Final project in Construction Management - Technion Institute of Technology

A construction Management project from beginning to end, including planning, scheduling, cost analysis and tenders.

  • Be the first to comment

Final project in Construction Management - Technion Institute of Technology

  1. 1. Final Project in Construction Management Final Presentation
  2. 2. Winter Semester 2013/14 Advisor: Ziv Hendel Submitted by: Paula Barmaimon 941104093
  3. 3. Location Rechov Nisim Aloni, Tel Aviv
  4. 4. 13500 m² Rechov Nisim Aloni, Tel Aviv
  5. 5. Site Layout Parking Parking Eating area 10 m 45 m 45 m Check the crane model
  6. 6. Site preparation Earthworks Parking Structural Works Finishing works Schedule Development
  7. 7. Crews Baranovich team Formwork walls, external & internal Steel Slab
  8. 8. Schedule Walls formwork placing Walls steel placing Slab formwork placingConcrete casting Concrete setting Slab steel placing
  9. 9. Day 1-4
  10. 10. Day 1-4
  11. 11. Day 5-7
  12. 12. Day 5-7
  13. 13. Day 8
  14. 14. Day 8
  15. 15. Day 9-12
  16. 16. Crews Baranovich team Formwork walls, external & internal Steel Slab
  17. 17. Baranovich system 1. Clean 2. Place the stones 3. Place the fuga 4. Place isolation 5. Place steel mesh • Used in high rise building with many typical floors • Shortens the duration of exterior cladding • Casts external walls and stones at the same time
  18. 18. Baranovich system • Scaffolding needed for workers to place it • At least 4 anchores/stone • Must be cleaned extremely well
  19. 19. Slab team – PERI Skydeck system
  20. 20. Advantages • Removal is possible after 1 day • Light components • Easy to clean • Fewer slab props- saves time and space
  21. 21. Total workers needed for concrete works 20 workers
  22. 22. Cost Analysis CIP CONCRETE
  23. 23. CIP concrete • Quantity • Cost
  24. 24. Steel Density of steel 7850 kg/m3
  25. 25. Cost of steel
  26. 26. Steel in beams
  27. 27. Steel
  28. 28. Formwork
  29. 29. Total Cost
  30. 30. Summary for Concrete Works Total Cost of Project 300,000,000  concrete works ~ 16% of total proyect The total duration of the proyect is 36 months. The total duration of concrete works is 19 months. Concrete works must be completed in 2 weeks/floor Peri Skydeck must be used to achieve this rate. The crew size for this purpose is 20 workers .
  31. 31. Project Manager 2 Site Engineer 2 Head Foreman Concrete Foreman Steel Foreman Parking Foreman Finishing Foreman Development Foreman Secretaries Guard MEP Manager BOQ Buying Coordinators MANAGEMENT CREW
  32. 32. Overheads
  33. 33. THANK YOU!!

×