Good neighbourly relations committee meeting - Brossard - January 25, 2017

149 views

Published on

- Follow up on the various files under the responsibility of Infrastructure Canada : anti-noise wall and DEL lightning
- Provide information about the work that has been completed, is underway and planned between now and July 2017
- Answer questions, find potential solutions and discuss the issues

Published in: Engineering
  • Be the first to comment

  • Be the first to like this

Good neighbourly relations committee meeting - Brossard - January 25, 2017

  1. 1. Good Neighbourly Relations Committee Meeting City of Brossard : 25 january 2017 New Champlain Bridge Corridor Project Centre communautaire Nathalie Croteau Please note that the English version is used only for refernce purposes. In case of disrepancy between the English and French versions, the French version shall prevail.
  2. 2. Projet de corridor du nouveau pont Champlain 2 Committee Members Residents Luis Oscar Corrales Ginette Dufresne Marc Gagné Nabil Halouani Jacques Picard Jaime Reis Marc Turcotte – Representative from a community organization Éric Jutras – Member of the business community Partners Dan Genest – The Signature on the Saint-Laurent team Benoît Fillion – City of Brossard Vincent Jarry – Infrastructure Canada
  3. 3. Projet de corridor du nouveau pont Champlain 1. Follow up on the various files under the responsibility of Infrastructure Canada : anti-noise wall and DEL lightning 2. Provide information about the work that has been completed, is underway and planned between now and July 2017 3. Answer questions, find potential solutions and discuss the issues Objectives of the Meeting 3
  4. 4. Projet de corridor du nouveau pont Champlain Agenda 4 Série Item Durée Heure 1. Opening 10 min. 19h00 à 19h10 2. Anti-noise wall : update 20 min. 19h10 à 19h30 3. Question period 10 min. 19h30 à 19h40 4. Work completed, underway and to come • Eastern approach area • Hwy-10 area • Cable-stayed bridge area 40 min. 19h40 à 20h20 5. Question period 20 min. 20h20 à 20h40 6. Varia 15 min. 20h40 à 20h55 7. Adjournment: next meeting and topic 5 min. 20h55 à 21h00
  5. 5. Projet de corridor du nouveau pont Champlain Work Completed over the Past Few Months
  6. 6. Projet de corridor du nouveau pont Champlain Survol des travaux complétés 6 • Fall season: solid work progress in general on the East Approach  Construction of footings and pier bases completed  Beginning of installation of prefabricated segments of piers and pier caps  Continue the construction of the east abutment • Installation of the new construction site exit • Very few complaints, mainly about the new construction site exit (5 on 8)
  7. 7. Projet de corridor du nouveau pont Champlain Impacts: new construction site exit 7 Impact sonore Visual impactMobility impact Noise impactOpening of the new construction site exit Duration : 3 years Period : 2017 à 2019 • No incidents recorded or reported • Flow rate : 75 to 150 car / day 10 à 30 car/ night • Installation of a visual screen • Visible beacon • Below the 75 dBA criteria • Exceedance caused by traffic on the upper road network
  8. 8. Projet de corridor du nouveau pont Champlain Noise Impact 8 Noise tracking at 7070 Place Turenne in Brossard Soundlevel(dBa) Noise limit
  9. 9. Projet de corridor du nouveau pont Champlain Community relations 9 • Presentation at the Club Optimiste Clamplain-Brossard: 1st November 2016 • Presentation in a primary school in Saint-Lambert : 2 December 2016 • Presentation at Association des gens d’affaires de Brossard : 7 December 2016
  10. 10. Projet de corridor du nouveau pont Champlain A great achievement of our workers ›Dons
  11. 11. Projet de corridor du nouveau pont Champlain Complaints Handling (April 29 to September 20, 2016) Thématique Brossard Fermées Ouvertes Total Noise 2 1 3 Air Quality 2 - 2 Traffic 3 - 3 Vibrations - - - Brightness 2 - 2 Other - - - Total 9 1 10 11 Eight complaints in the previous period from April 30 to September 20, 2016
  12. 12. Projet de corridor du nouveau pont Champlain Main Priorities for the Upcoming Months- South Shore
  13. 13. Projet de corridor du nouveau pont Champlain Location of Work Areas City of Brossard Cable-stayed bridge
  14. 14. Projet de corridor du nouveau pont Champlain Highway 10 • Soil management • Preparatory works for the configuration of the highway 10 East Approch • Installation of prefabricated segments of piers and pier caps • Continue the construction of the east abutment, including the building housing the electric systems • Preparations for the construction of the span above Route 132 Cable-stayed bridge • Construction of main pylon and rear span South Shore Priorities : January to June 2017 14
  15. 15. Projet de corridor du nouveau pont Champlain Description of Activity Approximate Duration of Works Planned Work Period Legend: Work and Impacts • Traffic and Public Transportation: • Proximity of Residential Areas: • Boating: • Bike Paths: Minor impact Medium impact Major impact Indication by level colour code 15
  16. 16. Projet de corridor du nouveau pont Champlain Key Activities Underway and to Come - East Approach Design and planning underway so modifications are possible
  17. 17. Projet de corridor du nouveau pont Champlain Objective: Construction of East Approach of the new Champlain Bridge Travaux en cours et à venir : • Placement of prefabricated segments of piers and pier caps • Continue the construction of the abutment, including the building housing the electric systems • Preparatory works for the construction of the span above Highway 132 Approach: • Daytime work, to the extent possible, when the impacts (especially noise levels) are significant • Nighttime work, to the extent possible, when the impacts on daytime traffic are too significant East Approach Area 17
  18. 18. Projet de corridor du nouveau pont Champlain Nov 2015 May Nov 2016 May Nov. 2017 Nov 2018 May East Approach: Timetable 18 Feb 2016 Aug Feb 2017 Aug. Feb. 2018 Aug. Construction of footings and pier bases Installation of piers and pier caps Assembly of superstructure and deck Finishing work
  19. 19. Projet de corridor du nouveau pont Champlain Works and Impacts: East Approach 19 Placement of prefabricated segments of piers and pier caps Duration: eight months Projected period: October 2016 to Summer 2017
  20. 20. Projet de corridor du nouveau pont Champlain Works and Impacts: East Approach 20 Construction of East Abutment’s building Duration: four months Projected period: April to July 2017
  21. 21. Projet de corridor du nouveau pont Champlain Works and Impacts: East Approach Preparatory works for the construction of the span above Highway 132 Duration : four months Projected period: april to july 2017 21
  22. 22. Projet de corridor du nouveau pont Champlain Key Activities Underway and to Come Highway 10 Conception et planification en développement donc des modifications sont possibles
  23. 23. Projet de corridor du nouveau pont Champlain Highway 10 Area 23 Objective: Area reserved for soil management for the work site and preparatory work for the reconfiguration of highway links Work underway: • Soil storage • Earthworks at the eastern abutment • Creation of a retaining basin for permanent drainage Upcoming Works • Installation of permanent anti-noise walls Approach: • Daytime work, to the extent possible, when the impacts (especially noise levels) are significant • Night-time trucking from the West Approach to the East Approach
  24. 24. Projet de corridor du nouveau pont Champlain Works and Impacts: Highway 10 Soil management and creation of a retaining basin Duration: throughout the project Projected period: 2016 to 2019 24
  25. 25. Projet de corridor du nouveau pont Champlain Works and Impacts: Highway 10 Earthworks at the eastern abutment Duration: one year Projected period: April 2016 to Spring 2017 25
  26. 26. Projet de corridor du nouveau pont Champlain Works and Impacts: Highway 10 Installation of permanent anti-noise walls Duration : three months Projected period: summer / fall 2017 26
  27. 27. Projet de corridor du nouveau pont Champlain Key Activities Underway and to Come Cable-stayed Bridge Design and planning underway so modifications are possible
  28. 28. Projet de corridor du nouveau pont Champlain Cable-stayed Bridge: Timetable 28 2. Pylon foundations October 2015 to April 20161. Jetty August to October 2015 7. Main span March 2017 to September 2018 3. Rear span November 2015 to July 2017 6. Upper pylon February to December 2017 4. Lower pylon May to October 2016 5. Lower crossbeam October to February 2017
  29. 29. Projet de corridor du nouveau pont Champlain Key activities since fall 2016 29 Construction of the lower pylon and the rear span
  30. 30. Projet de corridor du nouveau pont Champlain Key activities since fall 2016 Installation of the lower crossbeam
  31. 31. Projet de corridor du nouveau pont Champlain Works and impacts : Bike path of the seaway dike 31 Ponctual closing of variable duration for the seasons 2017 and 2018 et, if necessary, long term closing Communication strategy : bike path signs, newspaper, e-mail alerts and signalers
  32. 32. Projet de corridor du nouveau pont Champlain Anticipated Impacts
  33. 33. Projet de corridor du nouveau pont Champlain Anticipated impacts • Road traffic • Noise • Air quality 33
  34. 34. Projet de corridor du nouveau pont Champlain Traffic • Disruptions to come • Upcoming major disruptions for the Spring / Summer 2017 : installation of superstructure and deck above Highway 132 traffic lanes 34 Configuration – Disruptions Schedule Duration Installation of foundations and temporary scaffolding March / April 2017 1 week Passage of pier caps pieces May 2017 8 nights Route Deviation from route 132 & boul. Marie-Victorin May 2017 2 years
  35. 35. Projet de corridor du nouveau pont Champlain Passage of Pier Caps Pieces 35
  36. 36. Projet de corridor du nouveau pont Champlain Steel Pier Caps 36
  37. 37. Projet de corridor du nouveau pont Champlain 37 B1: Turenne area B2: Voltaire area B3: Tisserand area Noise Management Area Activity Period D/E/N Exposed sensitive area Ambient noise dBA Criterion dBA Estimated noise dBA Required measures D B1/B2 60/62 75 62/63 Not required Construction of building (east abutment) D B2 62 75 66 Not required Placement of prefabricated segments of piers and pier caps D/E-N B2 62 75/67 To come A10 Earthworks at the Eastern Abutment D B2 62 75 Cable- stayed Miscellaneous work D B1/B2 60/62 75 61/64 Not required EastApproach D B2 62 75 Preparatory works Highway 132 To come Installation of permanent anti- noise walls Monitoring required 73 Monitoring required 75
  38. 38. Projet de corridor du nouveau pont Champlain Air Quality Management • Migitation measures : increased environmental monitoring + Frequent water spaying and cleaning • Regulatory framework : Contractual environmental obligations and Clean Air Regulation (CAR) Applicable MDDELCC standards MDDELCC CAR PMt PM2.5 120 ug/m3 30 ug/m3 38
  39. 39. Projet de corridor du nouveau pont Champlain Follow-up on Interventions 39 SSL • Follow-up on the impacts of the new site exit • Date for the installations of anti-noise walls • Landscaping and building of the east abutment Ville de Brossard • Communications regarding the detour for cyclists during the reconstruction of Panama INFC (discuss previously) • Follow-up on the anti-noise walls • LED lighting tracking
  40. 40. Projet de corridor du nouveau pont Champlain Next meetings
  41. 41. Projet de corridor du nouveau pont Champlain Good Neighbourly Relations Committee :  10 or 17 may (to be confirmed)  Topics:  Mobility  Landscaping A site visit is planned for Friday 5 May in the afternoon Next meetings 41
  42. 42. Projet de corridor du nouveau pont Champlain • Newsletter: sign up online • Information sheets delivered to residents’ homes, if required, and notices in local newspapers • Sign up / contact us:  Website: www.newchamplain.ca  Email: info@sslc.ca  Phone us at: (514) 876-1020  Twitter: @NOUV_CHAMPLAIN Communication 42

×