Probabilistic project cost and schedule estimating - Michel Sterling - NESMA 2013

4,606 views

Published on

In an analysis of 1,200 IT projects completed over the past 5 years, on average, these projects turned out 8% under their approved budget and took 21% longer than their approved schedule. This means that too much money and resources are claimed and claimed resources become later available then planned. Too much money is left on the table that could have been allocated to other business opportunities.
Looking forward there are two trends that demand for faster delivery of IT projects:
Increasing pace of IT evolution
Shorter time windows for new business opportunities

To enable faster delivery of IT projects ExxonMobil is introducing P50 probabilistic project cost and schedule estimating for classified estimates. Classified estimates are estimates within the envelope of uncertainty when it is possible to make risk-based predictions of a possible range of the project outcome in both cost and schedule. For a single project the P50 estimate means a 50% probability of cost and schedule overrun. When these projects are accumulated into a portfolio the underruns and overruns even out to a level where money and resources are used as efficiently as possible.

Introducing P50 estimates is a culture change where overruns within the allowable range are accepted and results outside the acceptable range should be treated with equal scrutiny whether it’s an overrun or an underrun.

Published in: Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
4,606
On SlideShare
0
From Embeds
0
Number of Embeds
12
Actions
Shares
0
Downloads
53
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Probabilistic project cost and schedule estimating - Michel Sterling - NESMA 2013

  1. 1. Probabilistic Project Cost and Schedule Estimating NESMA Najaarsconferentie in Baarn, NL - 21 Nov 2013 Michel Sterling – ExxonMobil IT
  2. 2. Project Estimating      Case for action Cost and Schedule Essentials What is P50 estimating Why P50 ? Change Management Challenges 2
  3. 3. Case for Action  On average, IT projects completed over the past 5 years turn out 8% under their approved budget and take 21% longer than their approved schedule. Opportunity to leave less “money on the table”  Trend : Increasing pace of Information Technology evolution  Trend : Narrower windows of business opportunities Demand for faster delivery to capture full benefits of business opportunities. 3
  4. 4. Before we jump in…  “Everything that can be counted does not necessarily count; everything that counts cannot necessarily be counted.” – Albert Einstein  “There are three types of lies : Normal Lies, Damned Lies and Statistics” – Mark Twain 4
  5. 5. Cost and Schedule Essentials • Basis definition improves as project progresses through project stages, increasing confidence in the range of possible outcomes • Unclassified Estimates : No historical statistical data available to support accuracy • Classified Estimates : Risk-based predictions of possible range of outcomes. Estimate Classification Concept Notional "envelope of uncertainty" Cost 100 Contingency Allowances Base 0 5 Final Cost
  6. 6. What is P50? Actual / Estimate Cost Ratio  The P50 cost value is a probabilistic estimate of the project cost based on a 50% probability that the cost will be exceeded. Cost Estimate Performance 200% 180% P10 P50 P90 160% 140% 120% 100% 80% 60% 40% 20% 0%  Projects of a portfolio are considered at the mean of a simulated cost distribution, typically the P50 estimate. 6
  7. 7. Why P50 ?  For a project : an equal likelihood to complete under or over the appropriation basis (cost and duration)  Maximize individual project’s predictability, avoid surprises  Not wasting, not shortcutting; Net zero impact  Avoid overly conservative estimates that encumber resources  Capital that can be used elsewhere  Resources that can be deployed elsewhere  Requires thorough comprehension of Risk events, Opportunities and their impact on Cost and Schedule Level of experience Assessment of complexity 7
  8. 8. Confidence Ranges  Within a Portfolio :  8 out of 10 projects to complete within a given confidence range of the appropriation basis cost and duration.  Routine Project’s within +/- 10%  Repeatable  Known Risks, low uncertainty  High confidence 80%  One-off or first time  Unknown risks  New Technology, Geography, Process 8 Number of Projects  Non-Routine Projects within +/- 20% 10% 90% 10% 100 110% 80% 10% 80% 10% 100% 120%
  9. 9. Managing the Change  Culture change  A over-run within the allowable range (between 100-110% of appropriation basis) is as good as an under-run (between 90-100%)  A result outside the confidence band should be treated with equal scrutiny whether it's under or over  The confidence band should be broaden when there is more inherent risk in the estimate : A result between 100-120% of appropriation basis is as good as a result between 80-100%  Gate 2 – “Scoping” should represent a P50 too…  Process & Tools to implement P50  Norms and tools calibrated to P50  Cost and schedule controls earlier in the project life cycle  Risk management and contingency planning 9
  10. 10. Time for Questions 10

×