Scope of key projects, Aedilis UAB

869 views

Published on

Brief information about key projects of substation commissioning.

Published in: Technology, Business
  • Be the first to comment

  • Be the first to like this

Scope of key projects, Aedilis UAB

  1. 1. ` Aedilis, UAB Scope of projects Brief information about key projects of company Evaldas Paliliūnas, Project Manager 6/22/2011 v.1.1
  2. 2. SCOPE OF PROJECTS 6/22/2011ContentsConstruction of 330 kV transmission substation Bitenai. End user AB “LITGRID” ......................... 3Reconstruction of TR46-5 transformer substation. End user AB “Lietuvos gelezinkeliai”(Lithuanian railways)............................................................................................................................ 4Reconstruction of 110 kV transformer substation Valkininkai (Replacement of 110 kV circuitbreaker with switch . End user AB “Litgrid”....................................................................................... 5Reconstruction of 110 kV transformer substation Griskonys (Replacement of 110 kV circuitbreaker with switch . End user AB “Litgrid” ....................................................................................... 6Construction of 10/0, 4 kV distribution substation Klaipeda (SP-62). End user UAB “Klaipedosarena” (Arena of Klaipeda) ................................................................................................................... 7Construction of 35/10 kV transformer substation Dolomitas. End user AB “Dolomitas”............... 8Reconstruction of 110/10 kV transformer substation Savitiskis. End user AB “Litgrid”................ 9Reconstruction of 110/35/10 kV transformer substation N.Akmene. End user UAB “Lesto” ..... 10Reconstruction of 110/10 kV transformer substation Baksiai. End user UAB “Lesto” ................. 11Wind farm Lauksargiai........................................................................................................................ 12AB "Lietuvos gelezinkeliai" railway sector Siauliai – Klaipeda. End user AB “Lietuvosgelezinkeliai” (Lithuanian railways) .................................................................................................. 13 v.1.1 | Aedilis, UAB | Scope of projects 2
  3. 3. SCOPE OF PROJECTS 6/22/2011Construction of 330 kV transmission substation Bitenai. End user AB “LITGRID” Relay protection and Telecommunications RTU automation Construction of Bitenai switchyard at the border with Kaliningrad was a strategic site for Lithuania. The switchyard is necessary for consumers in Western Lithuania to receive electricity through the grid located in Lithuania. So far power lines at Bitenai were stretched from Lithuania to Kaliningrad region and from there – to Lithuania. Main contractor was “Empower”, UAB they choose “Aedilis”, UAB as their subcontractor for telecommunications, RTU and relay protection parts; Telecommunications: UAB „Aedilis“ did a detailed design for SDH and PDH networks, which was used to transmit data to SCADA system; All installation and configuration works were completed by our team; We supplied all equipment for telecommunications; RTU: In this substation we were programming and commissioning a Siemens Sicam AK 1703 ACP controller with data collection by IEC 61850 protocol. Relay protection and automation: UAB „Aedilis“ in this project did part of relay protection and automation commissioning works. The Siemens 6MD6641, 7SJ6471 relays were configured using IEC 61850 protocol; v.1.1 | Aedilis, UAB | Scope of projects 3
  4. 4. SCOPE OF PROJECTS 6/22/2011Reconstruction of TR46-5 transformer substation. End user AB “Lietuvos gelezinkeliai” (Lithuanian railways) Relay protection and SCADA RTU automation TR46-5 is transformer substation of Lithuanian railways located in Siauliai. Projecttask was to reconstruct this substation changing all 10kV cubicles, installing new RTUsystem and transmit all data to existing SCADA system; Main contractor was “Liumenas”, UAB they choose “Aedilis”, UAB to complete allcommissioning tasks for this substation.RTU:UAB “Aedilis” team supplied a cubicle of RTU with Siemens AK 1703 ACP controller inthis project. Did a commissioning of RTU and detailed design;Relay protection and automation:UAB “Aedilis” team did commissioning of all relays;SCADA:We integrated TR46-5 transformer substation in existing Siemens PowerCC SCADA; v.1.1 | Aedilis, UAB | Scope of projects 4
  5. 5. SCOPE OF PROJECTS 6/22/2011Reconstruction of 110 kV transformer substation Valkininkai (Replacement of 110 kV circuit breaker with switch . End user AB “Litgrid” Telecommunications RTU Replacement works of 110 kV circuit breaker with switch completed in 110 kV transformer substation Valkininkai. New equipment for relay protection and automation, RTU, telecommunications systems were provided. Main contractor in this project was UAB “Tetas” they choose UAB “Aedilis” as sub-contractor for RTU and telecommunications parts. RTU: UAB “Aedilis” team supplied a cubicle of RTU with Siemens AK 1703 ACP controller in this project. Did a commissioning of RTU and detailed design; Relay protection and automation: UAB “Aedilis” team did commissioning of all relays; Telecommunications: Our team installed and configured a radio relay system in this site; v.1.1 | Aedilis, UAB | Scope of projects 5
  6. 6. SCOPE OF PROJECTS 6/22/2011Reconstruction of 110 kV transformer substation Griskonys (Replacement of 110 kV circuit breaker with switch . End user AB “Litgrid” Relay protection Telecommunications RTU SCADA and automation Replacement works of 110 kV circuit breaker with switch completed in 110 kV transformer substation Griskonys. New equipment for relay protection and automation, RTU, telecommunications systems were provided. Main contractor in this project was UAB “Elektromontuotojas” they choose UAB “Aedilis” to complete all commissioning tasks for this substation. RTU: UAB “Aedilis” team supplied a cubicle of RTU with Siemens AK 1703 ACP controller in this project. Did a commissioning of RTU and detailed design; Relay protection and automation: UAB „Aedilis“ in this project did all commissioning works of relay protection and automation. The Siemens 7SJ6471 relays were configured; Telecommunications: Our team installed and configured a radio relay system in this site; Design: UAB “Aedilis” team did a design for all engineering parts for this substation; v.1.1 | Aedilis, UAB | Scope of projects 6
  7. 7. SCOPE OF PROJECTS 6/22/2011Construction of 10/0, 4 kV distribution substation Klaipeda (SP-62). End user UAB “Klaipedos arena” (Arena of Klaipeda) Automated system for powerTelecommunications RTU resources SCADA monitoring and accounting Purpose of this construction was to connect new user to the grid. Main contractor was UAB “Elmonta” they choose UAB “Aedilis” for works of telecommunications and RTU parts. RTU: UAB “Aedilis” team supplied a cubicle of RTU with Siemens AK 1703 ACP controller in this project. Did a commissioning of RTU and detailed design; Automated system for power resources monitoring and accounting: Our team assembled a cubicle for automated system for power resources monitoring and accounting with MDC1.01 controller and did a commissioning works; Telecommunications: UAB “Aedilis” supplied all fiber equipment for telecommunications and did a commissioning; SCADA: We integrated new distribution substation (SP-62) in existing ABB MicroSCADA system; v.1.1 | Aedilis, UAB | Scope of projects 7
  8. 8. SCOPE OF PROJECTS 6/22/2011 Construction of 35/10 kV transformer substation Dolomitas. End user AB “Dolomitas” Automated system Relay for power resources protection andTelecommunications RTU SCADA monitoring and automation accounting Purpose of this substation was to connect wind farm owned by AB “Dolomitas” to the grid. Main contractor was UAB “Liumenas” they choose UAB “Aedilis” to complete all commissioning task for this substation. RTU: UAB “Aedilis” team supplied a cubicle of RTU with Siemens AK 1703 ACP controller in this project. Did a commissioning of RTU and detailed design; Automated system for power resources monitoring and accounting: Our team assembled a cubicle for automated system for power resources monitoring and accounting with MDC1.01 controller and did a commissioning works; Telecommunications: UAB “Aedilis” supplied all fiber equipment for telecommunications and did a commissioning; SCADA: We integrated TR46-5 transformer substation in existing Siemens PowerCC SCADA; v.1.1 | Aedilis, UAB | Scope of projects 8
  9. 9. SCOPE OF PROJECTS 6/22/2011 Reconstruction of 110/10 kV transformer substation Savitiskis. End user AB “Litgrid” Relay protection andTelecommunications RTU automation Transformers, switches and relay protection and automation systems were replaced in this substation. Main contractor was UAB “Hidroelektromontazas” they choose UAB “Aedilis” to complete all commissioning tasks for this substation. RTU: UAB “Aedilis” team supplied a cubicle of RTU with Siemens AK 1703 ACP controller in this project. Did a commissioning of RTU and detailed design; Telecommunications: UAB “Aedilis” supplied all Ethernet based equipment for telecommunications and did a commissioning; Relay protection and automation:: UAB “Aedilis” team did commissioning of all relays; v.1.1 | Aedilis, UAB | Scope of projects 9
  10. 10. SCOPE OF PROJECTS 6/22/2011Reconstruction of 110/35/10 kV transformer substation N.Akmene. End user UAB “Lesto” Automated system for power resources Dispatcher Relay protectionTelecommunications RTU monitoring and panel and automation accounting Reconstruction of 35/10 kV part in 110/35/10 kV substation N.Akmene. All old equipment was changed by new one, 7 new substations were integrated in SCADA system. Main contractor UAB “Siemens Osakeyhtio Lithuania” chooses UAB “Aedilis” to complete all commissioning task for this substation; RTU: UAB “Aedilis” team assembled a cubicle of RTU with Siemens AK 1703 ACP, TM1703ACP controllers in this project. Did a commissioning of RTU and detailed design; Automated system for power resources monitoring and accounting: Our team assembled a cubicle for automated system for power resources monitoring and accounting with MDC1.01 controller and did a commissioning works; Telecommunications: UAB “Aedilis” supplied all radio equipment for telecommunications and did a detailed design and commissioning; Relay protection and automation: UAB “Aedilis” team did commissioning of all relays; Dispatcher panel: Our team designed, assembled and commissioned a dispatcher panel for control room; v.1.1 | Aedilis, UAB | Scope of projects 10
  11. 11. SCOPE OF PROJECTS 6/22/2011Reconstruction of 110/10 kV transformer substation Baksiai. End user UAB “Lesto” Automated system for powerTelecommunications RTU resources monitoring and accounting Reconstruction of 10 kV part in 110/10 kV substation Baksiai. Replacement of allrelay protection and automation cubicle. Main contractor was UAB “Siemens OsakeyhtioLithuania” they choose UAB “Aedilis” to complete all commissioning task for thissubstation.RTU:UAB “Aedilis” team assembled a cubicle of RTU with Siemens AK 1703 ACP, TM1703ACPcontrollers in this project. Did a commissioning of RTU and detailed design;Telecommunications:UAB “Aedilis” supplied all Ethernet based equipment for telecommunications and did alldesign and commissioning;Automated system for power resources monitoring and accounting:Our team assembled a cubicle for automated system for power resources monitoring andaccounting with MDC1.01 controller and did a commissioning works; v.1.1 | Aedilis, UAB | Scope of projects 11
  12. 12. SCOPE OF PROJECTS 6/22/2011 Wind farm LauksargiaiTelecommunications RTU WebSCADA Relay monitoring system Purpose of this 110/20 kV substation was to connect wind farm to the grid. Main contractor was UAB “Siemens Osakeyhtio Lithuania” they choose UAB “Aedilis” to complete all commissioning task for this substation. RTU: UAB “Aedilis” team assembled a cubicle of RTU with Siemens AK 1703 ACP, TM1703ACP controllers in this project. Did a commissioning of RTU and detailed design; Telecommunications: UAB “Aedilis” supplied all radio equipment for telecommunications and did a detailed design and commissioning; Relay monitoring system: Installation and commissioning of relay monitoring systems, equipment supply; WebSCADA : Our team created a solutions with netbiter WebSCADA for remote monitoring; v.1.1 | Aedilis, UAB | Scope of projects 12
  13. 13. SCOPE OF PROJECTS 6/22/2011 AB "Lietuvos gelezinkeliai" railway sector Siauliai – Klaipeda. End user AB “Lietuvos gelezinkeliai” (Lithuanian railways) Relay protection andTelecommunications RTU SCADA automation This project contained reconstruction of 17 substation in railway sector between cities Siauliai and Klaipeda. New systems for telecommunication and SCADA were installed. UAB “Siemens Osakeyhtio Lithuania” they choose UAB “Aedilis” to complete all commissioning task for this project. RTU: UAB “Aedilis” team assembled a cubicle of RTU with Siemens AK 1703 ACP and eRTU controllers in this project. Did a commissioning of RTU and detailed design, provided courses for clients; Telecommunications: UAB “Aedilis” supplied all Ethernet based equipment for telecommunications and did all design and commissioning; Relay protection and automation: UAB “Aedilis” team did commissioning of all relays; SCADA : Our team did a configuration and commissioning of Siemens PowerCC SCADA system. Courses for clients how to use this system were provided; v.1.1 | Aedilis, UAB | Scope of projects 13

×