  1. 1. River Road Area Sewer Improvements Neighborhood Advisory Committee June 24, 2004
  2. 2. Today’s Meeting <ul><li>Program Overview – Video </li></ul><ul><li>Role of the Committee </li></ul><ul><li>Sanitary Sewer Overflows </li></ul><ul><li>River Road Projects </li></ul><ul><li>Next Meeting Date </li></ul>
  3. 3. Role of the Committee <ul><li>Provide input and feedback </li></ul><ul><li>Independent and objective review </li></ul><ul><li>Serve for duration of projects </li></ul>
  4. 4. What You Can Do <ul><li>Listen to the presentations and issues that are presented to you </li></ul><ul><li>Offer your honest opinions on the issue </li></ul><ul><li>Work with us to help find constructive solutions </li></ul><ul><li>Help educate others on the project </li></ul>
  5. 5. Sanitary Sewer Overflows <ul><li>Nine Sanitary Sewer Overflows in Toledo </li></ul><ul><ul><li>4 in the River Road Area </li></ul></ul><ul><ul><li>2 in the Parkside Area </li></ul></ul><ul><ul><li>3 in Point Place </li></ul></ul><ul><li>Must be eliminated by November of 2006 </li></ul><ul><ul><li>Stiff penalties for missed deadlines </li></ul></ul>
  6. 6. Past & Ongoing River Road Area Projects <ul><li>Sanitary sewer study – 2000/2001 </li></ul><ul><li>Storm sewer study – 2002/2003 </li></ul><ul><li>Sewer lining – 2002/ongoing </li></ul><ul><li>Copland storm sewer – 2002 </li></ul><ul><li>Beverly/Medford storm sewer – 2004/ongoing </li></ul>
  7. 7. Proposed River Road Area Projects <ul><li>Underground Equalization Basin – Brookford Park </li></ul><ul><li>Underground Pump Station – Brookford Park </li></ul><ul><li>New Force Main Sewer – Brookford </li></ul><ul><li>New Relief Sewer– Beverly and River Road </li></ul><ul><li>Beverly Pump Station – West of Trail </li></ul>
  8. 8. River Road SSOs <ul><li>(insert map showing locations) </li></ul>
  9. 9. Project Schedules <ul><li>Projects will be built concurrently </li></ul><ul><li>Construction bids – October/November 2004 </li></ul><ul><li>Break Ground – Early 2005 </li></ul><ul><li>Completed by November 2006 </li></ul>
  10. 10. Equalization Basin <ul><li>Designed to eliminate need to discharge raw sewage into the Maumee River during heavy rains. </li></ul><ul><li>Will hold wastewater at “peak” times when flow of waste exceeds sewer system capacity. </li></ul><ul><li>When the rain lets up, wastewater in the basin sent to plant for treatment </li></ul>
  11. 11. Equalization Basin <ul><li>Underground facility </li></ul><ul><li>To be located at Brookford Park ball diamond site </li></ul><ul><ul><li>Tanks from old Toledo Water Plant currently located there </li></ul></ul><ul><li>3 million gallon storage capacity </li></ul><ul><li>120 ft. x 240 ft. </li></ul><ul><li>17 ft. deep </li></ul>
  12. 12. Equalization Basin
  13. 13. EQ Basin Issues & Discussion <ul><li>Construction Access Road </li></ul><ul><ul><li>From River Road to site (between playgrounds) </li></ul></ul><ul><ul><li>Reduces amount of construction equipment entering site from Brookford </li></ul></ul><ul><ul><li>Could disrupt playground areas </li></ul></ul>
  14. 14. Issues and Discussion <ul><li>Baseball field </li></ul><ul><ul><li>Will be lost for one season due to construction </li></ul></ul><ul><ul><li>Alternative options for replacement of the field </li></ul></ul>
  15. 15. Brookford Park Pump Station <ul><li>Located next to Equalization Basin </li></ul><ul><li>Bulk of facility underground </li></ul><ul><li>Control panel above ground </li></ul><ul><li>Will pump waste from River Road sewer to equalization basin </li></ul>
  16. 16. Beverly Pump Station <ul><li>Underground – with control panel(s) above ground </li></ul><ul><li>Will pump waste from Beverly sewer to new EQ basin </li></ul>
  17. 17. Force Main Sewer <ul><li>New sewer from Beverly pump station on west side of Anthony Wayne Trail down Brookford to the Equalization Basin </li></ul><ul><li>To be located on south side of Brookford </li></ul><ul><li>Shouldn’t disturb street – except for crossings at OLPH and Island Avenue </li></ul><ul><li>Traffic maintained </li></ul><ul><ul><li>Will work with committee to minimize disruption </li></ul></ul>
  18. 18. New Relief Sewers <ul><li>From River Road, Midland or Hemlock down River Road to Brookford </li></ul><ul><ul><li>New water line will be installed at same time </li></ul></ul><ul><ul><ul><li>Should help resolve water pressure problems </li></ul></ul></ul><ul><ul><li>Preferred sewer location is in east lane of River Road </li></ul></ul><ul><ul><ul><li>Discussion </li></ul></ul></ul>
  19. 19. New Relief Sewers <ul><li>On Beverly from Brookford to Medford </li></ul><ul><li>Both relief sewer lines should help alleviate basement flooding in area </li></ul>
  20. 20. Future Meetings <ul><li>Next meeting date? </li></ul><ul><li>Best time and location? </li></ul>

×