Deconstruct UK Limited    Deconstruct is a specialist provider of site enablement services, using the latest innovation an...
About the Project:    The calorifier vessels and pipework    within the boiler room had been    subjected to damage over t...
Project Challenges:  This project was undertaken adjacent to a live Community Centre that was in constant    use, so it wa...
List of Services:           Services provided by Deconstruct UK Ltd:           Deconstruction Services           Demolitio...
Upcoming SlideShare
Loading in …5
×

Asbestos Removal London Case Study – Community Centre Projects

538 views

Published on

Deconstruct UK Limited has launched a series of Slideshare Presentations to demonstrate their asbestos removal capabilities in the London and surrounding areas.

Published in: Business
  • Be the first to comment

  • Be the first to like this

Asbestos Removal London Case Study – Community Centre Projects

  1. 1. Deconstruct UK Limited Deconstruct is a specialist provider of site enablement services, using the latest innovation andprocesses to transform and prepare sites for development. With a commitment to delivering excellence we offer an unparalleled level of service. Community Centres Case Study Decontamination of asbestos from a boiler house in the local community centre. Client: Ayerst Environmental Ltd Location: Community Centre, London W6 Contractor: Deconstruct UK Ltd Completion Date: April 2011 Sector: Public Buildings ZERO HARM THROUGH ZERO TOLERANCE
  2. 2. About the Project: The calorifier vessels and pipework within the boiler room had been subjected to damage over the years and an effective repair was necessary. The damaged pipework was cleaned using h-type vacuum cleaners and ‘tac’ rags before being repaired using calico wrap and elastomeric paint. The boiler house was thoroughly decontaminated and the timber enclosure to the calorifiers was made good. ZERO HARM THROUGH ZERO TOLERANCE
  3. 3. Project Challenges: This project was undertaken adjacent to a live Community Centre that was in constant use, so it was imperative that our operatives carried out the works as discretely as possible and conducted themselves professionally at all times. The access to the working area was directly off the public highway, so a secure timber hoarding had to be erected around the entrance to the boiler room. An operative was stationed outside the entrance to the enclosure at all times, during working hours, to ensure that no unauthorised people entered the work area. ZERO HARM THROUGH ZERO TOLERANCE
  4. 4. List of Services: Services provided by Deconstruct UK Ltd: Deconstruction Services Demolition Services Enabling Works Asbestos Removal Services ✓ Asbestos Surveying Services Ground Works Services Piling Services Steelwork Installations Builders Works Emergency Dangerous Structures Temporary Works “All of the services above are provided by Deconstruct UK Limited.” ZERO HARM THROUGH ZERO TOLERANCE

×