Construction Update 6-28-2010
1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 6.23.2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
6.21.2010
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 2
and Area 3.
Site Utilities:
Storm Sewer installation (Line 6000) is ongoing on
east side of France Family Drive. Storm Sewer installation Field Level Area 3 – Secondary electrical
(Line 1000) has started at Village West Parkway. distribution is ongoing behind A-Line Wall.
Sanitary Sewer Line E installation is ongoing on east
side of France Family Dive.
Foundations:
Area 3 Field Level – Isolated footing installation is
Ongoing and is currently to Column Line 8.
Press Level Area 1 – Concrete placed for
Area 4 Mezzanine Level – Excavation for D-Line footing Exterior walkway outside of the Upper Suite
Is ongoing and is currently to Column Line 37.
Lounge. Note the Ceremonial 1st Column in
place.
Concrete Flatwork:
Area 1 – Mezzanine slab-on deck is complete, Main
Concourse structural slab is complete, Suite Level slab
on deck is complete, Press Level slab on deck is complete.
Area 1 – Precast concrete treads and riser
installation is ongoing between column lines
32-30.
Building the Future
2. Structural Steel Erection:
Area 1 –Steel Erection in sequence 1-3 is ongoing.
Area 1 – Roof deck installation has started in Sequence 1-4
Underground MEP:
Deep Underground Plumbing installation is ongoing in
Area 3. Area 1 – 142’ long Canopy Trusses are
starting to be delivered and staged in the
Electrical Secondary Distribution is ongoing in Area 3. field.
MEP Rough-in:
Plumbing and Electrical rough-in for Field Level slab on
grade is ongoing in Area 3.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of on-grade seating areas will continue in Area
3.
Area 1 – Shot of the West Building from the
Site Utilities: southeast. Notice the precast risers at the
Installation of the Storm Line 6000 on the East Side (France north end.
Family Drive) of the site will continue. Storm Line 1000
will continue. Installation of Sanitary Line E will continue.
Deep Underground Plumbing:
Deep Sanitary installation in Area 3 will continue.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Area 4 Mezzanine Level – Foundation Wall installation will
continue. Field Level Area 2 – Gang forms being
installed for concrete placement at
southeast corner.
Building the Future
3. Concrete Flatwork:
Area 1 Press Level – Concrete placement will begin.
Structural Steel Erection:
Erection of Structural Steel in Sequence 1-3 will
continue. Roof decking installation on Sequence 1-4 will
continue.
Delivery of Roof Trusses for sequence 1-7 will continue
throughout the week.
Structural Precast: Field Level Area 2 – Shot looking south (from
Erection of the precast risers in Area 1 will continue. Press Level Column Line 32) of Area 2.
Underground MEP:
Deep Sanitary installation will continue in Area 3.
Electrical Secondary will continue in Area 3.
MEP Rough-in:
Plumbing and Electrical rough-in for Area 1 Field Level slab
on grade will continue.
Field Level Area 3 – Isolated footing
installation is ongoing.
Building the Future
4. Additional Photos:
Field Level Area 3 – Shot looking south of A-
Line foundation wall. Note openings in wall
Rigging being installed on Canopy truss. for Supporters Section entrance.
France Family Drive – Storm inlet structure
installed at the west side of France Family Area 1 – Shot looking north of the West
drive. Building. Note the curve of the building.
Field Level Area 1 – Shotcrete wall weeps tie Press Level Area 1 – Roof Deck installation
in to storm sewer is ongoing. has started in Sequence 1-4.