05-02-2011 McCoy

  1. 1. Pricing History for Conceptual PhasesNew McCoy Elementary Schematic 50% DD 95% CD Final Budget on Variance From Design Package Estimate Estimate Bid Set Original Original Budget $14,898,998J Jacobs Construction N/A $14,118,687 5/6/2011 TBD -$780,311 Pricing Entity 1 N/A $14,325,769 N/A N/A -$573,229 Pricing Entity 2 N/A $13,305,876 N/A N/A -$1,593,122 Pricing Entity 3 N/A $13,992,812 N/A N/A -$906,186

×