  1. 1. HPP USTIKOLINA Sarajevo, May 2017
  2. 2. 2 Location
  3. 3. 3 Basic Technical data HPP Ustikolina based on Preliminary Design Normal (maximum) back water level 373,0 m.a.s.l. Usable reservoar capacity 2,70 x 10 hm³ Length of reservoar 9,35 km Height od dam above natural ground 19,00 m Width of dam in weir crest 15,00 m Length of dam in weir crest 207,50m Installed flow 450,00 m³/s Designed head 14,50 m Number of units 3 Maximum power of the power plant 60,48 MW Annual production of el. energy 236,80 GWh
  4. 4. HPP Ustikolina – description of the plant 4  HPP Ustikolina is run- of river hydropower plant with small reservoar and the power house in the dam body  Investment cost in construction is 141,17 mil EUR  The location of the dam is: 14 km upstream of Goražde and 16 km downstream of Foča  HPP Ustikolina is located in two municipalities, municipality Foča-Ustikolina, and municipality Goražde
  5. 5. Decision of the Government of F BiH and completition of Project Documentation 5  Decision of the Government of F BiH, The public interest for the preparation and construction of priority electricity facilities in the F BiH , including HPP Ustikolina  2009 signed Contract for the Preliminary design of HPP Ustikolina, with the Company "Energoinvest" dd Sarajevo  Preliminary Design- I Phase is completed with no research works  Continuation of the project is not possible without research works, environmental permit, urban planning permit and other approvals
  6. 6. 6  Securing our own energy source for electricity supply of Bosnian-Podrinje Goražde Canton  Increase in stability of electricity supply in the region  This significant investment will contribue to economic growth and development of municipalities Foča-Ustikolina and Goražde, Bosnian-Podrinje Goražde Canton and F BiH  Increase in percentage of participation of electricity production from hydro potential, from renewable energy resurces and contribution to the total decreasing in CO2, NOx emissions  Employing domestic workforce during construction and operation, create jobs and improve living standards Expected effects after the construction of HPP Ustikolina