Construction Update 5-5-2010

  1. 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 5.5.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 5.3.2010 Current Activities this Week: Mass Excavation: Grading is ongoing in Area 3. Backfilling of on-grade is ongoing in Area 1. Site Utilities: Installation of the new electrical ductbank is ongoing. Concourse Level Area 1/2 – E-Line Footing Installation of North Sanitary Manhole is complete. Placement is ongoing. Storm Sewer installation (Line 6000) is ongoing on east side of France Family Drive. Foundations: Area 2 Field Level – Footing installation on North Stage Footing is complete to Column Line 15. Area 1 Mezzanine Level – Installation of Elevator Pit walls are complete. Field Level Area 1 – Secondary Electric Ductbank installation has started at D-Line. Area 4 Mezzanine Level – Installation of Drilled Piers are ongoing. Soil Nail Wall: Area 2 – Shotcrete installation is complete. Concourse Level Area 1 – Steel Decking installation in Steel Erection Sequence 1-1 is ongoing. Building the Future
  2. 2. Structural Steel Erection: Field Bowl – Structural Steel Erection is ongoing in Sequence 1-1 (between Column Lines D-C). Installation of steel decking has started. Underground Electrical: Secondary service ducts is complete from Electrical Room Field Level Area 1 – South Field Wall 01.34.04 south past Column Line 25. Footings being placed. Secondary service ducts at Column Line D have started. Projected Activities occurring next Week: Mass Excavation: Grading at Truck Dock Area will begin. Site Utilities: Area 1 – Structural Steel Erection at West Installation of the Storm Line 6000 on the East Side (France Building continues. First Level of Stadium Family Drive) of the site will continue. Suite Steel being set. Deep Underground Plumbing: Sanitary in Area 3 will begin. Foundations: Area 2 Field Level – Placement of foundation walls at stage area will begin. Area 3 Field Level – Footing excavation will begin. Structural Steel Erection: Erection of Structural Steel in Sequence 1-2 will begin. Field Level Area 1 – Shot looking north from Concourse Level. Building the Future
  3. 3. Additional Photos: Field Level Area 1 – Southeast Vomitory Mezzanine Level Area 1 – VIP Entrance Foundation Wall. taking shape. Field Level Area 2 – West Stage Foundation Field Level Area 1 – Southeast Vomitory Wall. return wall formwork being installed. Area 1 – Shot looking North West showing Field Level Area 2 – North Stage footings are West Building Structural Steel. complete to Column Line 15. Building the Future

×