed as part of this section.
The final part of this section focuses on the project
manager as an integrator.
…as per PMBOK®
What’s Changed ? Continued...
• AGILE – New Section added in 6th edition
Since the Fifth Edition of the PMBOK® Guide
there has been more adoption of agile and
adaptive methodologies in the management of
projects. The Sixth Edition has included a
subsection called Considerations for Adaptive
Environments at the beginning of Sections 4
through 13. Some agile-specific tools and
techniques have been introduced into the
PMBOK® Guide, such as sprint and iteration
planning.
What’s Changed ? Continued...
What's new in pmbok guide 6th edition

More Related Content

What's hot

Value of PMP Certification and PMI Membership
Value of PMP Certification and PMI MembershipValue of PMP Certification and PMI Membership
Value of PMP Certification and PMI MembershipRahul Sudame
 
Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3Highmark Health
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2Anand Bobade
 
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management Processes
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management ProcessesKCS Academy PMP Exam Prep Course Chapter 3 - Project Management Processes
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management ProcessesKing Consulting Services
 
PMBOK® Guide Sixth Edition Update
PMBOK® Guide Sixth Edition UpdatePMBOK® Guide Sixth Edition Update
PMBOK® Guide Sixth Edition UpdateEPM International
 
KCS Academy PMP Exam Prep Course Chapter 2 - Organizational Influences and Pr...
KCS Academy PMP Exam Prep Course Chapter 2 - Organizational Influences and Pr...KCS Academy PMP Exam Prep Course Chapter 2 - Organizational Influences and Pr...
KCS Academy PMP Exam Prep Course Chapter 2 - Organizational Influences and Pr...King Consulting Services
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication ManagementDavidMcLachlan1
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope ManagementDavidMcLachlan1
 
Pmbok 5cartulinas
Pmbok 5cartulinasPmbok 5cartulinas
Pmbok 5cartulinasPedro Arcas
 
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...JustAcademy
 
KCS Academy PMP Exam Prep Course Chapter 1 - Introduction
KCS Academy PMP Exam Prep Course Chapter 1 - IntroductionKCS Academy PMP Exam Prep Course Chapter 1 - Introduction
KCS Academy PMP Exam Prep Course Chapter 1 - IntroductionKing Consulting Services
 
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionPMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionRicardo Viana Vargas
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaJoshua Render
 

What's hot (20)

Value of PMP Certification and PMI Membership
Value of PMP Certification and PMI MembershipValue of PMP Certification and PMI Membership
Value of PMP Certification and PMI Membership
 
Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
 
PMP Exam Changes
PMP Exam ChangesPMP Exam Changes
PMP Exam Changes
 
Pmbok6 changes
Pmbok6 changesPmbok6 changes
Pmbok6 changes
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management Processes
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management ProcessesKCS Academy PMP Exam Prep Course Chapter 3 - Project Management Processes
KCS Academy PMP Exam Prep Course Chapter 3 - Project Management Processes
 
PMBOK® Guide Sixth Edition Update
PMBOK® Guide Sixth Edition UpdatePMBOK® Guide Sixth Edition Update
PMBOK® Guide Sixth Edition Update
 
Process groups and knowledge areas PMBOK 5th Edition
Process groups and knowledge areas PMBOK 5th EditionProcess groups and knowledge areas PMBOK 5th Edition
Process groups and knowledge areas PMBOK 5th Edition
 
KCS Academy PMP Exam Prep Course Chapter 2 - Organizational Influences and Pr...
KCS Academy PMP Exam Prep Course Chapter 2 - Organizational Influences and Pr...KCS Academy PMP Exam Prep Course Chapter 2 - Organizational Influences and Pr...
KCS Academy PMP Exam Prep Course Chapter 2 - Organizational Influences and Pr...
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
Pmbok 5cartulinas
Pmbok 5cartulinasPmbok 5cartulinas
Pmbok 5cartulinas
 
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
Organizational Influences and Project Life Cycle,PMP Chapter 2,PMBOK,PMP Exam...
 
KCS Academy PMP Exam Prep Course Chapter 1 - Introduction
KCS Academy PMP Exam Prep Course Chapter 1 - IntroductionKCS Academy PMP Exam Prep Course Chapter 1 - Introduction
KCS Academy PMP Exam Prep Course Chapter 1 - Introduction
 
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionPMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
 

Similar to What's new in pmbok guide 6th edition

Pmi chapter 29.11.2017
Pmi chapter 29.11.2017Pmi chapter 29.11.2017
Pmi chapter 29.11.2017Ernar Makishev
 
PMPBOK 5th Edition Vs PMBOK 6th Edition, Knowledge Area Changes and New Proce...
PMPBOK 5th Edition Vs PMBOK 6th Edition, Knowledge Area Changes and New Proce...PMPBOK 5th Edition Vs PMBOK 6th Edition, Knowledge Area Changes and New Proce...
PMPBOK 5th Edition Vs PMBOK 6th Edition, Knowledge Area Changes and New Proce...Sanjay Rajpoot
 
Pmp Prep Session 1 Overview
Pmp Prep Session 1 OverviewPmp Prep Session 1 Overview
Pmp Prep Session 1 Overviewhouserdah
 
Overview pmbok guide4thedition
Overview pmbok guide4theditionOverview pmbok guide4thedition
Overview pmbok guide4theditionminhdd1980
 
PMBOK 4th Edtions Changes
PMBOK 4th Edtions ChangesPMBOK 4th Edtions Changes
PMBOK 4th Edtions Changesgryasam
 
PMP EXAM PREPARATION.pdf
PMP EXAM PREPARATION.pdfPMP EXAM PREPARATION.pdf
PMP EXAM PREPARATION.pdfDivya Malik
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6Amit Gupta
 
Pmbok 6 th Edition
Pmbok 6 th EditionPmbok 6 th Edition
Pmbok 6 th EditionAshraf Ali
 
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...Edureka!
 
White paper changes to the pmbok 4th edition
White paper changes to the pmbok 4th editionWhite paper changes to the pmbok 4th edition
White paper changes to the pmbok 4th editionBeyond20
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011tigcap
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011tigcap
 
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...Tareq Al-Behairi,PMP,PMI-ACP
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docxShiraPrater50
 
PMBoK V5 changes
PMBoK V5 changesPMBoK V5 changes
PMBoK V5 changesPeg Duggan
 

Similar to What's new in pmbok guide 6th edition (20)

14 key changes in pmbok ® guide sixth edition
14 key changes in pmbok ® guide sixth edition14 key changes in pmbok ® guide sixth edition
14 key changes in pmbok ® guide sixth edition
 
Pmi chapter 29.11.2017
Pmi chapter 29.11.2017Pmi chapter 29.11.2017
Pmi chapter 29.11.2017
 
PMPBOK 5th Edition Vs PMBOK 6th Edition, Knowledge Area Changes and New Proce...
PMPBOK 5th Edition Vs PMBOK 6th Edition, Knowledge Area Changes and New Proce...PMPBOK 5th Edition Vs PMBOK 6th Edition, Knowledge Area Changes and New Proce...
PMPBOK 5th Edition Vs PMBOK 6th Edition, Knowledge Area Changes and New Proce...
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
 
Pmp Prep Session 1 Overview
Pmp Prep Session 1 OverviewPmp Prep Session 1 Overview
Pmp Prep Session 1 Overview
 
Overview pmbok guide4thedition
Overview pmbok guide4theditionOverview pmbok guide4thedition
Overview pmbok guide4thedition
 
PMBOK 4th Edtions Changes
PMBOK 4th Edtions ChangesPMBOK 4th Edtions Changes
PMBOK 4th Edtions Changes
 
PMP EXAM PREPARATION.pdf
PMP EXAM PREPARATION.pdfPMP EXAM PREPARATION.pdf
PMP EXAM PREPARATION.pdf
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
 
Day 1 framework
Day 1 frameworkDay 1 framework
Day 1 framework
 
Pmbok 6 th Edition
Pmbok 6 th EditionPmbok 6 th Edition
Pmbok 6 th Edition
 
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
 
White paper changes to the pmbok 4th edition
White paper changes to the pmbok 4th editionWhite paper changes to the pmbok 4th edition
White paper changes to the pmbok 4th edition
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011
 
Capello Pw 2011
Capello Pw 2011Capello Pw 2011
Capello Pw 2011
 
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
Insights into the Project Management Body of Knowledge (PMBOK® Guide) - Sixth...
 
PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 
PM FrameWork: Module 1
PM FrameWork: Module 1PM FrameWork: Module 1
PM FrameWork: Module 1
 
PMBoK V5 changes
PMBoK V5 changesPMBoK V5 changes
PMBoK V5 changes
 

Recently uploaded

How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionCIToolkit
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project ManagementCIToolkit
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Giuseppe De Simone
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsHannah Smith
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...CIToolkit
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsCIToolkit
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentCIToolkit
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingGiuseppe De Simone
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 

Recently uploaded (16)

How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem Resolution
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project Management
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful Thinking
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 

What's new in pmbok guide 6th edition

  • 1. What’s new in PMBOK® Guide 6th Edition
  • 2. Document Objective: This document focuses on several key areas where the concepts of PMBOK Guide 5th edition have been revised. It highlights the changes in Knowledge Areas/Process Groups/Processes as per PMBOK® Guide 6th Edition. Background – The Project Management Institute (PMI)® performs a “Role Delineation Study (RDS)” periodically, every 5 to 7 years . The goal of this study is to identify what are the project managers around the world doing in their current projects and the changing trends and practices in project Management and it updates the content of the exam as per the result of the study. After the most recent RDS, PMI now has a list of tasks that the project managers perform, as well as the knowledge and skills required for the job and upgraded the exam syllabus for PMP certification and that is why there is an upgrade in PMBOK® Guide as well which is the single most important publication by the PMI® for PMP® Certification aspirants to study and prepare for the PMP® Exam.
  • 3. PMBOK® 6th Edition • The 6th edition of the Project Management Body of Knowledge (PMBOK®) Guide was released in September 2017 and PMP® certification exam format has been revised from March 26, 2018. • There are several new sections included in the PMBOK® 6th edition which are as per the changing trends and practices in project management and they’re all packed into a 976-page book, The PMBOK® Guide, 6th Edition. • The most significant addition in PMBOK® 6th edition is a section containing Agile Development. The Agile concept is incorporated in all 10 knowledge areas. Each knowledge area will contain a section entitled Approaches for Agile, Iterative and Adaptive Environments, describing how these practices integrate in project settings.
  • 4. PMBOK® 6th Edition vs. PMBOK® 5th Edition: What’s Changed? • Changes in Process Groups  The number of process groups remains the same in 5th and 6th edition. • Changes In Knowledge Area  Two Knowledge Areas names were changed to more closely reflect the work that is done.  Project Time Management was changed to Project Schedule Management to reflect that the project schedule is defined and managed during the project, whereas time is not managed.  Both team resources and physical resources are addressed in the Sixth Edition. Thus, the Knowledge Area Project Human Resource Management was changed to Project Resource Management. …as per PMBOK®
  • 5. • Changes in the number of Processes There are total 49 processes now in 6th edition as compared to 47 in 5th edition. One process was removed and three new processes were added in 6th edition, to reflect changes in the way projects are managed in practice. One process was moved between Knowledge Areas. These changes are summarized below :  Manage Project Knowledge —Added.  Estimate Activity Resources —Moved to Project Resource Management.  Control Resources —Added.  Implement Risk Responses —Added.  Close Procurements —Eliminated. …as per PMBOK® What’s Changed ? Continued...
  • 6. • Changes in the name of existing processes Several process names were changed to improve consistency across the processes and to improve clarity. Research ndicates that project managers tend to monitor, facilitate, and manage rather than control, particularly in processes that involve interactions with people. Therefore, process names for Control Communications, Control Risks, and Control Stakeholder Engagement were changed to Monitor Communications, Monitor Risks, and Monitor Stakeholder Engagement. The list below summarizes all the process name changes:  Perform Quality Assurance (Section 8.2)—Changed to Manage Quality.  Plan Human Resource Management (Section 9.1)—Changed to Plan Resource Management.  Acquire Project Team (Section 9.2)—Changed to Acquire Resources.  Develop Project Team (Section 9.3)—Changed to Develop Team.  Manage Project Team (Section 9.4)—Changed to Manage Team.  Control Communications (Section 10.3)—Changed to Monitor Communications  Control Risks (Section 11.6)—Changed to Monitor Risks.  Plan Stakeholder Management (Section 13.2)—Changed to Plan Stakeholder Engagement.  Control Stakeholder Engagement (Section 13.4)—Changed to Monitor Stakeholder Engagement. …as per PMBOK® What’s Changed ? Continued...
  • 7. • THE ROLE OF THE PROJECT MANAGER - New section in 6th Edition This is a new section that outlines the project manager’s role in the team. It includes information on the project manager’s sphere of influence and competencies. PMI’s Talent Triangle® is discussed with its emphasis on strategic and business management skills, technical project management skills, and leadership skills. Leadership styles and personality are also discussed as part of this section. The final part of this section focuses on the project manager as an integrator. …as per PMBOK® What’s Changed ? Continued...
  • 8. • AGILE – New Section added in 6th edition Since the Fifth Edition of the PMBOK® Guide there has been more adoption of agile and adaptive methodologies in the management of projects. The Sixth Edition has included a subsection called Considerations for Adaptive Environments at the beginning of Sections 4 through 13. Some agile-specific tools and techniques have been introduced into the PMBOK® Guide, such as sprint and iteration planning. What’s Changed ? Continued...