From:    Brandon Valdez                To: David Ficklin - OnGoal
                                                        ...
Structural Steel Erection:
 Area 1 – Steel Erection in sequence 1-5 complete. Steel
 Erection in sequence 1-3 is ongoing.
...
Structural Steel Erection:
 Erection of Structural Steel in Sequence 1-3 will
 continue.

 Delivery of Roof Trusses for se...
Additional Photos:




Area 1 – Shot looking at East Elevation of   Suite Level – Concrete placed at exterior
the West Bui...
Upcoming SlideShare
Loading in …5
×

Weekly Construction Update 6-22-2010

1,437 views

Published on

KC Soccer Stadium construction update from Turner Construction.

Published in: Sports, Business
  • Be the first to comment

  • Be the first to like this

Weekly Construction Update 6-22-2010

  1. 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 6.16.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 6.14.2010 Current Activities this Week: Mass Excavation: Backfilling of on-grade seating is ongoing in Area 1, Area 2 and Area 3. Site Utilities: Storm Sewer installation (Line 6000) is ongoing on Field Level Area 1 – Shallow Underground east side of France Family Drive. plumbing pipe installation ongoing at Aux Locker Rooms. Sanitary Sewer Line E installation is ongoing on east side of France Family Dive. Foundations: Area 2 Concourse Level – E-Line footing installation is complete to column line 14. Area 3 Field Level – A-Line wall (to column line 1) is complete. Area 3 Field Level – Isolated footing installation is Field Level Area 3 – A-Line wall installation is ongoing. complete to Column Line 1. Concrete Flatwork: Area 1 – Mezzanine slab-on deck is complete, Main Concourse structural slab is complete, Suite Level slab on deck is complete from column line 23-32. Area 1 – Underslab MEP rough-in is ongoing on Press Level. Suite Level – Concrete Slab on Metal Deck is complete from Column Line 23 - 32. Building the Future
  2. 2. Structural Steel Erection: Area 1 – Steel Erection in sequence 1-5 complete. Steel Erection in sequence 1-3 is ongoing. Decking/Detailing/Studs/Edge Angle is nearly complete in Sequence 1-5. Underground MEP: Deep Sanitary installation is ongoing in Area 3. Area 1 – Structural Steel Erection Sequence 1-3 in underway (outdoor terrace area). Electrical Secondary is ongoing in Area 2. MEP Rough-in: Plumbing and Electrical rough-in for concrete decks are ongoing at Press Level. Shallow plumbing rough-in is ongoing at Area 1 Field Level. Projected Activities occurring next Week: Mass Excavation: Backfilling of on-grade seating areas will continue in Area 3. Rough grading of field will continue. Area 1 – Structural Steel Erection at West Building is complete from Column Line 33 – Site Utilities: 23. Decking is ongoing on the Press Level. Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will continue. Storm Line 5000 and 4000 will begin. Installation of Sanitary Line E will continue. Deep Underground Plumbing: Deep Sanitary installation in Area 3 will continue. Foundations: Area 3 Field Level – Foundation installation will continue. Area 4 Mezzanine Level – Foundation Wall installation will Concourse Level Area 2 – Backfill of E-Line begin. walls are ongoing. This area is where southwest concourse restrooms and Concrete Flatwork: concessions are located. Area 1 Press Level – Concrete placement will begin. Building the Future
  3. 3. Structural Steel Erection: Erection of Structural Steel in Sequence 1-3 will continue. Delivery of Roof Trusses for sequence 1-7 will begin to arrive on site. Structural Precast: Field Level Area 2 – Shot looking south (from Erection of the precast risers and tubs will begin. Suite Level Column Line 32) of south foundation walls. Underground MEP: Deep Sanitary installation will continue in Area 3. Electrical Secondary will continue in Area 2 MEP Rough-in: Plumbing and Electrical rough-in for concrete decks will continue at Press Level. Shallow plumbing rough-in will continue at Area 1 Field Level. Shallow electrical will begin at Area 1 Field Level. Suite Level Area 1 – Steel edge plate installation ongoing at Roof Level. Building the Future
  4. 4. Additional Photos: Area 1 – Shot looking at East Elevation of Suite Level – Concrete placed at exterior the West Building. walkway outside of Lower Suite Lounge. Press Level – Underslab MEP rough-in ongoing prior to reinforcing steel Mezzanine Level Area 4 – Wall form installation. installation is ongoing. Concourse Level Area 1 – Ironworkers Field Level Area 1 – Electrical conduits installing one of the numerous pieces of penetrating D-Line wall into electrical room steel in Sequence 1-3. between Column Line 30 – 30.5. Building the Future

×