2. PROJECT DIRECTOR
Employer: Edilmonte Roma Ltd (Italy)
FROM MAI 2010 TO DATE
(Real Estate – Hotels & Resorts industry) contract position
Edilmonte Roma is an independent Real Estate Developer based in Italy (Rome) with main
operations in Hotels Industry.
Mission: to bring 5-star hotel project to completion; completion of Interior Design phase and
FF & E - fit-out, snagging and defects for this luxury development, managing handover to hotel
operator.
Responsible for the execution of the Contract in terms of the main contractual obligations.
The project is a 5 star Hotel & Resort with 356 bays, convention centre , spa and various
amenities now entering in FF & E phase. Soft-opening is scheduled for March 2011. Budget
approx. $ 100 Millions.
Responsibilities;
•Project delivery – Supervising Design
•Change management – Represent the Company to face Operator, consultants and sub-
contractors
•Contract management - Procurement management
•Subcontractor management
•
3.
4.
5.
6.
7.
8. From September 2008 to March 2009
Project Architect for Alargan Real
Estate Project Management Company
(Kuwait)
Project: The Oberoi 5 ** Resort at Al Khiran
Muscat Sultanate of Oman
Concept Designer: Bernard Khoury DW5
Beirut Lebanon
Building surface 22,000 square meters
Budget: USD $ 70 Millions
Status: on site
19. PROJECT DIRECTOR (Client side)
New complex SERVIER in Italy Rome
Delivered March 2003
Via Luca Passi 35 Rome Italy
Buildings surfaces 10,000 square meters
2000-2003
Budget USD $ 60 Millions
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32. Project Director & Designer
New H.Q. Mixed Used STRYKER
in Italy Formello
Delivered June 2008
Building surface 11,000 square meters
Total operational budget USD $ 20 Millions