SlideShare a Scribd company logo
1 of 36
Download to read offline
Leiden Institute of Advanced Computer Science



            System s Development and Project
            Management –
            Risk management and project
            escalation

            Prof. Dr. Thomas Bäck




                                                1
Leiden Institute of Advanced Computer Science                           Dates

Feb. 1               14:45 – 17:30           Introduction, Project Description
Feb. 2               13:45 – 16:30           STEP WISE Approach to Project Planning
Feb. 9               13:10 – 15:45           STEP WISE Approach to Project Planning,
                                             SAVE ENERGY Case
Feb. 15              14:45 – 17:30           Selecting an Appropriate Software Dev.
                                             Approach
Feb. 16              15:15 – 18:00           Activity Planning and Resource Allocation
Feb. 22              14:45 – 17:30           Software Effort Estimation
Feb. 23              13:15 – 15:45           Risk management, project escalation
Mar. 1               14:45 – 17:00           Exam
Mar. 2               13:45 – 16:30           Risk Management, Project monitoring and
                                             control
Mar. 8               14:45 – 17:30           Software Quality Assurance
Mar. 9               13:45 – 16:30           Managing People; Contract Management
Mar. 18              15:00 – 17:00           Trade Fair
                                                                                      2
Leiden Institute of Advanced Computer Science




Deliverable Planning
 February 18, midnight                Assignment 1:
                                      Project proposal ( bid )

 February 25, midnight                Assignment 2:
                                      Project Plan including functional specification

 March 7, midnight                    Assignment 3:
                                      Deutsche Bank case, 5 ppt slides

 March 1 (14:45 – 17:00)              Exam
 March 18 (15:00 – 17:00)             Trade fair, Plantsoen 97, Leiden
 (setup from 14:00)
 March 18, midnight                   Assignment 4:
                                      Personal reflection paper on project
                                      management




                                                                                        3
Leiden Institute of Advanced Computer Science




STEP WISE overview
      1. Identify project objectives           0. Select Project             2. Identify project infrastructure




                                         3. Analyze pr. characteristics


                                       4. Identify products and activities
                  Review lower
                  level detail
                                         5. Estimate effort for activity
                                                                                  For each activity

                                            6. Identify activity risks


   10. Lower level planning                  7. Allocate resources


       9. Execute plan                     8. Review / publicize plan



                                                                                                        4
Leiden Institute of Advanced Computer Science




Evaluation

  !   Not unusual to spend between 6-12 months
      and 40% of total acquisition and
      implementation cost on package evaluation
      with major customers.
  !   Make or buy?
    !    Buying is attractive when money available but
         other resources are short.
    !    Hazards, because staff time and attention is
         needed to manage such projects successfully.

                                                         5
Leiden Institute of Advanced Computer Science




Nature of risk

  !   Describes non-desirable events or outcomes
      (vs. opportunities)
  !   Risk management concerned with:
     !    Events or hazards
     !    Outcomes or problems
     !    Action plans
  !   Includes assessment of likelihoods,
      seriousness, costs and effectiveness of action

                                                      6
Leiden Institute of Advanced Computer Science




Types of risk

  !   Caused by estimation difficulties
     !    Some tasks are more difficult to estimate
  !   Caused by assumptions made during
      planning process
     !    Important to continuously list all assumptions and
          their likely effects
  !   Eventualities: Unforeseen hazards occurring
     !    Reduction through sound planning


                                                               7
Leiden Institute of Advanced Computer Science




Managing risk
  Boehm s risk engineering task breakdown                    Risk
                                                          engineering




                                                                                   Risk
                             Risk analysis
                                                                                management



      Risk
                           Risk estimation              Risk evaluation
  identification




  Risk planning      Risk control       Risk monitoring        Risk directing   Risk staffing


                                                                                            8
Leiden Institute of Advanced Computer Science




Managing risk (cont d)

  !   Risk analysis:
     !    Risk identification - listing all hazards which could
          affect project
     !    Risk estimation - likelihood and severeness of
          hazards
     !    Risk evaluation - ranking and determination of risk
          aversion strategies




                                                                  9
Leiden Institute of Advanced Computer Science




Managing risk (cont d)

  !   Risk management:
    !    Risk planning – drawing up contingency plans
    !    Risk control – quality control and dealing with
         emergent problems
    !    Risk monitoring – an ongoing activity
    !    Risk directing             Day-to-day risk management
    !    Risk staffing




                                                             10
Leiden Institute of Advanced Computer Science




Hazard identification

  !       Application factors
  !       Staff factors
  !       Project factors                                   Factors should be
  !       Project methods                                   considered for each
  !       Hardware/software                                 activity individually,
          factors                                           involving the whole
  !       Changeover factors                                project team
  !       Supplier factors
  !       Environment factors
  !       Health and safety
          factors                                                            11
Leiden Institute of Advanced Computer Science




Hazard analysis

  !   Most favored ranking method is to calculate
      risk exposure
     !    Risk exposure RE = risk likelihood * risk impact
  !   Alternative - scoring methods:
     !    Likelihood
     !    Impact
     !    Timeframe



                                                             12
Leiden Institute of Advanced Computer Science




Hazard analysis (cont d)

  !   Risk prioritization
     !    Reducing risk exposure by decreasing likelihood
          and/or impact
     !    Contingency plans
  !   Risk reduction leverage (RRL)
     !    RRL=(REbefore-REafter)/risk reduction cost
     !    Monetary values recommended
     !    RRL > 1: We can gain from implementing the risk
          reduction plan

                                                            13
Leiden Institute of Advanced Computer Science




Risk planning and control

  !     Hazard prevention
  !     Likelihood reduction
  !     Risk avoidance
  !     Risk transfer
  !     Contingency planning




                                                        14
Leiden Institute of Advanced Computer Science




Evaluating schedule risks

  !   In contrast to CPM, PERT requires three
      estimates:
     !    Most likely time (m)
     !    Optimistic time (a)
     !    Pessimistic time (b)
  !   Activity-on-arrow diagram
  !   te=(a+4m+b)/6, s=(b-a)/6, z=(T- te)/s
  !   Expected duration te, s-dev s., no. of s-dev.s
      between target and expected date z

                                                       15
Leiden Institute of Advanced Computer Science




Notation

                   Event number                      Target date


                                                      Standard
                  Expected date
                                                      deviation




                                                                   16
Leiden Institute of Advanced Computer Science




Evaluating schedule risks (cont d)

  1.  Use expected durations for forward pass
  2.  Calculate standard deviations for each
      project event (add squares and find square
      root of sum)
  3.  Calculate z-values - number of standard
      deviations between expected and target
      dates
                            If there are several possible
  4.  Convert z-values to probabilities largest standard
                            Paths: take
                                                  deviation
                                                              17
Leiden Institute of Advanced Computer Science



Example: Convert to activity-on-arrow
diagram!
                                B
                                                          E
                          Duration 6

                                                      Duration 8
         A                      C                                     G

     Duration 5
                          Duration 10                      F       Duration 4


                                D                     Duration 3

  ES = day 0
                          Duration 9
                                                                            18
Leiden Institute of Advanced Computer Science




Example: (now activity on arrow!)
                            3


                  B=6                      6     E   8

                                                 8       10   G   11
  1      A    2       C     4

  0      5            10                                      4
                                           7     F   9


                  D=9                            3
                            5




                                                                       19
Leiden Institute of Advanced Computer Science


                                     Optimistic time
                                               Most likely time
Complete               the table                     Pessimistic time
Activity	
   a	
         m	
   b	
      te	
      s	
     z	
    T 	
           Prob.	
  
A	
            4	
        5	
         6	
         	
       	
     	
     	
     	
  
B	
            4	
        6	
         8	
         	
       	
     	
     	
     	
  
C 	
           9	
        10	
        12	
        	
       	
     	
     	
     	
  
D 	
           8	
        9	
         10	
        	
       	
     	
     	
     	
  
E	
            5	
        8	
         11	
        	
       	
     	
     	
     	
  
F	
            1	
        3	
         4	
         	
       	
     	
     	
     	
  
G	
            3	
        4	
         5	
         	
       	
     	
     	
     	
  

                                                                                       20
Leiden Institute of Advanced Computer Science



Example:
t_e and standard deviations
                                                   E
                             3                    t=8
                      B                                             G
         A           t=6                          s=1              t=4
        t=5        s=0.67                  6            8        s=0.33
      s=0.33
  1            2                                            10            11
                         C 4
                      t=10.17
  0
                       s=0.5               7            9


                             5                      F
                      D                          t=2.83
                      9                           s=0.5
                    s=0.33




                                                                               21
Leiden Institute of Advanced Computer Science


                                                      (a+4m+b)/6
Complete the table                                           (b-a)/6

 Activit a            m          b           te         s      z       T   Prob
 y                                                                         .
 A       4            5          6           5          0.33
 B       4            6          8           6          0.67
 C       9            10         12          10.17 0.5
 D       8            9          10          9          0.33
 E       5            8          11          8          1
 F       1            3          4           2.83       0.5
 G       3            4          5           4          0.33
                                                                            22
Leiden Institute of Advanced Computer Science




Example: Expected dates
                                                        E
                                  3                    t=8
                          B                                                     G
             A           t=6                           s=1                     t=4
                                  11
            t=5        s=0.67                  6             8               s=0.33
          s=0.33
                                               15.17         23.17   10               11
     1             2         C    4
                          t=10.17                                    23.17            27.17
     0             5              15.17
                           s=0.5               7             9

                                               14            16.83
                                  5                     F
                          D                          t=2.83
                          9       14
                                                      s=0.5
                        s=0.33




                                                                                              23
Leiden Institute of Advanced Computer Science




Example: Cumulative standard deviations
                                                       E
                                 3                    t=8
                          B                                                     G
             A           t=6                          s=1                      t=4
                                 11 0.75
            t=5        s=0.67                  6            8                s=0.33
          s=0.33
                                               15.17 0.75 23.17 1.25    10            11
     1             2       C     4
                        t=10.17                                         23.17 1.25    27.17 1.29
     0             5 0.33       15.17 0.6
                         s=0.5                 7            9

                                               14 0.75      16.83 0.9
                                 5                      F
                          D                          t=2.83
                          9      14 0.47
                                                      s=0.5
                        s=0.33




                                                                                              24
Leiden Institute of Advanced Computer Science


Evaluating schedule risks (cont d)
!   Monte Carlo simulation as an alternative
   !    Calculates large number of activity completion
        dates
   !    Random selection of activity times from set of
        estimates
   !    Input depending on available information, e.g.
        historic project information
   !    Output can take form of graphs and summaries
!   Specialized software packages available
   !    Interfaces to project planning and spreadsheet
        software
   !    Cost, resource, and duration estimates
                                                         25
Leiden Institute of Advanced Computer Science




ICT project management 'runaways’…

  !   Standish "Chaos" report
    !    1994:
          •  16% success,
          •  31% cancelled
          •  53% challenged
    !    2000:
          •  34% successful
          •  15% cancelled
          •  51% challenged



                                                      26
Leiden Institute of Advanced Computer Science




Project Management & Success
                                         !  Technical issues
challenged                                    !   Hardware/software/telecommunications    systems
  51%                                             don't work
                                              !   Frequent failure/errors in operation
                             cancelled
                                15%
                                         !  Economic issues
                                              !   Time or budget overrun
             success
                                              !   Low/no ROI ( productivity paradox )
              34%
                                         !  Organizational (implementation)
                                            issues
                                              !   Resulting system fails to achieve desired benefit
                                              !   Users reject system
Leiden Institute of Advanced Computer Science




Project Escalation

  !   Continued commitment in the face of negative
      information about prior resource allocations coupled
      with uncertainty surrounding the likelihood of goal
      attainment (Brockner, 1992)

     Project                                          Social
     Factors                                          Factors
                                      Project
                                     Escalation
     Psychol.                                         Organiz.
     Factors                                          Factors

                                                                 28
Leiden Institute of Advanced Computer Science




Escalation factors

  Project factors:                                Risk of escalation:
  !   Objective features of                       !   Large potential payoff
      the project                                 !   Long-term investment
  !   Perception by                                   to reap gains
      management                                  !   Setbacks perceived as
  !   Costs and benefits                              temporary problems
      associated with the
      project
  !   Difficulties (risk) and
      duration

                                                                               29
Leiden Institute of Advanced Computer Science




Escalation factors (cont d)

  Psychological factors:                          Risk of escalation:
  !   „Things do not look that                    !   Errors in processing
      bad                                             information
  !   Continuation will                                !    Throwing good money
                                                            after bad
      eventually lead to
                                                       !    Self-justification
      success
  !   Project manager s
      previous experience
  !   Emotional attachment


                                                                                  30
Leiden Institute of Advanced Computer Science




Escalation factors (cont d)

  Social factors:                                 Risk of escalation:
  !   Competitive rivalry with                    !   Competition between
      other social groups                             decision-making groups
  !   Needs for external                          !   Staying the course
      justification
  !   Norms for consistency




                                                                           31
Leiden Institute of Advanced Computer Science




Escalation factors (cont d)

  Organizational factors:                         Risk of escalation:
  !   Structural environment                      !   Strong top management
  !   Political environment,                          support
      i.e. top management                         !   Institutionalization
      support
  !   Institutionalization with
      organizational goals
      and values



                                                                          32
Leiden Institute of Advanced Computer Science




Organizational contexts of whistle blowing
                                             Deaf effect
                                Weak                       Strong
                  Weak



                           Healthy                    Ostrich
     Mum effect




                           organization               organization
                  Strong




                           Cover-up                   Deaf-dumb-blind
                           organization               organization


                                                                        33
Leiden Institute of Advanced Computer Science



Organizational contexts of whistle blowing
(cont d)
  !   Mum-effect (reluctance                         !   Deaf-effect (reluctance
      to blow the whistle)                               to hear the whistle)
     !     Risks to own career                            !    Organizational
     !     Fear of reprisals                                   leapfrogging as a remedy
     !     Critical audit may                             !    Executives insulate
           contradict best judgment                            themselves from dealing
           and vested interest of                              with non-urgent problems
           powerful people                                !    Disassociating from
                                                               failing endeavor




                                                                                     34
Leiden Institute of Advanced Computer Science



Implication for project management
practice
  !   IT managers:
     !    Traditional project management approaches build
          on rational philosophy
     !    Expand with behavioral and organizational
          perspective
     !    Recognize tendency to over-commitment
     !    Alternative courses of action




                                                            35
Leiden Institute of Advanced Computer Science



Implication for project management
practice (cont d)
  !   Organizations:
     !    Match project management with development
          stage
     !    Continuous risk assessment
           •  Probability of technical success
           •  Probability of customer acceptance
     !    Serious project audits, e.g. review boards with
          appointed members
     !    Reduce need for self-justification, e.g. by dividing
          initial and subsequent decision-making
                                                                 36

More Related Content

What's hot

Introduction to the CSLP and the SELP
Introduction to the CSLP and the SELPIntroduction to the CSLP and the SELP
Introduction to the CSLP and the SELPStephen Gilmore
 
PM2 ARTICALS
PM2 ARTICALSPM2 ARTICALS
PM2 ARTICALSra na
 
Pm soln9416141129710
Pm soln9416141129710Pm soln9416141129710
Pm soln9416141129710Nikhil Todkar
 
SE_Lec 11_ Project Management
SE_Lec 11_ Project ManagementSE_Lec 11_ Project Management
SE_Lec 11_ Project ManagementAmr E. Mohamed
 
Announcement Letter Synopsys Summer Internship Program
Announcement Letter Synopsys Summer Internship ProgramAnnouncement Letter Synopsys Summer Internship Program
Announcement Letter Synopsys Summer Internship Programchairperson
 
SOFTWARE PROJECT MANAGEMENT TOOL Project Report
SOFTWARE PROJECT MANAGEMENT TOOL Project ReportSOFTWARE PROJECT MANAGEMENT TOOL Project Report
SOFTWARE PROJECT MANAGEMENT TOOL Project ReportSai Charan
 
Kelis king - software engineering and best practices
Kelis king -  software engineering and best practicesKelis king -  software engineering and best practices
Kelis king - software engineering and best practicesKelisKing
 
Immutable principles of project management (austin pmi)(v4)(no exercise)
Immutable principles of project management (austin pmi)(v4)(no exercise)Immutable principles of project management (austin pmi)(v4)(no exercise)
Immutable principles of project management (austin pmi)(v4)(no exercise)Glen Alleman
 

What's hot (13)

Introduction to the CSLP and the SELP
Introduction to the CSLP and the SELPIntroduction to the CSLP and the SELP
Introduction to the CSLP and the SELP
 
Daniel dumitrescu
Daniel dumitrescuDaniel dumitrescu
Daniel dumitrescu
 
2 Process
2 Process2 Process
2 Process
 
33136 eval forms en
33136 eval forms en33136 eval forms en
33136 eval forms en
 
PM2 ARTICALS
PM2 ARTICALSPM2 ARTICALS
PM2 ARTICALS
 
Pm soln9416141129710
Pm soln9416141129710Pm soln9416141129710
Pm soln9416141129710
 
SE_Lec 11_ Project Management
SE_Lec 11_ Project ManagementSE_Lec 11_ Project Management
SE_Lec 11_ Project Management
 
20 54-1-pb
20 54-1-pb20 54-1-pb
20 54-1-pb
 
Announcement Letter Synopsys Summer Internship Program
Announcement Letter Synopsys Summer Internship ProgramAnnouncement Letter Synopsys Summer Internship Program
Announcement Letter Synopsys Summer Internship Program
 
Guide to Software Estimation
Guide to Software EstimationGuide to Software Estimation
Guide to Software Estimation
 
SOFTWARE PROJECT MANAGEMENT TOOL Project Report
SOFTWARE PROJECT MANAGEMENT TOOL Project ReportSOFTWARE PROJECT MANAGEMENT TOOL Project Report
SOFTWARE PROJECT MANAGEMENT TOOL Project Report
 
Kelis king - software engineering and best practices
Kelis king -  software engineering and best practicesKelis king -  software engineering and best practices
Kelis king - software engineering and best practices
 
Immutable principles of project management (austin pmi)(v4)(no exercise)
Immutable principles of project management (austin pmi)(v4)(no exercise)Immutable principles of project management (austin pmi)(v4)(no exercise)
Immutable principles of project management (austin pmi)(v4)(no exercise)
 

Viewers also liked

Stanford Class Presidents, Session One, Feedback
Stanford Class Presidents, Session One, FeedbackStanford Class Presidents, Session One, Feedback
Stanford Class Presidents, Session One, FeedbackEd Batista
 
Decision Making for the Project Leader
Decision Making for the Project LeaderDecision Making for the Project Leader
Decision Making for the Project Leaderrazausman
 
Minco Ruiter, Inforsa. RR Conference workshop 26th June '14
Minco Ruiter, Inforsa. RR Conference workshop 26th June '14Minco Ruiter, Inforsa. RR Conference workshop 26th June '14
Minco Ruiter, Inforsa. RR Conference workshop 26th June '14Restraint Reduction Network
 
Decision Framing in Project Decision-Making
Decision Framing in Project Decision-MakingDecision Framing in Project Decision-Making
Decision Framing in Project Decision-MakingIntaver Insititute
 
PMP - Risk Management plan & template
PMP - Risk Management plan & templatePMP - Risk Management plan & template
PMP - Risk Management plan & templateAllie Gentry
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance StructureSaurabh Sardesai
 

Viewers also liked (7)

Escalation lets do it right
Escalation   lets do it rightEscalation   lets do it right
Escalation lets do it right
 
Stanford Class Presidents, Session One, Feedback
Stanford Class Presidents, Session One, FeedbackStanford Class Presidents, Session One, Feedback
Stanford Class Presidents, Session One, Feedback
 
Decision Making for the Project Leader
Decision Making for the Project LeaderDecision Making for the Project Leader
Decision Making for the Project Leader
 
Minco Ruiter, Inforsa. RR Conference workshop 26th June '14
Minco Ruiter, Inforsa. RR Conference workshop 26th June '14Minco Ruiter, Inforsa. RR Conference workshop 26th June '14
Minco Ruiter, Inforsa. RR Conference workshop 26th June '14
 
Decision Framing in Project Decision-Making
Decision Framing in Project Decision-MakingDecision Framing in Project Decision-Making
Decision Framing in Project Decision-Making
 
PMP - Risk Management plan & template
PMP - Risk Management plan & templatePMP - Risk Management plan & template
PMP - Risk Management plan & template
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance Structure
 

Similar to SDPM - Lecture 6 - Risk management and project escalation

SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project PlanningSDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project PlanningOpenLearningLab
 
SDPM - Lecture 1 - Introduction
SDPM - Lecture 1 - IntroductionSDPM - Lecture 1 - Introduction
SDPM - Lecture 1 - IntroductionOpenLearningLab
 
SDPM - Lecture 7 - Project monitoring and control
SDPM - Lecture 7 - Project monitoring and controlSDPM - Lecture 7 - Project monitoring and control
SDPM - Lecture 7 - Project monitoring and controlOpenLearningLab
 
Project risk management
Project risk managementProject risk management
Project risk managementEr Swati Nagal
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.pptavisha23
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.pptAyidAlmgati
 
PMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.pptPMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.pptDorraLamouchi1
 
Risk management
Risk managementRisk management
Risk managementbipulpwc
 
Project Management Risks Review
Project Management Risks ReviewProject Management Risks Review
Project Management Risks ReviewDavid Tennant
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskMuzette Charles, PMP
 
project_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptproject_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptBetshaTizazu2
 
P&msp2010 07 risk-and-change-management
P&msp2010 07 risk-and-change-managementP&msp2010 07 risk-and-change-management
P&msp2010 07 risk-and-change-managementEmanuele Della Valle
 
Project risk management focus on risk identification techniques
Project risk management   focus on risk identification techniquesProject risk management   focus on risk identification techniques
Project risk management focus on risk identification techniquesMarco De Santis, PMP, CFPP
 
Risk Analysis On It Assets Using Case Based Reasoning
Risk Analysis On It Assets Using Case Based ReasoningRisk Analysis On It Assets Using Case Based Reasoning
Risk Analysis On It Assets Using Case Based ReasoningAfeef Veetil
 
Risk analysis and management
Risk analysis and managementRisk analysis and management
Risk analysis and managementgnitu
 
Risk management(software engineering)
Risk management(software engineering)Risk management(software engineering)
Risk management(software engineering)Priya Tomar
 

Similar to SDPM - Lecture 6 - Risk management and project escalation (20)

SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project PlanningSDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
 
SDPM - Lecture 1 - Introduction
SDPM - Lecture 1 - IntroductionSDPM - Lecture 1 - Introduction
SDPM - Lecture 1 - Introduction
 
SDPM - Lecture 7 - Project monitoring and control
SDPM - Lecture 7 - Project monitoring and controlSDPM - Lecture 7 - Project monitoring and control
SDPM - Lecture 7 - Project monitoring and control
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Pmp risk management
Pmp risk managementPmp risk management
Pmp risk management
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.ppt
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.ppt
 
PMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.pptPMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.ppt
 
Risk management
Risk managementRisk management
Risk management
 
Project Management Risks Review
Project Management Risks ReviewProject Management Risks Review
Project Management Risks Review
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
project_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptproject_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.ppt
 
P&msp2010 07 risk-and-change-management
P&msp2010 07 risk-and-change-managementP&msp2010 07 risk-and-change-management
P&msp2010 07 risk-and-change-management
 
Project risk management focus on risk identification techniques
Project risk management   focus on risk identification techniquesProject risk management   focus on risk identification techniques
Project risk management focus on risk identification techniques
 
Risk Analysis On It Assets Using Case Based Reasoning
Risk Analysis On It Assets Using Case Based ReasoningRisk Analysis On It Assets Using Case Based Reasoning
Risk Analysis On It Assets Using Case Based Reasoning
 
Unit 7
Unit 7Unit 7
Unit 7
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Overview in Project Manager Role
Overview in Project Manager Role Overview in Project Manager Role
Overview in Project Manager Role
 
Risk analysis and management
Risk analysis and managementRisk analysis and management
Risk analysis and management
 
Risk management(software engineering)
Risk management(software engineering)Risk management(software engineering)
Risk management(software engineering)
 

More from OpenLearningLab

Requirements Engineering - Werkcollege 2012: 05-Estimating+Planning
Requirements Engineering - Werkcollege 2012: 05-Estimating+PlanningRequirements Engineering - Werkcollege 2012: 05-Estimating+Planning
Requirements Engineering - Werkcollege 2012: 05-Estimating+PlanningOpenLearningLab
 
Requirements Engineering - Werkcollege 2012: 04-Documentation
Requirements Engineering - Werkcollege 2012: 04-DocumentationRequirements Engineering - Werkcollege 2012: 04-Documentation
Requirements Engineering - Werkcollege 2012: 04-DocumentationOpenLearningLab
 
Requirements Engineering - Werkcollege 2012: 03-Elicitation
Requirements Engineering - Werkcollege 2012: 03-ElicitationRequirements Engineering - Werkcollege 2012: 03-Elicitation
Requirements Engineering - Werkcollege 2012: 03-ElicitationOpenLearningLab
 
Requirements Engineering - Werkcollege 2012: 02-Stakeholders
Requirements Engineering - Werkcollege 2012: 02-StakeholdersRequirements Engineering - Werkcollege 2012: 02-Stakeholders
Requirements Engineering - Werkcollege 2012: 02-StakeholdersOpenLearningLab
 
Re werkcollege12-02-stakeholders
Re werkcollege12-02-stakeholdersRe werkcollege12-02-stakeholders
Re werkcollege12-02-stakeholdersOpenLearningLab
 
Requirements Engineering - Werkcollege 2012: 01-introduction
Requirements Engineering - Werkcollege 2012: 01-introductionRequirements Engineering - Werkcollege 2012: 01-introduction
Requirements Engineering - Werkcollege 2012: 01-introductionOpenLearningLab
 
Managing Innovation_innovation governance
Managing Innovation_innovation governanceManaging Innovation_innovation governance
Managing Innovation_innovation governanceOpenLearningLab
 
Managing Innovation_innovation system
Managing Innovation_innovation systemManaging Innovation_innovation system
Managing Innovation_innovation systemOpenLearningLab
 
Managing Innovation_entrepreneurship and transformation
Managing Innovation_entrepreneurship and transformation Managing Innovation_entrepreneurship and transformation
Managing Innovation_entrepreneurship and transformation OpenLearningLab
 
Managing Innovation_organization of innovation
Managing Innovation_organization of innovationManaging Innovation_organization of innovation
Managing Innovation_organization of innovationOpenLearningLab
 
Managing Innovation_innovation concepts
Managing Innovation_innovation conceptsManaging Innovation_innovation concepts
Managing Innovation_innovation conceptsOpenLearningLab
 
Managing Innovation_Introduction to Innovation
Managing Innovation_Introduction to InnovationManaging Innovation_Introduction to Innovation
Managing Innovation_Introduction to InnovationOpenLearningLab
 
SDPM - Lecture 9 - Managing people and organizing teams
SDPM - Lecture 9 - Managing people and organizing teamsSDPM - Lecture 9 - Managing people and organizing teams
SDPM - Lecture 9 - Managing people and organizing teamsOpenLearningLab
 
SDPM - Lecture 2a - Project evaluation – for the buyer, and for the vendor
SDPM - Lecture 2a - Project evaluation – for the buyer, and for the vendorSDPM - Lecture 2a - Project evaluation – for the buyer, and for the vendor
SDPM - Lecture 2a - Project evaluation – for the buyer, and for the vendorOpenLearningLab
 
Research Seminar - Thesis Projects for ICTiB
Research Seminar - Thesis Projects for ICTiBResearch Seminar - Thesis Projects for ICTiB
Research Seminar - Thesis Projects for ICTiBOpenLearningLab
 
Session09 corporate andsocialentrepreneurship
Session09 corporate andsocialentrepreneurshipSession09 corporate andsocialentrepreneurship
Session09 corporate andsocialentrepreneurshipOpenLearningLab
 
Session08 entrepreneurship andtransformation
Session08 entrepreneurship andtransformationSession08 entrepreneurship andtransformation
Session08 entrepreneurship andtransformationOpenLearningLab
 
Session06 introduction totheoryofentrepreneurship
Session06 introduction totheoryofentrepreneurshipSession06 introduction totheoryofentrepreneurship
Session06 introduction totheoryofentrepreneurshipOpenLearningLab
 
Session05 innovation governance
Session05 innovation governanceSession05 innovation governance
Session05 innovation governanceOpenLearningLab
 
Session04 innovation system
Session04 innovation systemSession04 innovation system
Session04 innovation systemOpenLearningLab
 

More from OpenLearningLab (20)

Requirements Engineering - Werkcollege 2012: 05-Estimating+Planning
Requirements Engineering - Werkcollege 2012: 05-Estimating+PlanningRequirements Engineering - Werkcollege 2012: 05-Estimating+Planning
Requirements Engineering - Werkcollege 2012: 05-Estimating+Planning
 
Requirements Engineering - Werkcollege 2012: 04-Documentation
Requirements Engineering - Werkcollege 2012: 04-DocumentationRequirements Engineering - Werkcollege 2012: 04-Documentation
Requirements Engineering - Werkcollege 2012: 04-Documentation
 
Requirements Engineering - Werkcollege 2012: 03-Elicitation
Requirements Engineering - Werkcollege 2012: 03-ElicitationRequirements Engineering - Werkcollege 2012: 03-Elicitation
Requirements Engineering - Werkcollege 2012: 03-Elicitation
 
Requirements Engineering - Werkcollege 2012: 02-Stakeholders
Requirements Engineering - Werkcollege 2012: 02-StakeholdersRequirements Engineering - Werkcollege 2012: 02-Stakeholders
Requirements Engineering - Werkcollege 2012: 02-Stakeholders
 
Re werkcollege12-02-stakeholders
Re werkcollege12-02-stakeholdersRe werkcollege12-02-stakeholders
Re werkcollege12-02-stakeholders
 
Requirements Engineering - Werkcollege 2012: 01-introduction
Requirements Engineering - Werkcollege 2012: 01-introductionRequirements Engineering - Werkcollege 2012: 01-introduction
Requirements Engineering - Werkcollege 2012: 01-introduction
 
Managing Innovation_innovation governance
Managing Innovation_innovation governanceManaging Innovation_innovation governance
Managing Innovation_innovation governance
 
Managing Innovation_innovation system
Managing Innovation_innovation systemManaging Innovation_innovation system
Managing Innovation_innovation system
 
Managing Innovation_entrepreneurship and transformation
Managing Innovation_entrepreneurship and transformation Managing Innovation_entrepreneurship and transformation
Managing Innovation_entrepreneurship and transformation
 
Managing Innovation_organization of innovation
Managing Innovation_organization of innovationManaging Innovation_organization of innovation
Managing Innovation_organization of innovation
 
Managing Innovation_innovation concepts
Managing Innovation_innovation conceptsManaging Innovation_innovation concepts
Managing Innovation_innovation concepts
 
Managing Innovation_Introduction to Innovation
Managing Innovation_Introduction to InnovationManaging Innovation_Introduction to Innovation
Managing Innovation_Introduction to Innovation
 
SDPM - Lecture 9 - Managing people and organizing teams
SDPM - Lecture 9 - Managing people and organizing teamsSDPM - Lecture 9 - Managing people and organizing teams
SDPM - Lecture 9 - Managing people and organizing teams
 
SDPM - Lecture 2a - Project evaluation – for the buyer, and for the vendor
SDPM - Lecture 2a - Project evaluation – for the buyer, and for the vendorSDPM - Lecture 2a - Project evaluation – for the buyer, and for the vendor
SDPM - Lecture 2a - Project evaluation – for the buyer, and for the vendor
 
Research Seminar - Thesis Projects for ICTiB
Research Seminar - Thesis Projects for ICTiBResearch Seminar - Thesis Projects for ICTiB
Research Seminar - Thesis Projects for ICTiB
 
Session09 corporate andsocialentrepreneurship
Session09 corporate andsocialentrepreneurshipSession09 corporate andsocialentrepreneurship
Session09 corporate andsocialentrepreneurship
 
Session08 entrepreneurship andtransformation
Session08 entrepreneurship andtransformationSession08 entrepreneurship andtransformation
Session08 entrepreneurship andtransformation
 
Session06 introduction totheoryofentrepreneurship
Session06 introduction totheoryofentrepreneurshipSession06 introduction totheoryofentrepreneurship
Session06 introduction totheoryofentrepreneurship
 
Session05 innovation governance
Session05 innovation governanceSession05 innovation governance
Session05 innovation governance
 
Session04 innovation system
Session04 innovation systemSession04 innovation system
Session04 innovation system
 

Recently uploaded

Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)cama23
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationRosabel UA
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
Food processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsFood processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsManeerUddin
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptxmary850239
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 

Recently uploaded (20)

Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translation
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
Food processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture honsFood processing presentation for bsc agriculture hons
Food processing presentation for bsc agriculture hons
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 

SDPM - Lecture 6 - Risk management and project escalation

  • 1. Leiden Institute of Advanced Computer Science System s Development and Project Management – Risk management and project escalation Prof. Dr. Thomas Bäck 1
  • 2. Leiden Institute of Advanced Computer Science Dates Feb. 1 14:45 – 17:30 Introduction, Project Description Feb. 2 13:45 – 16:30 STEP WISE Approach to Project Planning Feb. 9 13:10 – 15:45 STEP WISE Approach to Project Planning, SAVE ENERGY Case Feb. 15 14:45 – 17:30 Selecting an Appropriate Software Dev. Approach Feb. 16 15:15 – 18:00 Activity Planning and Resource Allocation Feb. 22 14:45 – 17:30 Software Effort Estimation Feb. 23 13:15 – 15:45 Risk management, project escalation Mar. 1 14:45 – 17:00 Exam Mar. 2 13:45 – 16:30 Risk Management, Project monitoring and control Mar. 8 14:45 – 17:30 Software Quality Assurance Mar. 9 13:45 – 16:30 Managing People; Contract Management Mar. 18 15:00 – 17:00 Trade Fair 2
  • 3. Leiden Institute of Advanced Computer Science Deliverable Planning February 18, midnight Assignment 1: Project proposal ( bid ) February 25, midnight Assignment 2: Project Plan including functional specification March 7, midnight Assignment 3: Deutsche Bank case, 5 ppt slides March 1 (14:45 – 17:00) Exam March 18 (15:00 – 17:00) Trade fair, Plantsoen 97, Leiden (setup from 14:00) March 18, midnight Assignment 4: Personal reflection paper on project management 3
  • 4. Leiden Institute of Advanced Computer Science STEP WISE overview 1. Identify project objectives 0. Select Project 2. Identify project infrastructure 3. Analyze pr. characteristics 4. Identify products and activities Review lower level detail 5. Estimate effort for activity For each activity 6. Identify activity risks 10. Lower level planning 7. Allocate resources 9. Execute plan 8. Review / publicize plan 4
  • 5. Leiden Institute of Advanced Computer Science Evaluation !   Not unusual to spend between 6-12 months and 40% of total acquisition and implementation cost on package evaluation with major customers. !   Make or buy? !  Buying is attractive when money available but other resources are short. !  Hazards, because staff time and attention is needed to manage such projects successfully. 5
  • 6. Leiden Institute of Advanced Computer Science Nature of risk !   Describes non-desirable events or outcomes (vs. opportunities) !   Risk management concerned with: !  Events or hazards !  Outcomes or problems !  Action plans !   Includes assessment of likelihoods, seriousness, costs and effectiveness of action 6
  • 7. Leiden Institute of Advanced Computer Science Types of risk !   Caused by estimation difficulties !  Some tasks are more difficult to estimate !   Caused by assumptions made during planning process !  Important to continuously list all assumptions and their likely effects !   Eventualities: Unforeseen hazards occurring !  Reduction through sound planning 7
  • 8. Leiden Institute of Advanced Computer Science Managing risk Boehm s risk engineering task breakdown Risk engineering Risk Risk analysis management Risk Risk estimation Risk evaluation identification Risk planning Risk control Risk monitoring Risk directing Risk staffing 8
  • 9. Leiden Institute of Advanced Computer Science Managing risk (cont d) !   Risk analysis: !  Risk identification - listing all hazards which could affect project !  Risk estimation - likelihood and severeness of hazards !  Risk evaluation - ranking and determination of risk aversion strategies 9
  • 10. Leiden Institute of Advanced Computer Science Managing risk (cont d) !   Risk management: !  Risk planning – drawing up contingency plans !  Risk control – quality control and dealing with emergent problems !  Risk monitoring – an ongoing activity !  Risk directing Day-to-day risk management !  Risk staffing 10
  • 11. Leiden Institute of Advanced Computer Science Hazard identification !   Application factors !   Staff factors !   Project factors Factors should be !   Project methods considered for each !   Hardware/software activity individually, factors involving the whole !   Changeover factors project team !   Supplier factors !   Environment factors !   Health and safety factors 11
  • 12. Leiden Institute of Advanced Computer Science Hazard analysis !   Most favored ranking method is to calculate risk exposure !  Risk exposure RE = risk likelihood * risk impact !   Alternative - scoring methods: !  Likelihood !  Impact !  Timeframe 12
  • 13. Leiden Institute of Advanced Computer Science Hazard analysis (cont d) !   Risk prioritization !  Reducing risk exposure by decreasing likelihood and/or impact !  Contingency plans !   Risk reduction leverage (RRL) !  RRL=(REbefore-REafter)/risk reduction cost !  Monetary values recommended !  RRL > 1: We can gain from implementing the risk reduction plan 13
  • 14. Leiden Institute of Advanced Computer Science Risk planning and control !   Hazard prevention !   Likelihood reduction !   Risk avoidance !   Risk transfer !   Contingency planning 14
  • 15. Leiden Institute of Advanced Computer Science Evaluating schedule risks !   In contrast to CPM, PERT requires three estimates: !  Most likely time (m) !  Optimistic time (a) !  Pessimistic time (b) !   Activity-on-arrow diagram !   te=(a+4m+b)/6, s=(b-a)/6, z=(T- te)/s !   Expected duration te, s-dev s., no. of s-dev.s between target and expected date z 15
  • 16. Leiden Institute of Advanced Computer Science Notation Event number Target date Standard Expected date deviation 16
  • 17. Leiden Institute of Advanced Computer Science Evaluating schedule risks (cont d) 1.  Use expected durations for forward pass 2.  Calculate standard deviations for each project event (add squares and find square root of sum) 3.  Calculate z-values - number of standard deviations between expected and target dates If there are several possible 4.  Convert z-values to probabilities largest standard Paths: take deviation 17
  • 18. Leiden Institute of Advanced Computer Science Example: Convert to activity-on-arrow diagram! B E Duration 6 Duration 8 A C G Duration 5 Duration 10 F Duration 4 D Duration 3 ES = day 0 Duration 9 18
  • 19. Leiden Institute of Advanced Computer Science Example: (now activity on arrow!) 3 B=6 6 E 8 8 10 G 11 1 A 2 C 4 0 5 10 4 7 F 9 D=9 3 5 19
  • 20. Leiden Institute of Advanced Computer Science Optimistic time Most likely time Complete the table Pessimistic time Activity   a   m   b   te   s   z   T   Prob.   A   4   5   6             B   4   6   8             C   9   10   12             D   8   9   10             E   5   8   11             F   1   3   4             G   3   4   5             20
  • 21. Leiden Institute of Advanced Computer Science Example: t_e and standard deviations E 3 t=8 B G A t=6 s=1 t=4 t=5 s=0.67 6 8 s=0.33 s=0.33 1 2 10 11 C 4 t=10.17 0 s=0.5 7 9 5 F D t=2.83 9 s=0.5 s=0.33 21
  • 22. Leiden Institute of Advanced Computer Science (a+4m+b)/6 Complete the table (b-a)/6 Activit a m b te s z T Prob y . A 4 5 6 5 0.33 B 4 6 8 6 0.67 C 9 10 12 10.17 0.5 D 8 9 10 9 0.33 E 5 8 11 8 1 F 1 3 4 2.83 0.5 G 3 4 5 4 0.33 22
  • 23. Leiden Institute of Advanced Computer Science Example: Expected dates E 3 t=8 B G A t=6 s=1 t=4 11 t=5 s=0.67 6 8 s=0.33 s=0.33 15.17 23.17 10 11 1 2 C 4 t=10.17 23.17 27.17 0 5 15.17 s=0.5 7 9 14 16.83 5 F D t=2.83 9 14 s=0.5 s=0.33 23
  • 24. Leiden Institute of Advanced Computer Science Example: Cumulative standard deviations E 3 t=8 B G A t=6 s=1 t=4 11 0.75 t=5 s=0.67 6 8 s=0.33 s=0.33 15.17 0.75 23.17 1.25 10 11 1 2 C 4 t=10.17 23.17 1.25 27.17 1.29 0 5 0.33 15.17 0.6 s=0.5 7 9 14 0.75 16.83 0.9 5 F D t=2.83 9 14 0.47 s=0.5 s=0.33 24
  • 25. Leiden Institute of Advanced Computer Science Evaluating schedule risks (cont d) !   Monte Carlo simulation as an alternative !  Calculates large number of activity completion dates !  Random selection of activity times from set of estimates !  Input depending on available information, e.g. historic project information !  Output can take form of graphs and summaries !   Specialized software packages available !  Interfaces to project planning and spreadsheet software !  Cost, resource, and duration estimates 25
  • 26. Leiden Institute of Advanced Computer Science ICT project management 'runaways’… !   Standish "Chaos" report !  1994: •  16% success, •  31% cancelled •  53% challenged !  2000: •  34% successful •  15% cancelled •  51% challenged 26
  • 27. Leiden Institute of Advanced Computer Science Project Management & Success !  Technical issues challenged !   Hardware/software/telecommunications systems 51% don't work !   Frequent failure/errors in operation cancelled 15% !  Economic issues !   Time or budget overrun success !   Low/no ROI ( productivity paradox ) 34% !  Organizational (implementation) issues !   Resulting system fails to achieve desired benefit !   Users reject system
  • 28. Leiden Institute of Advanced Computer Science Project Escalation !   Continued commitment in the face of negative information about prior resource allocations coupled with uncertainty surrounding the likelihood of goal attainment (Brockner, 1992) Project Social Factors Factors Project Escalation Psychol. Organiz. Factors Factors 28
  • 29. Leiden Institute of Advanced Computer Science Escalation factors Project factors: Risk of escalation: !   Objective features of !   Large potential payoff the project !   Long-term investment !   Perception by to reap gains management !   Setbacks perceived as !   Costs and benefits temporary problems associated with the project !   Difficulties (risk) and duration 29
  • 30. Leiden Institute of Advanced Computer Science Escalation factors (cont d) Psychological factors: Risk of escalation: !   „Things do not look that !   Errors in processing bad information !   Continuation will !  Throwing good money after bad eventually lead to !  Self-justification success !   Project manager s previous experience !   Emotional attachment 30
  • 31. Leiden Institute of Advanced Computer Science Escalation factors (cont d) Social factors: Risk of escalation: !   Competitive rivalry with !   Competition between other social groups decision-making groups !   Needs for external !   Staying the course justification !   Norms for consistency 31
  • 32. Leiden Institute of Advanced Computer Science Escalation factors (cont d) Organizational factors: Risk of escalation: !   Structural environment !   Strong top management !   Political environment, support i.e. top management !   Institutionalization support !   Institutionalization with organizational goals and values 32
  • 33. Leiden Institute of Advanced Computer Science Organizational contexts of whistle blowing Deaf effect Weak Strong Weak Healthy Ostrich Mum effect organization organization Strong Cover-up Deaf-dumb-blind organization organization 33
  • 34. Leiden Institute of Advanced Computer Science Organizational contexts of whistle blowing (cont d) !   Mum-effect (reluctance !   Deaf-effect (reluctance to blow the whistle) to hear the whistle) !  Risks to own career !  Organizational !  Fear of reprisals leapfrogging as a remedy !  Critical audit may !  Executives insulate contradict best judgment themselves from dealing and vested interest of with non-urgent problems powerful people !  Disassociating from failing endeavor 34
  • 35. Leiden Institute of Advanced Computer Science Implication for project management practice !   IT managers: !  Traditional project management approaches build on rational philosophy !  Expand with behavioral and organizational perspective !  Recognize tendency to over-commitment !  Alternative courses of action 35
  • 36. Leiden Institute of Advanced Computer Science Implication for project management practice (cont d) !   Organizations: !  Match project management with development stage !  Continuous risk assessment •  Probability of technical success •  Probability of customer acceptance !  Serious project audits, e.g. review boards with appointed members !  Reduce need for self-justification, e.g. by dividing initial and subsequent decision-making 36