LIST OF ALL ROAD PROJECTS/NO   PROJECT                    LENGT     CONTRACTOR              DATE       CONTRACT SUM       ...
18.   Otun-Osan-Ora Bridge     9.6km     Johnson Int. Co Ltd.      Sep-09     494,379,067.00     21%      June-12    On-go...
road                                Ltd37.   Access road to CAC        0.3km     Hill Gate Continental     Dec-08     17,8...
Axis roads59.   Igede-Eyio-Iworoko        19.4km    Hajaig Const. Ltd.         Dec.08     1,919,496,593.00   9.46%   Feb-1...
LIST OF ON-GOING PROJECTS IN EKITI STATES/NO   PROJECT                                  LENGTH          CONTRACTOR        ...
26.   Oke-Iya Sharp Corner, Ara                               Lumobs inv. Co. Ltd.     May-10     “ “27.   Wuraola Gomez S...
www.ekitistate.gov.ng
www.ekitistate.gov.ng
www.ekitistate.gov.ng
Upcoming SlideShare
Loading in …5
×

List Of All Road Project

4,235 views

Published on

List of all New, On-going, proposed, suspended and Terminated road projects in Ekiti state.

Published in: Technology, Art & Photos
  • Be the first to comment

  • Be the first to like this

List Of All Road Project

  1. 1. LIST OF ALL ROAD PROJECTS/NO PROJECT LENGT CONTRACTOR DATE CONTRACT SUM % EXPECTED REMARK H AWARDED COMPLETIO COMPLETIO (KM) N N DATE1. Omisanjana- 9.3km JP Sigma Nig Ltd Mar-11 574,904,431.00 16% Aug-12 New 132/133kva-Deeper Life church, Ikere road2. Ado-Afao road 10.745k Kallen Tech. Nig. April-11 538,638,704.26 47.5% Mar-12 New m Ltd3. Ado-Ilawe road 11.5km Dromo Int. Co. Ltd. May-11 482,849,098.20 75% Feb-12 New4. Igede-Awo-Ido road 24km Stateco Nig. Ltd Nov-11 995,662,458.00 0.71% Dec-12 New5. Ikere-Igbaraodo road 19km Palmyra Constr. Co. Nov-11 494,815,781.25 0.8% Aug-12 New Ltd6. Ikogosi-Ipole – Iloro 24km Roosco Resources Niv-11 877,218,981.91 Dec-12 New road Nig Ltd7. Ijan-Ise road 17km RCF Nig. Ltd Nov-11 702,037,054.62 May-12 New8. Ijero-Ipoti-Ayetoro road 17km Ratcon Const. Co. Nov-11 888,258,892.50 New Ltd9. Dualization of Old 0.8km Hartland Nig. Ltd Nov-11 866,872,873.13 Oct-12 New Garage-Ojumose road10. Dualization of 0.9km Hartland Nig. Ltd Nov-11 891,822,525.30 Oct-12 New Atikankan-Nitel-Baptist road11. Ilawe-Igbaraodo-Ibuji 17km Dromo Int. Co. Ltd Nov-11 894,698,043.75 Oct-12 New road12. Ikole-Ijesa-Isu-Ilumoba 23km Scoa Nig. PLC Nov-11 1,139,155,368.75 Dec-12 New road13. Ijigbo-Baptist College 3.62km Dromo Int. Co Ltd. Nov-11 788,038,599.60 0.2% Oct-12 New (Ilawe road)14. Ojumose-Basiri/Polic 4.9km Hartland Nig. Ltd Nov-11 1,488,054,374.92 Oct-12 New Hqrs. (Iyin road)15. Fajuyi-University 1.65km Hartland Nig. Ltd Nov-11 447,544,063.50 May-12 New Teaching Hospital road16. Oye-Ikun-Otun road 43km Charvet Nig. Ltd Nov-11 1,002,883,612.50 0.4% Dec-12 New17. Ikere-Emure road 30km RCF Nig. Ltd Dec-07 766,857,725.37 82.0% Mar-12 On-going www.ekitistate.gov.ng
  2. 2. 18. Otun-Osan-Ora Bridge 9.6km Johnson Int. Co Ltd. Sep-09 494,379,067.00 21% June-12 On-going19. Rehab. Of Ado Minor EKROMA May-11 153,959,429.42 70% April-12 “ “ Township roads20. Kere-Ilawe road 20km Jobi Gold Profile Nig April-09 763,997,771.25 1% “ “ Ltd21. Odo-Owa-Oke-Ila road 12km Kopek Construction Jan-09 749,927,872.95 68% June-12 “ “ Co.Ltd22. Ado-Iworoko-Ifaki road 19km Hajaig Nig. Ltd Dec-07 7,471,743,345.46 62% April-12 “ “ dualization23. Ilemeso-Omu road 3.60km Bindigari Const. Ltd. Dec-08 346,366,510.00 26% May-12 “ “24. Ido-Ile-Okemesi 8.5km Sadiat Nig. Ltd Dec-08 363,832,331.62 43.16% June-12 “ “ Junction road25. Ewu bridge Roosco Resources Nov-08 220,361,972.60 70% Mar-12 “ “ Const. Ltd26. Secretariat-Awodele 260m Maurice Morrison Mary-10 18,884,887.90 60% April-12 “ “ road Extension Nig Ltd27. Oke-Iya Sharp Corner, Lumobs inv. Co. Ltd. May-10 10,494,157.28 24.5% Mar-12 “ “ Ara28. Wuraola Gomez Street, 762m Lumobs inv. Co. Ltd Aug-10 41,456,623.95 23% May-12 “ “ GRA, Ado39. Aramoko-Ijero-Ido road 27.56km Ratcon Const. Co. Aug-10 1,159,412,953.50 29.64% Aug-12 “ “ Ltd.30. Itawure-Okemesi-Osun 15.67km EBLA Construction April-07 331,740,173.11 79% July-12 “ “ State Border road Ltd.31. Box culvert connecting Ministry of Works April-11 22,370,545.26 90% Reb-12 “ “ Apostolic Faith Community with Ajilosun main road32. Rehab. Of failing Ministry of Works April-11 17,904,159.00 32.5% Aril-12 “ “ culverts along Adebayo-Housing road33. Irele-Ponyan road 11.64km Sanju Sunny Nig. Ltd Dec-08 848,011,338.50 47% June-12 “ “34. Opopogbooro- 5.6km Ortim Nig. Ltd Mar-08 293,341,365.61 49.2% April-12 Pending but Parkview-Afao Junction necessary road35. Ilawe Housing Estate 2km MNE Nig. Ltd May-o8 83,800,143.00 86% April-12 “ “ road36. Ori-Apata-Adebayo 22.6km Hill Gate Continental June-08 116,359,641.69 38% May-12 Pending www.ekitistate.gov.ng
  3. 3. road Ltd37. Access road to CAC 0.3km Hill Gate Continental Dec-08 17,840,228.91 May-12 “ “ Church Adebayo Ltd38. Aaye-Ifisin-Igbole road 6.2km Genius Jack Eng. Ltd Sep-08 257,603,812.14 86% April-12 “ “39. Ijesa Isu Gen. Hospital 265m EKROMA Nov-08 10,102,317.75 50% April-12 “ “ road40. Itapajio-Oke Ado road 9.16km BCCL Dec-08 934,831,286.10 54% “ “41. Oye-Ire road 10.2km BCCL Dec-08 712,337,597.00 42% “ “42. Aisegba-Ijesa Isu road 14.068 Parson Science Eng. Dec-08 795,482,635.50 34.62% Aug-12 “ “ km Ltd43. Igbemo-Ikoyi-Ikole 20km Kopek Construction Dec-08 1,640,000,000.00 32.4% July-12 “ “ road Co. Ltd.44. Ipole Iloro-Ogotun road 11.8 km Dortmund Const. Ltd Dec-08 756,508,408.70 42% Nov-11 “ “45. State Model Estate 3.885km MAC Engineering July-08 147,490,380.61 13.8% June-12 “ “ roads network LTD46. Ode township road 2.5km Parson Science Eng Sep-09 131,432,755.00 25.17% April-12 “ “ Ltd47. Alanaka (Efon) road 2.5km Horizon const. Co. July-09 104,856,086.00 37.87% April-12 “ “ Ltd.48. Ifaki township roads 3.671km Bill const. Co. Ltd. Nov-09 273,894,224.15 34.0% “ “ phase II49. Bishop Fagun’s 1.65km Bill Constr. Co. Ltd Dec-09 91,225,260.00 30% June-12 “ “ House/Hope paper Mill road50. Maintenance of Ado Bill const. Co. Ltd Mar-10 120,856,179.76 21.4% “ “ Township road51. Rubberized bumps Topfoda Venture Ltd May-10 11,056,500.00 70% “ “52. Egbewa-GRA 2.7km Bill contr. Co. Ltd May-10 81,733,010.00 21% June-12 “ “53. Oke-Iya Sharp Corner, Lumobs inv. Co. Ltd Aug-10 10,801,743.75 2% May-12 “ “ Ara Extension54. Ikoro Township road 2.7km Ratcon Const. Co. Aug-10 166,881,456.00 “ “ Ltd55. Ilamo Community road 3km Promised Land Aug-10 123,006,474.43 1% May-12 “ “ Construction56. Olokuta/Ilora road, Ado 736m Zebflux Resources Aug. 10 30,745,197.00 1% June-12 “ “ Nig. Ltd.57. Babamboni road, Iyin Ratcon Const. Co. July-10 25,790,341.50 85% March-12 “ “ Ltd58. Repair of Ado major Bill const. Co. Ltd April-11 79,970,976.16 62% March-12 “ “ www.ekitistate.gov.ng
  4. 4. Axis roads59. Igede-Eyio-Iworoko 19.4km Hajaig Const. Ltd. Dec.08 1,919,496,593.00 9.46% Feb-11 Terminated road60. Itapa-Ijelu road 6.5km Damabog Ltd Dec-07 359,400,124.16 Sep-11 Terminated61. Ido-Ipere-Iludun road 15.8km Flat International Co. Sep-09 379,841,285.12 Dec-11 “ “ Ltd.62. Usi-Ilogbo road 3.375km Ky-fy Global Nig. Sep-08 109,260,169.15 Aug-11 “ “ Ltd63. Ayegunle-Ijurin-Iloro 11.2km Tee-pama Nig. Ltd Sep-08 271,812,645.04 Dec-11 “ “ road64. Oye-Are road 12.148 MAC Engeneering Dec-08 814,981,286.10 Dec-11 “ “ Km Ltd.65. Osi-Epe road 4.85km Alma Essence Ltd Dec-08 366,792,544.13 Oct-11 “ “66. Igbaraodo-Ilawe road 12km Black Hawk Energy Nov-09 231,881,603.13 Oct-11 “ “ Services Ltd67. Erinmope-Odo Owa 1.48km Ramadco Nig. Ltd Aug-10 46,963,302.75 Oct-11 “ “ road68. Ikole-Ara-Isinbode road 18.7km Dortmund Do. Ltd Aug-10 835,671,270.50 Dec-11 “ “69. Repair of Isinbode A.K.H. Samar Junction/Dam/Egbe/ Construction Ltd Aug-10 47,613,943.13 Sep-11 “ “ Ondo State Border70. Repair of Fajuyi-Trade JP Sigma April-11 126,461,150.00 30% Jan-12 Suspended Fair road71. Ijesa-Isu-Ode road 10km Parson Science Eng. Sept-08 384,390,592.90 89.6% March-12 Completed Ltd72. Osun-Iloro road 9.4km Roosco Resources Dec-08 518,321,729.00 90% Feb-12 Completed Const. Ltd73. Awo-Iyin road 6km Ratcon Const. Co. Dec-08 690,561,251.70 93% Feb-12 Completed Ltd74. Rehab. Of Ijigbo-Isato- 1.8km Muck Maroa Const. June-11 72,089,167.50 66% Feb-12 Completed Ile Abiye road Co. Ltd Total www.ekitistate.gov.ng
  5. 5. LIST OF ON-GOING PROJECTS IN EKITI STATES/NO PROJECT LENGTH CONTRACTOR DATE AWARDED REMARKS (KM)1. Omisanjana-132/133kva-Deeper Life 9.3km JP Sigma Nig Ltd Mar-11 New church, Ikere road2. Ado-Afao road 10.745km Kallen Tech. Nig. Ltd April-11 “ “3. Ado-Ilawe road 11.5km Dromo Int. Co. Ltd. May-11 “ “4. Igede-Awo-Ido road 24km Stateco Nig. Ltd Nov-11 “ “5. Ikere-Igbaraodo road 19km Palmyra Constr. Co. Ltd Nov-11 “ “6. Ikogosi-Ipole – Iloro road 24km Roosco Resources Nig Ltd Niv-11 “ “7. Ijan-Ise road 17km RCF Nig. Ltd Nov-11 “ “8. Ijero-Ipoti-Ayetoro road 17km Ratcon Const. Co. Ltd Nov-11 “ “9. Dualization of Old Garage-Ojumose 0.8km Hartland Nig. Ltd Nov-11 “ “ road10. Dualization of Atikankan-Nitel-Baptist 0.9km Hartland Nig. Ltd Nov-11 “ “ road11. Ilawe-Igbaraodo-Ibuji road 17km Dromo Int. Co. Ltd Nov-11 “ “12. Ikole-Ijesa-Isu-Ilumoba road 23km Scoa Nig. PLC Nov-11 “ “13. Ijigbo-Baptist College (Ilawe road) 3.62km Dromo Int. Co Ltd. Nov-11 “ “14. Ojumose-Basiri/Polic Hqrs. (Iyin road) 4.9km Hartland Nig. Ltd Nov-11 “ “15. Fajuyi-University Teaching Hospital 1.65km Hartland Nig. Ltd Nov-11 “ “ road16. Oye-Ikun-Otun road 43km Charvet Nig. Ltd Nov-11 “ “17. Ikere-Emure road 30km RCF Nig. Ltd Dec-07 On-going18. Otun-Osan-Ora Bridge 9.6km Johnson Int. Co Ltd. Sep-09 “ “19. Ikere Ilawe road Jobi Gold Profile Nig April-09 “ :” 20km Ltd20. Odo-Owa-Oke-Ila road 12km Kopek Construction Co.Ltd Jan-09 “ “21. Ado-Iworoko-Ifaki road dualization 19km Hajaig Nig. Ltd Dec-07 “ “22. Ilemeso-Omu road 3.60km Bindigari Const. Ltd. Dec-08 “ “23. Ido-Ile-Okemesi Junction road 8.5km Sadiat Nig. Ltd Dec-08 “ “24. Ewu bridge Roosco Resources Const. Ltd Nov-08 “ “25. Secretariat-Awodele road Extension 260m Maurice Morrison Nig Ltd Mary-10 “ “ www.ekitistate.gov.ng
  6. 6. 26. Oke-Iya Sharp Corner, Ara Lumobs inv. Co. Ltd. May-10 “ “27. Wuraola Gomez Street, GRA, Ado 762m Lumobs inv. Co. Ltd Aug-10 “ “28. Aramoko-Ijero-Ido road 27.56km Ratcon Const. Co. Ltd. Aug-10 On-going29. Itawure-Okemesi-Osun State Border 15.67km EBLA Construction Ltd. April-07 “ “ road30. Box culvert connecting Apostolic Faith Ministry of Works April-11 “ “ Community with Ajilosun main road31. Rehab. Of failing culverts along Ministry of Works April-11 “ “ Adebayo-Housing road32. Irele-Ponyan road 11.64km Sanju Sunny Nig. Ltd Dec-08 “ “ www.ekitistate.gov.ng
  7. 7. www.ekitistate.gov.ng
  8. 8. www.ekitistate.gov.ng
  9. 9. www.ekitistate.gov.ng

×