TVC Tracking for New Construction Projects
A Path Forward
MERCER TECHNICAL SERVICES
Historical Perspective
• 1935, The "American Tentative Standard Code for Pressure Piping”,
ASA B...
MERCER TECHNICAL SERVICES
Steel Pipe (proposed rule)
§ 192.67 Records: Materials.
Each operator of transmission pipelines ...
MERCER TECHNICAL SERVICES
Pipeline Components (proposed rule)
§ 192.205 Records: Pipeline components.
Each operator of tra...
MERCER TECHNICAL SERVICES
Welders (proposed rule)
§ 192.227 Qualification of welders.
* * * * *
(c) Records for transmissi...
MERCER TECHNICAL SERVICES
We Have Come a Long Way…..
MERCER TECHNICAL SERVICES
Typical Work Flow
Receive
Material at Pipe
Yard and Create
a Pipe Tally with
HN and JN
MTR’s
Pip...
MERCER TECHNICAL SERVICES
Typical Records
MERCER TECHNICAL SERVICES
Risk
Risk = Probability of Failure x Consequence
(Missing Records) (Financial Impact)
MERCER TECHNICAL SERVICES
Material Identification
0
100
200
300
400
500
600
700
800
900
1,000
1930 1940 1950 1960 1970 198...
MERCER TECHNICAL SERVICES
Time Dependent
0
100
200
300
400
500
600
700
800
900
1,000
Pipe Mill Coating Mill Transport Stag...
MERCER TECHNICAL SERVICES
Mitigate Risk
Ensure material is RTVC when consequence is low
Receive
Material at Pipe
Yard and ...
MERCER TECHNICAL SERVICES
Material Tracking Systems
• Tagging system have been in the pipeline industry
since 19XX
• Vario...
MERCER TECHNICAL SERVICES
Lessons Learned - Tags
• Tags places on the inside of pipe
• Comes off the pipe and flows with t...
MERCER TECHNICAL SERVICES
Material Database Requirements
• What data will be stored and the method of storage
• Remote acc...
MERCER TECHNICAL SERVICES
Database
Material database can evolve into a project database
• Tracking of X-Rays
• Welder Qual...
MERCER TECHNICAL SERVICES
Mapping
• You must be able to tie your material information
to the physical location of the mate...
MERCER TECHNICAL SERVICES
Planning
• As with any project, planning is key in
implementing a material tracking system
• Rev...
MERCER TECHNICAL SERVICES
Value Added
• Transparency for the project team
• Streamline communications through real time
re...
MERCER TECHNICAL SERVICES
Contact Information
Mark E. Anderson
Vice President
Mercer Technical Services
8826 Santa Fe Driv...
Upcoming SlideShare
Loading in …5
×

INGAA TVC Presentation

1,709 views

Published on

TVC Tracking for New Construction PRojects

Published in: Engineering
  • Be the first to comment

  • Be the first to like this

INGAA TVC Presentation

  1. 1. TVC Tracking for New Construction Projects A Path Forward
  2. 2. MERCER TECHNICAL SERVICES Historical Perspective • 1935, The "American Tentative Standard Code for Pressure Piping”, ASA B31.1 was issued • 1955, Section 8, designated B31.1.8, represented a significant technical advancement in requirements for natural gas transmission and distribution piping systems • 1970, DOT issues original versions of 49 CFR Parts 191 & 192 • 2011, PHMSA issues Advisory Bulletin requiring material to be “Traceable, Verifiable and Complete” • 2016, PHMSA NPRM: Safety of Gas Transmission & Gathering Pipelines
  3. 3. MERCER TECHNICAL SERVICES Steel Pipe (proposed rule) § 192.67 Records: Materials. Each operator of transmission pipelines must acquire and retain for the life of the pipeline the original steel pipe manufacturing records that document tests, inspections, and attributes required by the manufacturing specification in effect at the time the pipe was manufactured, including, but not limited to, yield strength, ultimate tensile strength, and chemical composition of materials for pipe in accordance with § 192.55.
  4. 4. MERCER TECHNICAL SERVICES Pipeline Components (proposed rule) § 192.205 Records: Pipeline components. Each operator of transmission pipelines must acquire and retain records documenting the manufacturing standard and pressure rating to which each valve was manufactured and tested in accordance with this subpart. Flanges, fittings, branch connections, extruded outlets, anchor forgings, and other components with material yield strength grades of 42,000 psi or greater must have records documenting the manufacturing specification in effect at the time of manufacture, including, but not limited to, yield strength, ultimate tensile strength, and chemical composition of materials.
  5. 5. MERCER TECHNICAL SERVICES Welders (proposed rule) § 192.227 Qualification of welders. * * * * * (c) Records for transmission pipelines demonstrating each individual welder qualification in accordance with this section must be retained for the life of the pipeline.
  6. 6. MERCER TECHNICAL SERVICES We Have Come a Long Way…..
  7. 7. MERCER TECHNICAL SERVICES Typical Work Flow Receive Material at Pipe Yard and Create a Pipe Tally with HN and JN MTR’s Pipe Mill String Pipe and Document Check HN and JN to Pipe Tally Load Out Pipe At Pipe Yard and Track Inventory Check HN and JN to Pipe Tally As-Build Survey Collects GPS Shots in Ditch and Check HN and JN to Pipe Tally As-Build Survey Off Line Features As-Build Drawings, Check HN and JN to Pipe Tally Data to Client X-Check to Pipe Tally MTR’s to Client
  8. 8. MERCER TECHNICAL SERVICES Typical Records
  9. 9. MERCER TECHNICAL SERVICES Risk Risk = Probability of Failure x Consequence (Missing Records) (Financial Impact)
  10. 10. MERCER TECHNICAL SERVICES Material Identification 0 100 200 300 400 500 600 700 800 900 1,000 1930 1940 1950 1960 1970 1980 1990 2000 2010 2020 Probability of Not Meeting Code ???
  11. 11. MERCER TECHNICAL SERVICES Time Dependent 0 100 200 300 400 500 600 700 800 900 1,000 Pipe Mill Coating Mill Transport Staging Yard Stringing Welded Hydro In-Service Audit Failure Consequence
  12. 12. MERCER TECHNICAL SERVICES Mitigate Risk Ensure material is RTVC when consequence is low Receive Material at Pipe Yard and Scan Material Pipe Mill Receive MTR’s and Enter into Database String Pipe and Scan to Track Material Load Out Pipe At Pipe Yard and Scan to Track Inventory As-Build Survey Collects GPS Shots in Ditch and Scan As-Build Survey Off Line Features As-Build Drawings, Use Information From Database Data to Client Interactive Database
  13. 13. MERCER TECHNICAL SERVICES Material Tracking Systems • Tagging system have been in the pipeline industry since 19XX • Various types of tags can be used • RFD • Bar Codes • Wide range of quality • One tag does not fit all needs • Material Database • What is tracked in the database • Is the database real time
  14. 14. MERCER TECHNICAL SERVICES Lessons Learned - Tags • Tags places on the inside of pipe • Comes off the pipe and flows with the product • Tags prevents pipe coating from being jeeped • Tags destroyed during handling • Pipe is cut at the firing line and pup moved ahead • Tags deteriorated on pipe being stored due to UV The type and style of the tags you use on your project is a critical desicion point
  15. 15. MERCER TECHNICAL SERVICES Material Database Requirements • What data will be stored and the method of storage • Remote access to the database • Office • Field • Operator • Database security • Levels of access to database • Cyber security • Storage requirements • Data transfer to operator at end of project
  16. 16. MERCER TECHNICAL SERVICES Database Material database can evolve into a project database • Tracking of X-Rays • Welder Qualifications • Hydrostatic test • Maintenance tickets for defective material • Tracking location of material • Inventory control
  17. 17. MERCER TECHNICAL SERVICES Mapping • You must be able to tie your material information to the physical location of the material • Fencing will not be excepted • Survey must be integrated with the database • Survey accuracy will be key • Mapping material on a liner pipeline is no problem • Mapping material for fabrication is challenging
  18. 18. MERCER TECHNICAL SERVICES Planning • As with any project, planning is key in implementing a material tracking system • Review the process with all stake holders • The material tracking starts with the ordering of the material to the final as-built into the operators records system • Work with the affected service providers • Combined traditional tasks with new tasks needed for material tracking
  19. 19. MERCER TECHNICAL SERVICES Value Added • Transparency for the project team • Streamline communications through real time reporting (dashboards) • Reduce the time from physical completion of project to completion of the project
  20. 20. MERCER TECHNICAL SERVICES Contact Information Mark E. Anderson Vice President Mercer Technical Services 8826 Santa Fe Drive, Suite 150 Overland Park, KS 66212 mark.anderson@mertechserv.com P: 913.433.4099

×