Bud Blancher TrailAugust 17, 2012
Background•  2009 Eatonville Trails Plan•  Bud Blancher and Koch Family Donation:   $500,000•  RCO Grant: $700,000 award r...
Bud Blancher Trail Location
Phase 1: Volunteer Project
Phase 1: Volunteer Project
Phase 2: To Be Bid
Phase 2: Little Mashel BankStabilization and Enhancement
Phase 2: Little Mashel BankStabilization and Enhancement
Phase 2: MashelRiver Bridge •  Use existing    abutments •  Remove old bridge    pier from center of    river •  Install p...
Phase 2: Mashel River Bridge
Trail Section
Project Schedule•  Volunteer Project Phase 1 – September 8, 2012•  Complete Design on Phase 2 – October 2012•  Phase 2 Per...
Bud Blancher Trail Construction, Eatonville 2012
Upcoming SlideShare
Loading in …5
×

Bud Blancher Trail Construction, Eatonville 2012

1,221 views

Published on

Presentation given by Nick Bond, Town Planner of Eatonville

Published in: Technology, Sports
  • Be the first to comment

  • Be the first to like this

Bud Blancher Trail Construction, Eatonville 2012

  1. 1. Bud Blancher TrailAugust 17, 2012
  2. 2. Background•  2009 Eatonville Trails Plan•  Bud Blancher and Koch Family Donation: $500,000•  RCO Grant: $700,000 award requiring a $702,000 match•  Eatonville required to come up with matching funds including in kind contributions totaling $202,000•  Total Project Cost: $1,402,000
  3. 3. Bud Blancher Trail Location
  4. 4. Phase 1: Volunteer Project
  5. 5. Phase 1: Volunteer Project
  6. 6. Phase 2: To Be Bid
  7. 7. Phase 2: Little Mashel BankStabilization and Enhancement
  8. 8. Phase 2: Little Mashel BankStabilization and Enhancement
  9. 9. Phase 2: MashelRiver Bridge •  Use existing abutments •  Remove old bridge pier from center of river •  Install prefabricated bridge to minimize disturbance
  10. 10. Phase 2: Mashel River Bridge
  11. 11. Trail Section
  12. 12. Project Schedule•  Volunteer Project Phase 1 – September 8, 2012•  Complete Design on Phase 2 – October 2012•  Phase 2 Permitting – In progress – Complete by May 2013•  Bid Phase 2 Project – January 2013•  Phase 2 construction start date – June 2013

×