‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬                            ‫‪Primavera‬‬


                                                  ‫ﺍﻟﻤﻭﺭﺩ: ﻫﻭ ﻜل ﻤﺎﺩﺓ ﺃﻭ ﺁﻟﻴﺔ ﺃﻭ ﻴﺩ ﻋﺎﻤﻠﺔ ﻴﺘﻡ ﺍﺴﺘﺨﺩﺍﻤﻬﺎ ﻓﻲ ﻋﻤﻠﻴﺔ ﻤﺎ‬
                                      ‫ﻨﺨﺘﺎﺭ ‪ Resource‬ﻓﺘﻔﺘﺢ ﻨﺎﻓﺫﺓ‬                ‫ﺇﺫﻥ ﻹﺩﺨﺎل ﺍﻟﻤﻭﺍﺭﺩ ﻤﻥ ﻗﺎﺌﻤﺔ ‪Data‬‬




                    ‫ﻴﺘﻡ ﺇﺩﺨﺎل ﺍﻟﻤﻭﺍﺭﺩ ﻓﻲ ﺤﻘل ‪ Resource‬ﻭﻫﻨﺎ ﻴﺠﺏ ﺍﻟﺘﻤﻴﻴﺯ ﺒﻴﻥ ﺁﻟﻴﺔ ﻭﻴﺩ ﻋﺎﻤﻠﺔ ﻓﻜﻴﻑ ﻴﻤﻜﻥ ﺍﻟﺘﻤﻴﻴﺯ؟‬
                                                                         ‫ﻤﺎﻟﻔﺭﻕ ﺒﻴﻥ ﻤﻭﺍﺭﺩ ﺍﻵﻟﺔ ﻭﻤﻭﺍﺭﺩ ﺍﻟﻴﺩ ﺍﻟﻌﺎﻤﻠﺔ؟‬
                              ‫ﺍﻟﻤﺎﺩﺓ ﻓﻲ ﺠﺩﻭل ﺍﻟﻜﻤﻴﺎﺕ ﻫﻲ ﺜﺎﺒﺘﺔ ﻭﻜﻤﻴﺘﻬﺎ ﻻ ﺘﺯﻴﺩ ﻭﻻ ﺘﻨﻘﺹ ﻤﻊ ﺘﻐﻴﺭ ﻤﺩﺓ ﺘﻨﻔﻴﺫ ﺍﻟﻌﻤﻠﻴﺔ.‬
        ‫ﺒﻴﻨﻤﺎ ﺍﻟﻴﺩ ﺍﻟﻌﺎﻤﻠﺔ ﻴﻤﻜﻥ ﺃﻥ ﺘﺘﻐﻴﺭ ﻜﻤﻴﺘﻬﺎ ﺒﺎﻟﺯﻴﺎﺩﺓ ﻭﺍﻟﻨﻘﺼﺎﻥ ﻤﻊ ﺘﻐﻴﺭ ﻤﺩﺓ ﺘﻨﻔﻴﺫ ﺍﻟﻌﻤﻠﻴﺔ ﻭﻜﺫﻟﻙ ﺍﻵﻟﺔ ﻤﻤﻜﻥ ﺃﻥ ﺘﺘﻐﻴﺭ‬
                                                                                           ‫ﻜﻤﻴﺘﻬﺎ ﺒﺎﻟﺯﻴﺎﺩﺓ ﻭﺍﻟﻨﻘﺼﺎﻥ.‬
                ‫ﺇﺫﻥ ﻟﻠﺘﻤﻴﻴﺯ ﺒﻴﻥ ﻤﻭﺭﺩ ﺁﻟﺔ ﺃﻭ ﻤﺎﺩﺓ ﺃﻭ ﻴﺩ ﻋﺎﻤﻠﺔ ﻨﺭﺍﻋﻲ ﺒﺎﻟﺘﺴﻤﻴﺔ ﺃﻥ ﻴﺩل ﺍﻟﺤﺭﻑ ﺍﻷﻭل ﻋﻠﻰ ﺍﻟﻤﺎﺩﺓ ﻤﺜﻼ :‬
                                                                                             ‫‪ L‬ﻴﺩل ﻋﻠﻰ ﻴﺩ ﻋﺎﻤﻠﺔ‬
                                                                                                   ‫‪ M‬ﻴﺩل ﻋﻠﻰ ﺁﻟﺔ‬
                                                                                                  ‫‪ Q‬ﻴﺩل ﻋﻠﻰ ﻤﺎﺩﺓ‬
       ‫ﻟﻨﻔﺭﺽ ﺍﻟﻤﻬﻨﺩﺴﻴﻥ ﺍﻟﻤﻭﺠﻭﺩﻴﻥ ﻤﻘﺴﻤﻴﻥ ﻟﻤﺠﻤﻭﻋﺎﺕ ﻓﻲ ﺍﻟﻤﺸﺭﻭﻉ " ﻤﺠﻤﻭﻋﺔ ١ + ﻤﺠﻤﻭﻋﺔ ٢ + ﻤﺠﻤﻭﻋﺔ ٣ " .‬
                                   ‫ﺒﺤﺎل ﺤﺼﻭل ﻨﻘﺹ ﻓﻲ ﺃﻱ ﻤﺠﻤﻭﻋﺔ ﻴﻤﻜﻥ ﺃﻥ ﻴﺴﺘﻜﻤل ﺍﻟﻨﻘﺹ ﻤﻥ ﺒﺎﻗﻲ ﺍﻟﻤﺠﻤﻭﻋﺎﺕ‬
                     ‫ﻜﻴﻑ ﺴﻨﺩﺨل ﺃﺴﻤﺎﺀ ﺍﻟﻤﻬﻨﺩﺴﻴﻥ ﺒﺤﻴﺙ ﻴﺘﻌﺎﻤل ﺍﻟﺤﺎﺴﺏ ﻤﻌﻬﻡ ﻋﻠﻰ ﺃﻨﻬﻡ ﻤﻭﺯﻋﻴﻥ ﻟﻤﺠﻤﻭﻋﺎﺕ ٣،٢،١‬
                                                         ‫ﺒﻌﻤﻭﺩ ﺍﻟﻤﻭﺭﺩ ﻨﻜﺘﺏ * ‪ Civil‬ﺜﻡ ﻨﻜﺘﺏ .…,1‪Civil‬‬


                                                                                                       ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬
                                                          ‫01/١‬

‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬
‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬                         Primavera
                            Civil *
                            Civil 1
                            Civil 2   ‫ﺍﻟﻨﺠﻤﺔ ﺘﺸﻜل‬
                            Civil 3
         ‫ ﻓﺈﺫﺍ ﻅﻬﺭ ﻨﻘﺹ ﺒﻬﺎ‬Civil1 ‫ ﻓﺈﻥ ﺍﻟﺤﺎﺴﺏ ﻓﻲ ﻫﺫﻩ ﺍﻟﺤﺎﻟﺔ ﻴﺫﻫﺏ ﺇﻟﻰ‬Civil * ‫ﻭﻫﻨﺎ ﺇﺫﺍ ﻋﻤﻠﻨﺎ ﺘﺴﻭﻴﺔ ﻋﻠﻰ ﺍﻟﻤﻭﺭﺩ‬
                                                                       .‫ ﻭﻫﻜﺫﺍ‬Civil1 ‫ ﻭﻴﻌﻁﻲ‬Civil2 ‫ﻴﺄﺨﺫ ﻤﻥ‬
                                                            Civil 1        ‫ﻭﻫﻨﺎ ﻴﻜﻭﻥ ﺭﺒﻁ ﺍﻟﻌﻤﻠﻴﺎﺕ ﻋﻠﻰ‬
                                                            Civil 2
                                                             Civil3
                                         .‫ ﺤﻴﺙ ﺍﻟﻨﺠﻤﺔ * ﺘﺘﻡ ﻋﻠﻰ ﻭﺠﻭﺩ ﻤﺠﻤﻭﻋﺔ‬Civil* ‫ﻭﻟﻜﻥ ﺍﻟﺘﺴﻭﻴﺔ ﺘﺘﻡ ﻋﻠﻰ‬
                                             ‫ﺍﻟﻴﺩ ﺍﻟﻌﺎﻤﻠﺔ ﻭﺍﺤﺩﺘﻬﺎ ﻤﺠﻤﻭﻋﺔ ﻭﻜل ﻤﺠﻤﻭﻋﺔ ﺤﺴﺏ ﻁﺒﻴﻌﺔ ﺍﻟﻤﻭﺭﺩ ﻤﺜﻼ‬
         ‫ ﻨﺩﺨل ﺒﻴﺎﻨﺎﺕ ﺍﻟﻤﻭﺍﺭﺩ ﺤﻴﺙ ﻓﻲ ﺍﻟﻌﻤﻭﺩ ﺍﻷﻭل ﻨﺩﺨل ﺍﺴﻡ ﺍﻟﻤﻭﺭﺩ ﻭﻓﻲ‬Resource ‫ﺇﺫﻥ ﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﻤﻥ ﻨﺎﻓﺫﺓ‬
                                                    .‫ﺍﻟﻌﻤﻭﺩ ﺍﻟﺜﺎﻨﻲ ﻨﺩﺨل ﺍﻟﻭﺤﺩﺓ ﻤﺜﻼ ﻭﺤﺩﺓ ﺍﻟﻴﺩ ﺍﻟﻌﺎﻤﻠﺔ ﻫﻲ ﻤﺠﻤﻭﻋﺔ‬
       Resource                         Description                          unit       price per unit

                                                    LABOUR
       L_CARPEN         ‫ﻨﺠﺎﺭ ﺒﻴﺘﻭﻥ‬       2 carpenter                           no.         20.00/day
       L_ELECTR          ‫ﻜﻬﺭﺒﺎﺌﻲ‬         2worker                               no.         11.00/day
       L_MASON             ‫ﺒﻨﺎﺀ‬          2worker                               no.        11.00/day
       L_OR_CAR "‫2 ﻨﺠﺎﺭ ﺸﺭﻗﻲ "ﻟﻸﺒﻭﺍﺏ ﺍﻟﺩﺍﺨﻠﻴﺔ‬worker(oriental carpenter)        no.        11.00/day
       L_OVERH ‫ ﺍﻟﻬﻴﻜل ﺍﻹﺩﺍﺭﻱ ﻟﻠﻤﺸﺭﻭﻉ‬over head man power                       no.        285232.00
       L_O_work        ‫ﻋﺎﻤل ﻋﺎﺩﻱ‬         ordinary worker                       no.        5.00/day
       L_PAINT         ‫ﺩﻫﺎﻥ ﻋﺎﺩﻱ‬         Painter 1 Worker                      no.        5.00/day
       L_PLAST             ‫ﻤﻠﻴﺱ‬          2 worker                              no.        11.00/day
       L_POLISH            ‫ﺠﻠﻰ‬           Polisher 1 worker                                5.00/day
       L_SANITA       ‫ﻤﻌﻠﻡ ﺼﺤﻴﺔ‬          Sanitary 2 worker                     no.        11.00/day
       L_STUDY ‫ ﺍﻟﻬﻴﻜل ﺍﻟﺩﺍﺭﺱ ﻟﻠﻤﺸﺭﻭﻉ‬Study the project                                    114100.00/day
       L_ST_FIX           ‫ﺤﺩﺍﺩ‬           Steel fixer 2 worker                  no.         20.00/day
       L_SURVEY           ‫ﺎﺡ‬ ‫ﻤ‬
                             ‫ﺴ‬           Survey -3 labor                       no.         16.00/day
       L_TILES            ‫ﺒﻼﻁ‬            2worker                               no.         11.00/day
                                                MACHINE
       M_BAGER              ‫ﺒﺎﻏﺭ‬          Bagger                                 no.            240.00/day
       M_BOBCAT                           BobCat                                 no.            120.00/day
                                                                                                  ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬
                                                       ٢/10

PDF created with pdfFactory trial version www.pdffactory.com
‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬                 Primavera
       M_BUS          ‫ﺒﺎﺹ‬                 Bus                                no.      80.00/day
       M_CAR         ‫ﺴﻴﺎﺭﺓ‬                Car for eng.                       no.      40.00/day
       M_CA_CRA ‫ﺴﻴﺎﺭﺓ ﻤﻊ ﺭﺍﻓﻌﺔ‬            Car with crane                     no.      160.00/day
       M_COMPAC      ‫ﻤﺩﺤﻠﺔ‬                Compactor                          no.      40.00/day
       M_VIBRAT   ‫ﺭﺠﺎﺝ ﺨﺭﺴﺎﻨﺔ‬             Vibrator                           no.      20.00/day
       M_SERVIS   ‫ﺴﻴﺎﺭﺍﺕ ﺨﺩﻤﺔ‬             Service                            no.      50.00/day
       M_TRACTO     ‫ﺘﺭﺍﻜﺘﻭﺭ‬               Tractors                           no.      50.00/day
       M_WH_LO ‫ﻟﺘﺴﻭﻴﺔ ﺍﻟﺸﻭﺍﺭﻉ‬             Wheel loaders                      no.      240.00/day
       M_TRUCK       ‫ﺸﺎﺤﻨﺔ‬                Truck 12 m3                        no.     105.00/day
       M_WATER ‫ﺸﺎﺤﻨﺔ ﻤﻊ ﺼﻬﺭﻴﺞ‬             Truck for water 20 m3              no.      120.00/day
       M_WL_CRA ‫ﺭﺍﻓﻌﺔ ﺠﺩﺍﺭﻴﺔ‬              Wall crane                         no.      16.00/day

                                              MATERIAL
       Q_ASPHAL         ‫ﺃﺴﻔﻠﺕ‬             Asphalt work                         Ls    66480.00
       Q_AS_ELA ‫ ﻤﻭﺍﺩ ﺍﻹﻨﻬﺎﺀﺍﺕ ﺍﻟﻜﻬﺭﺒﺎﺌﻴﺔ‬Fixture electricity material          Ls    2200.00
       Q_AS_SSA ‫ﻤﻭﺍﺩ ﺇﻨﻬﺎﺀﺍﺕ ﺼﺤﻴﺔ‬         Fixture sanitary material           Ls     3200.00
       Q_BARDOR ‫ﺤﺠﺭ ﺭﺼﻴﻑ‬                  Curb stone material                  Lm    3.00
       Q_BLC_FG      ‫ﺒﻠﻭﻙ ﻟﻠﺴﻭﺭ‬           Block for fence                      M3    20.00
       Q_BLOCK            ‫ﺒﻠﻭﻙ‬            Block                                M3    20.00
       Q_BL_ELA ‫ ﺴﻭﺍﺩﺍﺕ ﻜﻬﺭﺒﺎﺀ‬Primary installation electrical material Ls            200.00
       Q_BL_SAA ‫ ﺴﻭﺍﺩﺍﺕ ﺼﺤﻴﺔ‬Primary installation sanitary material Ls                1000.00
       Q_CERAMI      ‫ﺴﻴﺭﺍﻤﻴﻙ‬              Ceramic material                     M2    4.50
       Q_COL_LI     ‫ﺃﻋﻤﺩﺓ ﺇﻨﺎﺭﺓ‬           Columns for external lighting no           200.00
       Q_CONC20 ٢٠٠ ‫ﺨﺭﺴﺎﻨﺔ ﻋﻴﺎﺭ‬           Concrete 200kg/m3                    M3    17.00
       Q_CONC30 ٣٠٠ ‫ﺨﺭﺴﺎﻨﺔ ﻋﻴﺎﺭ‬           Concrete 300 kg/m3                   M3    20.00
       Q_CONC35 ٣٥٠ ‫ﺨﺭﺴﺎﻨﺔ ﻋﻴﺎﺭ‬           Concrete 350 kg/m3                   M3    23.00
       Q_CRU_S        ‫ﺒﻘﺎﻴﺎ ﻤﻘﺎﻟﻊ‬         Crushed stone material               M3    3.50
       Q_ELE_DI ‫ﻤﻭﺍﺩ ﻏﺭﻓﺔ ﺍﻟﻜﻬﺭﺒﺎﺀ‬        Tran station dis.                    Ls    13500.00
       Q_EX_E_M ‫ ﻤﻭﺍﺩ ﺍﻟﺘﻤﺩﻴﺩﺍﺕ ﺍﻟﻜﻬﺭﺒﺎﺌﻴﺔ ﺍﻟﺨﺎﺭﺠﻴﺔ‬External electrical material Ls   132000.00
       Q_E_S_PM ‫ ﺍﻷﻨﺎﺒﻴﺏ ﺍﻟﺼﺤﻴﺔ ﺍﻟﺨﺎﺭﺠﻴﺔ‬External sanitary pipe material Lm
       Q_FORMWO ٣ ‫ﻗﺎﻟﺏ ﺨﺸﺒﻲ ﻡ‬             Formwork material per m3             M3    3.00
       Q_FORM_W ٢‫ﻗﺎﻟﺏ ﺨﺸﺒﻲ ﻡ‬              Formwork material per m2             M2    1.00
                                                                                       ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬
                                                     ٣/10

PDF created with pdfFactory trial version www.pdffactory.com
‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬                          Primavera
       Q_F_F_M      ‫ﻤﻭﺍﺩ ﻤﻜﺎﻓﺤﺔ ﺍﻟﺤﺭﻴﻕ‬    Fire fighting material        Ls                       31000.00
       Q_GARDEN          ‫ﻤﻭﺍﺩ ﺍﻟﺤﺩﺍﺌﻕ‬     Garden material               Ls
       Q_INSULA          ‫ﻤﻭﺍﺩ ﺍﻟﻌﺯل‬       Insulation material & Labour Ls                    1600.00
       Q_INS_UW‫ ﻤﻭﺍﺩ ﻏﺯل ﺨﺯﺍﻥ ﻤﻁﻤﻭﺭ‬Insulation for under ground water tank                 M2 3.00
       Q_MORTAR              ‫ﻤﻭﻨﺔ‬         Mortar                        M3                   17.00
       Q_PAINTM             ‫ﺩﻫﺎﻥ‬          Paint material                Ton
       Q_PAVIOR         ‫ﺒﻼﻁ ﺃﺭﻀﻴﺔ‬         Cement screed PC_Paviors      M2                       3.70
       Q_PI_RNE‫ﻤﻭﺍﺴﻴﺭ ﻟﺸﺒﻜﺔ ﺼﺭﻑ ﻤﻴﺎﻩ ﺍﻷﻤﻁﺎﺭ‬Pipe for rain water net work Lm                       4.50
       Q_PI_SNE‫ ﻤﻭﺍﺴﻴﺭ ﺼﺭﻑ ﻤﻴﺎﻩ ﻤﺎﻟﺤﺔ‬Pipe for sanitary water net work Lm                         4.00
       Q_PUMP     ‫ﺘﺠﻬﻴﺯﺍﺕ ﻤﺤﻁﺔ ﺍﻟﻀﺦ‬       Pumping station material      Ls                       11635.00
       Q_REINFO      ‫ﺤﺩﻴﺩ ﺍﻟﺘﺴﻠﻴﺢ‬         Steel for concrete            Ton                      260.00
       Q_RENDR ‫ ﻤﻭﺍﺩ ﺭﺸﺔ ﺘﻴﺭﻭﻟﻴﺔ‬External rendering with white cement M3                          75.00
       Q_SCIRTI           ‫ﺍﻟﻨﻌﻠﺔ‬          Skirting material             Lm                       1.50
       Q_SERVIC       ‫ﻨﺜﺭﻴﺎﺕ ﺍﻟﻤﻭﻗﻊ‬       Paper & computer & ….         Ls                       171140.00
       Q_SEW_PI ‫ ﻤﻭﺍﺴﻴﺭ ﺼﺭﻑ ﺼﺤﻲ‬Swage pipe                               Lm                       22.50
       Q_SOIL ‫ ﻤﻭﺍﺩ ﺭﺩﻤﻴﺔ ﻤﻥ ﺨﺎﺭﺝ ﺍﻟﻤﻭﻗﻊ‬Back filling from barrow        M3                       1.60
       Q_STAIRS        ‫ﺒﻼﻁ ﺃﺩﺭﺍﺝ‬          Stair tiles material          Lm                       4.50
       Q_STEEL        ‫ﻤﻭﺍﺩ ﺃﻋﻤﺎل ﻤﻌﺩﻨﻴﺔ‬   Metal works                   Ton                      700.00
       Q_ST_GAT       ‫ﻤﻭﺍﺩ ﺍﻟﺒﻭﺍﺒﺔ‬        Gate for fence                no.                      1000.00
       Q_TEL_M ‫ ﻤﻭﺍﺩ ﺸﺒﻜﺔ ﺍﻟﺘﻠﻔﻭﻥ ﺍﻟﺨﺎﺭﺠﻴﺔ‬External telephone material   Ls                       16850.00
       Q_TERAZO ‫ﺒﻼﻁ ﻋﺎﺩﻱ‬                  Terrazzo material*10          M2                       3.00
       Q_U_B_PI ‫ ﻤﻭﺍﺴﻴﺭ ﺍﻟﺨﺯﺍﻥ ﺍﻟﻤﻁﻤﻭﺭ‬Un gr . pipe for building         Ls                       542.50
       Q_WI_ELA ‫ﻤﻭﺍﺴﻴﺭ ﺍﻷﺴﻼﻙ ﺍﻟﻜﻬﺭﺒﺎﺌﻴﺔ‬Wire electricity material        Ls                       600.00
       Q_W_DOOR ‫ﺃﺒﻭﺍﺏ ﺨﺸﺒﻴﺔ‬               Wooden doors                  Ls                       3375.00

           ‫ ﻴﺴﺘﺨﺩﻡ ﻟﺘﺤﻴﺩ ﻤﺎ ﺇﺫﺍ ﻜﺎﻥ‬Resource ‫ ﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﺒﻨﺎﻓﺫﺓ‬Driving ‫ ﻓﻲ ﺍﻟﻌﻤﻭﺩ ﺍﻟﺜﺎﻟﺙ‬Driving ‫ﺍﻟﺨﺎﺼﺔ‬
                                                                                             ‫ﺍﻟﻤﻭﺭﺩ ﻤﺘﺤﻜﻡ ﺃﻡ ﻻ‬
         ‫ﻤﺎﻟﻤﻘﺼﻭﺩ ﺒﻤﺘﺤﻜﻡ ؟ ﺇﺫﺍ ﻜﺎﻥ ﺍﻟﻤﻭﺭﺩ ﻏﻴﺭ ﻤﺘﺤﻜﻡ ﻓﻤﻬﻤﺎ ﺯﺍﺩﺕ ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﺃﻭ ﻨﻘﺼﺕ ﺘﺒﻘﻰ ﺍﻟﻤﺩﺓ ﺜﺎﺒﺘﺔ ﻭﻻ ﺘﺘﻐﻴﺭ‬
                          ‫ﺒﻴﻨﻤﺎ ﺇﺫﺍ ﻜﺎﻥ ﺍﻟﻤﻭﺭﺩ ﻤﺘﺤﻜﻡ ﻓﺈﻥ ﻤﺩﺓ ﺍﻟﻌﻤﻠﻴﺔ ﺘﺯﻴﺩ ﺃﻭ ﺘﻨﻘﺹ ﺒﺯﻴﺎﺩﺓ ﺃﻭ ﻨﻘﺼﺎﻥ ﺍﻟﻤﻭﺭﺩ‬
                                                         Driving ‫ﻏﺎﻟﺒﺎ ﻓﻲ ﻜل ﺍﻟﺨﻁﻁ ﺍﻟﺯﻤﻨﻴﺔ ﻻ ﻨﻔﻌل ﻫﺫﺍ ﺍﻟﺨﻴﺎﺭ‬



                                                                                                   ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬
                                                       ٤/10

PDF created with pdfFactory trial version www.pdffactory.com
‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬                         ‫‪Primavera‬‬
         ‫ﺍﻟﺨﺎﺼﻴﺔ ‪ Base‬ﻓﻲ ﺍﻟﻌﻤﻭﺩ ﺍﻟﺭﺍﺒﻊ ﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﺒﻨﺎﻓﺫﺓ ‪ Resource‬ﺭﻭﺯﻨﺎﻤﺔ ﺍﻟﻤﻭﺭﺩ ﺭﻭﺯﻨﺎﻤﺔ ﺍﻟﻤﺸﺭﻭﻉ‬
        ‫ﻜﺎﻥ ﺭﻗﻤﻬﺎ ١ ﻭﻫﻨﺎ ﺴﻴﺄﺨﺫ ﺭﻭﺯﻨﺎﻤﺔ ﺍﻟﻤﺸﺭﻭﻉ ﺤﻴﺙ ﻴﺸﻜل ﻨﺴﺨﺔ ﻋﻨﻬﺎ ﻭﻴﺴﻤﻴﻬﺎ ﺒﺎﺴﻡ ﺭﻭﺯﻨﺎﻤﺔ ﺍﻟﻤﻭﺭﺩ ﻭﻴﺴﻤﺢ‬
                                                                                  ‫ﺒﺈﺠﺭﺍﺀ ﺃﻱ ﺘﻌﺩﻴل ﻋﻠﻴﻬﺎ‬




                        ‫ﻓﻲ ﺍﻟﺠﺯﺀ ﺍﻟﺴﻔﻠﻲ ﻤﻥ ﻨﺎﻓﺫﺓ ‪ Resource‬ﻟﺩﻴﻨﺎ ﻨﺎﻓﺫﺓ ‪ Limits‬ﺍﻟﺤﺩﻭﺩ ﻭﻨﺎﻓﺫﺓ ‪ Prices‬ﺍﻟﻜﻠﻑ‬
                                                         ‫١- ‪ Limits‬ﺍﻟﺤﺩﻭﺩ ﻫﻲ ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﺍﻟﻤﺘﻭﻓﺭﺓ ﻟﺩﻴﻨﺎ‬
                                                      ‫‪ Normal‬ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﺍﻻﻋﺘﻴﺎﺩﻴﺔ ﺍﻟﻤﻭﺠﻭﺩﺓ ﻓﻲ ﺍﻟﻤﻭﻗﻊ‬
                                              ‫ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﺍﻟﻌﻅﻤﻰ ﺍﻟﺘﻲ ﻴﻤﻜﻥ ﺃﻥ ﺘﺘﺄﻤﻥ ﻓﻲ ﺍﻟﻤﻭﻗﻊ‬   ‫‪Max‬‬
                                          ‫ﺘﺤﺩﻴﺩﻩ ﻟﻪ ﻁﺭﻴﻘﺘﻴﻥ ١- ﺍﻟﺸﺭﻜﺔ ﺘﺤﺩﺩ ٥١ ﻤﺠﻤﻭﻋﺔ ﻹﻨﻬﺎﺀ ﺍﻟﻤﺸﺭﻭﻉ‬
         ‫٢-ﺍﻟﺸﺭﻜﺔ ﺘﺴﺄل ﻤﺩﻴﺭ ﺍﻟﻤﺸﺭﻭﻉ ﻜﻡ ﻤﺠﻤﻭﻋﺔ ﻨﺠﺎﺭ ﻴﺤﺘﺎﺝ ﻹﻨﻬﺎﺀ ﺍﻟﻤﺸﺭﻭﻉ ﻓﻲ ﺍﻟﻤﺩﺓ‬
            ‫ﺍﻟﻤﺤﺩﺩﺓ ﻭﺒﻬﺫﻩ ﺍﻟﺤﺎﻟﺔ ﻤﺩﻴﺭ ﺍﻟﻤﺸﺭﻭﻉ ﻴﻀﻊ ﺍﻟﺨﻁﺔ ﺍﻟﺯﻤﻨﻴﺔ ﺒﺎﻟﻜﺎﻤل ﻭﺒﺎﻷﺨﻴﺭ ﻴﺤﺴﺏ‬
        ‫ﺒﺎﻟﺒﺭﻨﺎﻤﺞ ﻜﻡ ﻤﺠﻤﻭﻋﺔ ﻴﺤﺘﺎﺝ ﻭﺍﻟﻨﺎﺘﺞ ﺍﻟﺘﻲ ﻴﻅﻬﺭ ﻤﻌﻪ ﻴﺯﻴﺩﻩ ﺒﻨﺴﺒﺔ ٠٢ % ﻭﻴﻌﻁﻲ ﺍﻟﻨﺎﺘﺞ‬
                                                                          ‫ﻜـ‪Normal‬‬
        ‫ﺍﻟﺨﺎﺼﻴﺔ ‪ through‬ﻓﻲ ﺍﻟﻌﻤﻭﺩ ﺍﻟﺨﺎﻤﺱ ﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﺒﻨﺎﻓﺫﺓ ‪ Resource‬ﺘﻌﺒﺭ ﻋﻥ ﺘﻐﻴﺭ ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﻤﻊ‬
                                                                                                  ‫ﺍﻟﺯﻤﻥ‬

                                                                                                ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬
                                                     ‫01/٥‬

‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬
‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬                         ‫‪Primavera‬‬
        ‫ﻤﺜﻼ ﺸﺭﻜﺔ ﺴﺘﺅﻤﻥ ﻟﻠﻤﺸﺭﻭﻉ ﺨﻼ ﻤﺩﺓ ﻤﻌﻴﻨﺔ ﻤﻥ ﺘﺎﺭﻴﺦ .... ﺇﻟﻰ ﺘﺎﺭﻴﺦ ....... ٥١ ﻋﺎﻤل ﺜﻡ ﻭﺒﻌﺩ ﻤﺩﺓ ﺯﻤﻨﻴﺔ‬
       ‫ﻤﻌﻴﻨﺔ ﺃﺭﺒﻌﺔ ﺃﺸﻬﺭ ﻤﺜﻼ ﻟﺩﻴﻬﺎ ﻋﻤﺎل ﻴﻌﻤﻠﻭﻥ ﻟﺩﻯ ﺸﺭﻜﺔ ﺃﺨﺭﻯ ﻭﺴﻴﻨﻬﻭﻥ ﻋﻤﻠﻬﻡ ﺒﺘﺎﺭﻴﺦ ..... ﻓﺒﻌﺩ ﻫﺫﺍ ﺍﻟﺘﺎﺭﻴﺦ‬
         ‫ﻴﻤﻜﻥ ﺇﻀﺎﻓﺔ ٥ ﻤﺠﻤﻭﻋﺎﺕ ﻤﻨﻬﻡ ﺃﻭ ٠١ ﻟﻤﺸﺭﻭﻋﻨﺎ ﻭﺒﻬﺫﺍ ﻴﺼﺒﺢ ﻟﺩﻴﻨﺎ ٠٢ ﻤﺠﻤﻭﻋﺔ ﻋﻤﺎل ، ﻭﺒﻌﺩ ﺸﻬﺭ ﺘﻌﻭﺩ‬
                                    ‫ﻜﻤﻴﺔ ﺍﻟﻤﻭﺍﺭﺩ ﻜﺎﻟﺴﺎﺒﻕ ﻭﻫﺫﺍ ﻨﺩﺨﻠﻪ ﻤﻥ ﺨﻼل ﺍﻟﻌﻤﻭﺩ ‪ Through‬ﻤﺜﻼ ﻨﺩﺨل:‬
          ‫‪Normal‬‬            ‫‪Max‬‬          ‫‪Through‬‬
            ‫21‬              ‫51‬           ‫7002/5/2‬
            ‫02‬              ‫52‬           ‫7002/9/3‬
            ‫21‬              ‫51‬           ‫ﻨﺘﺭﻙ ﻓﺭﺍﻍ‬             ‫ﻓﻴﺄﺨﺫ ﺍﻟﺭﻗﻡ ٥١ ﻋﻠﻰ ﻜﺎﻤل ﺍﻟﻤﺸﺭﻭﻉ‬


                                                                                 ‫‪ Price‬ﻜﻠﻔﺔ ﺍﻟﻤﺠﻤﻭﻋﺔ‬
                                                                    ‫ﻤﺎ ﻫﻲ ﻭﻅﻴﻔﺔ ﺍﻟﻤﻔﺘﺎﺡ ‪ Calculate‬؟‬
         ‫ﻟﻨﻔﺭﺽ ﺃﻨﻨﺎ ﺃﺩﺨﻠﻨﺎ ﺍﻟﻤﻭﺍﺭﺩ ﻭﺍﻟﻌﻤﻠﻴﺎﺕ ﻭﺭﺒﻁﻨﺎ ﺍﻟﻤﻭﺍﺭﺩ ﻤﻊ ﺍﻟﻌﻤﻠﻴﺎﺕ ﺜﻡ ﺤﺩﺙ ﺘﻐﻴﺭ ﻓﻲ ﺴﻌﺭ ﺍﻟﻤﻭﺭﺩ ﻜﺎﻥ‬
            ‫ﻨﻀﻐﻁ ﻤﻔﺘﺎﺡ ‪ Calculate‬ﻓﻴﻌﻴﺩ ﺍﻟﺒﺭﻨﺎﻤﺞ‬         ‫ﻫﻨﺎ ﻨﺤﺘﺎﺝ ﻟﺘﻌﺩﻴل ﺍﻟﺴﻌﺭ‬      ‫٠٠١ ﺃﺼﺒﺢ ٥٢١‬
                                            ‫ﺤﺴﺎﺏ ﻜﻠﻑ ﺍﻟﻌﻤﻠﻴﺎﺕ ﻜﻠﻬﺎ ﻟﻠﻤﺸﺭﻭﻉ ﺍﻋﺘﻤﺎﺩﺍ ﻋﻠﻰ ﺍﻟﻜﻠﻔﺔ ﺍﻟﺠﺩﻴﺩﺓ‬
                                                                    ‫ﻤﺎ ﻫﻲ ﻭﻅﻴﻔﺔ ﺍﻟﻤﻔﺘﺎﺡ ‪ Transfare‬؟‬
                                                   ‫ﻭﻅﻴﻔﺘﻪ ﻨﻘل ﺍﻟﻤﻭﺍﺭﺩ ﻤﻥ ﺍﻟﻤﺸﺭﻭﻉ ﺇﻟﻰ ﺍﻟﻤﺸﺭﻭﻉ ﺍﻟﺤﺎﻟﻲ‬
                                                                   ‫ﻤﺎ ﻫﻲ ﻭﻅﻴﻔﺔ ﺍﻟﻤﻔﺘﺎﺡ ‪ Calendars‬؟‬
                                 ‫ﻭﻅﻴﻔﺘﻪ ﺃﻥ ﺍﻟﺒﺭﻨﺎﻤﺞ ﻴﻔﺘﺢ ﺍﻟﺭﻭﺯﻨﺎﻤﺔ ﻤﻥ ﺃﺠل ﺘﻌﺩﻴل ﺭﻭﺯﻨﺎﻤﺔ ﺍﻟﻤﻭﺭﺩ ﺍﻟﺤﺎﻟﻲ‬
                        ‫ﺍﻷﻥ ﺴﻨﺘﺤﺩﺙ ﻋﻥ ﻭﻅﻴﻔﺔ ﺍﻟﻨﺎﻓﺫﺓ ‪ Resource Curve‬ﻭﺍﻟﺘﻲ ﻨﻔﺘﺤﻬﺎ ﻤﻥ ﺍﻟﻘﺎﺌﻤﺔ ‪Data‬‬
              ‫‪Data‬‬                ‫‪Resource curve‬‬




                                                                                                ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬
                                                      ‫01/٦‬

‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬
‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬                            ‫‪Primavera‬‬
           ‫ﻫﻭ ﻤﻨﺤﻨﻲ ﺩﺨﻭل ﺍﻟﻤﻭﺭﺩ ﺇﻟﻰ ﺍﻟﻌﻤﻠﻴﺔ ، ﻭﺍﻟﻠﻭﻥ ﺍﻷﺼﻔﺭ ﻴﻌﺒﺭ ﻋﻥ ﺍﻟﻜﻤﻴﺔ ﺍﻟﻴﻭﻤﻴﺔ ﺒﻴﻨﻤﺎ ﺍﻟﻠﻭﻥ ﺍﻷﺯﺭﻕ ﻴﻌﺒﺭ ﻋﻥ‬
                                                                                                         ‫ﺍﻟﺘﺭﺍﻜﻤﻴﺔ‬
        ‫ﻨﻀﻐﻁ ﻤﻔﺘﺎﺡ ‪ Display‬ﻟﻤﻌﺭﻓﺔ ﺃﻨﻭﺍﻉ ﺍﻟﻤﻨﺤﻨﻴﺎﺕ ﺍﻟﻤﺘﻭﻓﺭﺓ ﻟﺩﻴﻨﺎ‬            ‫ﻟﻤﻌﺭﻓﺔ ﺃﻨﻭﺍﻉ ﺍﻟﻤﻨﺤﻨﻴﺎﺕ ﺍﻟﻤﺘﻭﻓﺭﺓ ﻟﺩﻴﻨﺎ؟‬



                                                                                               ‫ﻨﻨﻘﺭ ﻫﻨﺎ ﻓﺘﻅﻬﺭ ﺃﺸﻜﺎل‬
                                                                                                      ‫ﻤﻨﺤﻨﻴﺎﺕ ﺠﺩﻴﺩﺓ‬




                                               ‫‪ Linear‬ﺍﻟﻤﻭﻀﺢ ﺒﺎﻟﺯﺍﻭﻴﺔ ﺍﻟﻴﺴﺭﻯ ﺍﻟﻌﻠﻴﺎ ﻟﻠﻨﺎﻓﺫﺓ‬           ‫١-‬
                                       ‫ﻨﻼﺤﻅ ﺃﻨﻪ ﺜﺎﺒﺕ ﻜل ﻴﻭﻡ ﻴﺯﻴﺩ ﺒﻨﻔﺱ ﺍﻟﻨﺴﺒﺔ " ﻤﺜﻠﺙ ﻤﺘﺴﺎﻭﻱ ﺍﻟﺴﺎﻗﻴﻥ "‬
                                           ‫‪ Triangular‬ﺍﻟﻤﻭﻀﺢ ﺒﺎﻟﺯﺍﻭﻴﺔ ﺍﻟﻴﻤﻨﻰ ﺍﻟﻌﻠﻴﺎ ﻟﻠﻨﺎﻓﺫﺓ‬           ‫٢-‬
                                                                        ‫ﻴﻜﻭﻥ ﻗﻠﻴل ﻭﻴﺯﻴﺩ ﺜﻡ ﻴﻘل ﻤﺭﺓ ﺜﺎﻨﻴﺔ‬
                              ‫‪ Triangular Increase‬ﺍﻟﻤﻭﻀﺢ ﺒﺎﻟﺯﺍﻭﻴﺔ ﺍﻟﻴﺴﺭﻯ ﺍﻟﺴﻔﻠﻰ ﻟﻠﻨﺎﻓﺫﺓ‬               ‫٣-‬
                                                                   ‫ﺒﺩﺍﻴﺔ ﻤﺜﻠﺜﻴﺔ ﻭﺘﺯﺩﺍﺩ ﺤﺘﻰ ﻨﻬﺎﻴﺔ ﺍﻟﻤﺸﺭﻭﻉ‬
                               ‫‪ Triangular Decrease‬ﺍﻟﻤﻭﻀﺢ ﺒﺎﻟﺯﺍﻭﻴﺔ ﺍﻟﻴﻤﻨﻰ ﺍﻟﺴﻔﻠﻰ ﻟﻠﻨﺎﻓﺫﺓ‬              ‫٤-‬
                                                 ‫ﻤﺜﻠﺙ ﻤﺘﻨﺎﻗﺹ ، ﺒﺩﺍﻴﺔ ﻜﺒﻴﺭﺓ ﻭﺘﻨﺎﻗﺹ ﺤﺘﻰ ﻨﻬﺎﻴﺔ ﺍﻟﻤﺸﺭﻭﻉ‬
                                              ‫ﻭﺘﻭﺠﺩ ﻤﺠﻤﻭﻋﺎﺕ ﺃﺨﺭﻯ ﻤﻥ ﺍﻟﻤﻨﺤﻨﻴﺎﺕ ﻹﻅﻬﺎﺭﻫﺎ ﻨﻀﻐﻁ ﺯﺭ‬
                                               ‫ﻟﻪ ﻓﺎﺌﺩﺘﻴﻥ:‬         ‫ﻤﺎ ﻫﻲ ﺍﻟﻔﺎﺌﺩﺓ ﻤﻥ ﺍﺴﺘﺨﺩﺍﻡ ﻫﺫﺍ ﺍﻟﻤﻨﺤﻨﻲ؟‬
                                       ‫١- ﺘﻐﻴﺭ ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﺍﻟﻴﻭﻤﻴﺔ ﺍﻟﺩﺍﺨﻠﺔ ﻟﻠﻌﻤﻠﻴﺔ ﻭﻫﺫﺍ ﻓﻴﻪ ﻨﻘﺼﺎﻥ ﻟﻠﻜﻠﻔﺔ‬
                                     ‫٢- ﺘﻭﻓﻴﺭ ﻜﻤﻴﺎﺕ ﺍﻟﻤﻭﺍﺭﺩ ﻟﻌﻤﻠﻴﺎﺕ ﺃﺨﺭﻯ ﺘﻜﻭﻥ ﻤﺘﺯﺍﻤﻨﻪ ﻤﻊ ﻫﺫﻩ ﺍﻟﻌﻤﻠﻴﺔ‬
         ‫ﺘﺨﻔﻴﺽ ﻓﻲ ﺍﻟﻜﻠﻔﺔ ﻭﺘﻭﻓﻴﺭ ﻓﻲ ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﺍﻟﻤﺴﺘﺨﺩﻡ ﻻﺴﺘﺨﺩﺍﻤﻪ ﻓﻲ ﻋﻤﻠﻴﺎﺕ ﻤﺘﺯﺍﻤﻨﺔ ﻤﻊ ﺍﻟﻌﻤﻠﻴﺔ ﺍﻟﺤﺎﻟﻴﺔ‬
                                          ‫ﻨﻌﻭﺩ ﻟﻨﺎﻓﺫﺓ ‪Resource Curve‬‬                   ‫ﺍﻵﻥ ﻟﺘﺸﻜﻴل ﻤﻨﺤﻨﻲ‬


                                                                                                     ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬
                                                       ‫01/٧‬

‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬
‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬                         ‫‪Primavera‬‬
          ‫ﺜﻡ ﻭﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﻨﻀﻴﻑ ﺴﻁﺭ ﻓﻲ ﻗﺴﻡ ‪ " Designator‬ﻨﺤﺫﻑ ﺍﻟﺴﻁﺭ ﺍﻷﺨﻴﺭ ٩ ﻭﻨﻀﻴﻑ ﺒﺩﻴﻼ ﻟﻪ‬
                                                                             ‫"ﻭﻨﺴﻤﻴﻪ ﻭﻨﻜﺘﺏ ﻭﺼﻑ ﻟﻪ‬
             ‫‪Designator‬‬            ‫‪Title‬‬
              ‫9‬                    ‫‪test‬‬




         ‫ﺜﻡ ﻨﻌﺩل ﺒﺎﻟﻨﺴﺏ ﺍﻟﻤﻜﺘﻭﺒﺔ ﺃﺴﻔﻠﻪ ﺒﺸﻜل ﻻ ﻋﻠﻰ ﺍﻟﺘﻌﻴﻴﻥ ﻭﻨﻼﺤﻅ ﺘﻐﻴﺭ ﻟﻭﻥ ﺍﻟﻤﺩﺓ ‪ Total‬ﺇﻟﻰ ﺍﻟﻠﻭﻥ ﺍﻷﺤﻤﺭ‬
                                            ‫ﻋﻨﺩﻤﺎ ﺘﺯﻴﺩ ﻋﻥ ٠٠١ ﺤﻴﺙ ﻴﺠﺏ ﺃﻥ ﺘﺒﻘﻰ ﻗﻴﻤﺔ ‪١٠٠ = Total‬‬
          ‫ﻭﻹﺭﺠﺎﻉ ﻫﺫﻩ ﺍﻟﻨﺴﺒﺔ ‪ Total‬ﺇﻟﻰ ٠٠١ ﻨﻀﻐﻁ ﺯﺭ ‪ Prorate‬ﺤﻴﺙ ﻴﻘﻭﻡ ﻫﺫﺍ ﺍﻟﺯﺭ ﺒﺈﺭﺠﺎﻉ ﺍﻟﻨﺴﺒﺔ ﺇﻟﻰ‬
                                        ‫٠٠١% ﻋﻥ ﻁﺭﻴﻕ ﺘﺨﻔﻴﻀﻪ ﺍﻟﻌﻤﻠﻴﺎﺕ ﺒﻨﺴﺒﺔ ﺜﺎﺒﺘﺔ ﻟﻜل ﺍﻟﻤﺩﺩ ﺍﻟﺯﻤﻨﻴﺔ‬
                        ‫ﻭﻅﻴﻔﺔ ﺍﻟﺯﺭ ‪ Template‬ﺃﻨﻪ ﻴﺄﺨﺫ ﻤﻨﺤﻨﻲ ﻤﻭﺠﻭﺩ ﺴﺎﺒﻘﺎ ﻭﻴﺸﻜل ﻨﺴﺨﺔ ﻋﻨﻪ ﻭﻴﻌﺩل ﻋﻠﻴﻪ‬
                                                          ‫ﻨﻀﻐﻁ ﻤﻔﺘﺎﺡ ‪ Template‬ﻓﺘﻅﻬﺭ ﻨﺎﻓﺫﺓ‬




                                                                                    ‫ﻨﺨﺘﺎﺭ ﻤﻨﻬﺎ ﺸﻜﻼ ﻤﺎ‬




                                                                                                ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬
                                                      ‫01/٨‬

‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬
‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬                          ‫‪Primavera‬‬
                                                                                      ‫ﺜﻡ ﻨﻀﻐﻁ ‪OK‬‬




                                                   ‫ﺜﻡ ﻨﺠﺭﻱ ﺘﻌﺩﻴﻼﺘﻨﺎ ﻭﻨﻀﻐﻁ ﺯﺭ ‪ Prorate‬ﺜﻡ ‪. OK‬‬
                               ‫ﻭﻅﻴﻔﺔ ﺍﻟﻤﻔﺘﺎﺡ ‪ Restore‬ﻫﻭ ﺇﺭﺠﺎﻉ ﺍﻟﻘﻴﻤﺔ ﺍﻻﻓﺘﺭﺍﻀﻴﺔ ﻟﻠﻤﻨﺤﻨﻴﺎﺕ ﺍﻟﺠﺎﻫﺯﺓ .‬
                  ‫ﻨﻨﺘﻘل ﺍﻵﻥ ﺇﻟﻰ ﺃﻤﺭ ﺁﺨﺭ ﻤﻥ ﺃﻭﺍﻤﺭ ﺍﻟﻘﺎﺌﻤﺔ ‪ Data‬ﻭﻫﻭ ‪ Cost account‬ﺍﻟﺸﺠﺭﺓ ﺍﻟﻤﺤﺎﺴﺒﻴﺔ:‬
             ‫‪Data‬‬          ‫‪Cost Account‬‬



                                                                                    ‫ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ‬
                                                                                   ‫ﻨﻜﺘﺏ ﺍﻟﻔﺌﺔ ﻭﺸﺭﺤﻬﺎ‬


                                                                                     ‫ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﺴﻔﻠﻰ‬
                                                                                 ‫ﻨﻜﺘﺏ ﺍﻟﺸﺠﺭﺓ ﺍﻟﻤﺤﺎﺴﺒﻴﺔ‬




                                                                               ‫ﻜﻴﻑ ﺘﺒﻨﻰ ﺍﻟﺸﺠﺭﺓ ﺍﻟﻤﺤﺎﺴﺒﻴﺔ؟‬
                                  ‫١- ﺃﺭﻗﺎﻡ ﻤﻜﻭﻨﺔ ﻤﻥ ﺨﺎﻨﺘﻴﻥ ﻤﺜﻼ ٢١ ﺃﻭ ٣١ ﺃﻭ ٤١ ﺃﻭ ..... ﺤﺘﻰ ٩٩‬
         ‫٢- ﻜل ﺜﻨﺎﺌﻲ ﻴﺘﻔﺭﻉ ﻤﻨﻪ ﺜﻼﺜﻲ ﻭﻜل ﺜﻼﺜﻲ ﻴﺘﻔﺭﻉ ﻤﻨﻪ ﺭﺒﺎﻋﻲ ﻭﻜل ﺭﺒﺎﻋﻲ ﻴﺘﻔﺭﻉ ﻤﻨﻪ ﺨﻤﺎﺴﻲ ﻭﻜل ﺨﻤﺎﺴﻲ‬
                                    ‫ﻴﺘﻔﺭﻉ ﻤﻨﻪ ﺴﺩﺍﺴﻲ ﻭﻜل ﺴﺩﺍﺴﻲ ﻴﺘﻔﺭﻉ ﻤﻨﻪ ﻋﺸﺭﻱ ﻷﻨﻪ ﺭﻗﻡ ﺍﻟﻔﻭﺍﺘﻴﺭ .‬

                                                                                               ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬
                                                    ‫01/٩‬

‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬
‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬                            ‫‪Primavera‬‬
                                                              ‫ﻤﺜﻼ ﺘﺴﺘﻁﻴﻊ ﺇﺩﺨﺎل ٠٠٠٠١ ﻓﺎﺘﻭﺭﺓ ﺘﺤﺕ ﻜل ﺭﻗﻡ .‬
               ‫ﻤﺜﻼ ﻟﻨﻔﺭﺽ ﺃﻥ ﺍﻟﺤﺴﺎﺏ ﺭﻗﻡ ٢١ "ﺍﻟﻤﻜﻭﻥ ﻤﻥ ﺨﺎﻨﺘﻴﻥ " ﻴﻌﺒﺭ ﻋﻥ ﻤﻭﺠﻭﺩﺍﺕ ﺜﺎﺒﺘﺔ ﻟﻤﺅﺴﺴﺔ ﻤﺜل ) ﺍﻟﺒﻨﺎﺀ ،‬
                ‫ﺍﻵﻟﻴﺎﺕ ، ﺍﻟﻔﺭﺵ ، ﺍﻷﺭﺍﻀﻲ ﺍﻟﺘﻲ ﺘﻤﻠﻜﻬﺎ ﺍﻟﻤﺅﺴﺴﺔ ..( ﻫﺫﻩ ﺍﻟﻤﻭﺠﻭﺩﺍﺕ ﺍﻟﺜﺎﺒﺘﺔ ﻴﻤﻜﻥ ﺃﻥ ﺘﻜﻭﻥ ﻓﻲ ]ﺍﻟﻘﻭﺍﻋﺩ‬
                                                                                 ‫)ﺒﺎﻟﻤﺩﻴﻨﺔ( ﺃﻭ ﻓﻲ ﺍﻟﻔﺭﻭﻉ )ﺒﺎﻟﻀﻭﺍﺤﻲ([‬
            ‫ﻴﺘﻔﺭﻉ ﻋﻥ ﺍﻟﺨﺎﻨﺘﻴﻥ‬           ‫ﻜﻴﻑ ﺴﻨ ‪‬ﺭﻑ ﺃﻥ ﻜل ﻤﻥ ﻫﺫﻩ ﺍﻟﻤﻭﺠﻭﺩﺍﺕ ﻴﺘﺒﻊ ﻟﻠﺤﺴﺎﺏ ﺭﻗﻡ ٢١ ﺍﻟﺘﺎﺒﻊ ﻟﻠﻤﺅﺴﺴﺔ‬
                                                                                                   ‫ﻌ‬
                                    ‫ﺜﻼﺙ ﺨﺎﻨﺎﺕ ﻤﺜﻼ ١٢١ ﺃﻭ ٢٢١ ......ﺜﻡ ﻴﺘﻔﺭﻉ ﻋﻥ ﺍﻟﺨﺎﻨﺘﻴﻥ ﺜﻼﺙ ﺨﺎﻨﺎﺕ ﻭﻫﻜﺫﺍ‬


                                                   ‫)ﺒﺎﻟﻤﺩﻴﻨﺔ( ١٢١‬   ‫ﻓﻲ ﺍﻟﻘﻭﺍﻋﺩ‬      ‫ﺤﺴﺎﺏ ﺍﻟﻤﺅﺴﺴﺔ ٢١ ﻤﻭﺠﻭﺩﺍﺕ ﺜﺎﺒﺘﺔ‬

‫١١١٢٢١‬   ‫ﺘﺨﺯﻴﻥ ١١٢٢١‬                                                                ‫ﻴﻤﻜﻥ ﺃﻥ ﺘﻜﻭﻥ‬
                             ‫ﺃﺭﺍﻀﻲ ١٢٢١‬          ‫ﻓﻲ ﺍﻟﻔﺭﻭﻉ )ﺒﺎﻟﻀﻭﺍﺤﻲ( ٢٢١‬
           ‫ﺒﻨﺎﺀ ٢١٢٢١‬
                              ‫ﺍﻵﻟﻴﺎﺕ ٢٢٢١‬

         ‫ﺒﺭﻨﺎﻤﺞ ﺍﻟﻤﺤﺎﺴﺒﺔ ﻴﺠﻤﻊ ﻜل ﺍﻟﻔﻭﺍﺘﻴﺭ ﺍﻟﺘﻲ ﺃﺭﻗﺎﻤﻬﺎ ﺍﻟﺴﺘﺔ ﺍﻷﻭﻟﻰ ﺘﺴﺎﻭﻱ ﺍﻟﺭﻗﻡ ١١١٢١ ﻤﺜﻼ ﻭﺒﻌﺩ ﺃﻥ ﻴﺠﻤﻌﻬﺎ ﻴﺭﺤﻠﻬﺎ‬
                                                                                            ‫ﻟﻬﺫﺍ ﺍﻟﺤﺴﺎﺏ ﻭﻫﻜﺫﺍ .....‬
                    ‫ﻨﻔﺱ ﺍﻟﻨﻅﺎﻡ ‪ Primavera‬ﻭﻟﻜﻥ ‪ Primavera‬ﻫﻭ ٣١ ﻭﻟﻴﺱ ﻋﺸﺭﻱ ﺤﻴﺙ ﻟﺩﻴﻪ ٢١ ﻋﺩﺩ ﻭﻭﺍﺤﺩ ﺤﺭﻓﻲ .‬
             ‫ﺍﻟﺨﺎﻨﺔ ﺍﻟﺤﺭﻓﻴﺔ ﻫﻨﺎ ﻫﻲ ﺍﻟﻔﺌﺔ ﺤﻴﺙ ﻟﺩﻴﻨﺎ ﻫﻨﺎ ﻤﺤﺎﺴﺒﺔ ﻤﺸﺎﺭﻴﻊ ﻤﺜﻼ ﻟﺩﻴﻨﺎ ﺃﻋﻤﺩﺓ ، ﻓﻘﻴﻤﺔ ﺃﻋﻤﺎل ﺍﻷﻋﻤﺩﺓ ﺘﺄﺘﻲ ﻤﻥ‬
             ‫ﺘﻜﺎﻟﻴﻑ ﻤﻘﺎﻭل + ﺘﻜﺎﻟﻴﻑ ﻴﺩ ﻋﺎﻤﻠﻪ + ﺘﻜﺎﻟﻴﻑ ﻤﻭﺍﺩ + ........، ﺇﺫﻥ ﻫﻨﺎ ﻻ ﻨﺴﺘﻁﻴﻊ ﻭﻀﻊ ﺭﻗﻡ ﻟﻴﺩ ﻋﺎﻤﻠﺔ ﻭﺭﻗﻡ‬
            ‫ﻟﻠﻤﻭﺍﺩ ﺒل ﺘﻭﺠﺩ ﻁﺭﻴﻘﺔ ﺃﺨﺭﻯ ﻟﻠﺘﻤﻴﻴﺯ ﻭﻫﻲ ﻜﺘﺎﺒﺔ ﺍﻟﻔﺌﺔ ، ﻓﺒﺤﺎل ﻜﻭﻥ ﺍﻟﻔﺌﺔ ‪ L‬ﻤﺜﻼ ﻓﻬﻲ ﺘﻌﺒﺭ ﻋﻥ ﺍﻟﻴﺩ ﺍﻟﻌﺎﻤﻠﺔ ..‬
                ‫‪L‬‬                     ‫ﻴﺩ ﻋﺎﻤﻠﺔ‬
                ‫‪E‬‬                       ‫ﺁﻟﻴﺎﺕ‬
                ‫‪M‬‬                     ‫ﻤﻭﺍﺩ‬
                ‫‪S‬‬                  ‫ﻤﻘﺎﻭل ﺒﺎﻁﻥ‬
                ‫‪O‬‬                     ‫ﺃﺨﺭﻯ‬
                                  ‫ﺇﺫﻥ ﺒﺩﻭﻥ ﺨﺎﻨﺔ ﺤﺭﻓﻴﺔ ﻴﻌﻁﻲ ﺭﻗﻡ ﺇﺠﻤﺎﻟﻲ ﻭﻤﻊ ﺍﻟﺨﺎﻨﺔ ﺍﻟﺤﺭﻓﻴﺔ ﻴﻌﻁﻲ ﻟﻜل ﻓﺌﺔ ﻟﻭﺤﺩﻫﺎ.‬
                                    ‫ﺒﻨﻅﺎﻡ ﺍﻟﻤﺤﺎﺴﺒﺔ " ﻨﺎﻓﺫﺓ ‪ " Cost Accounts‬ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﻤﺴﺘﻘﻠﺔ ﻋﻥ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﺴﻔﻠﻰ .‬
                                    ‫ﻨﻜﺘﺏ ﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﺍﻟﻔﺌﺔ ﻭﺸﺭﺤﻬﺎ ﺒﻴﻨﻤﺎ ﻨﻜﺘﺏ ﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﺴﻔﻠﻰ ﺍﻟﺸﺠﺭﺓ ﺍﻟﻤﺤﺎﺴﺒﻴﺔ‬




                                                                                                        ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬
                                                          ‫01/٠١‬

 ‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬

More Related Content

More from Anas Ramadan

Ch11 متانة الخرسانة (المعمرية او الديمومة
Ch11 متانة الخرسانة (المعمرية او الديمومةCh11 متانة الخرسانة (المعمرية او الديمومة
Ch11 متانة الخرسانة (المعمرية او الديمومةAnas Ramadan
 
Ch10 الانكماش والزحف
Ch10 الانكماش والزحفCh10 الانكماش والزحف
Ch10 الانكماش والزحفAnas Ramadan
 
Ch9 الاختبارات غير المتلفة للخرسانة
Ch9 الاختبارات غير المتلفة للخرسانةCh9 الاختبارات غير المتلفة للخرسانة
Ch9 الاختبارات غير المتلفة للخرسانةAnas Ramadan
 
Ch8 خواص واختبارات الخرسانة المتصلدة
Ch8 خواص واختبارات الخرسانة المتصلدةCh8 خواص واختبارات الخرسانة المتصلدة
Ch8 خواص واختبارات الخرسانة المتصلدةAnas Ramadan
 
Ch7 خواص واختبارات الخرسانة الطازجة
Ch7 خواص واختبارات الخرسانة الطازجةCh7 خواص واختبارات الخرسانة الطازجة
Ch7 خواص واختبارات الخرسانة الطازجةAnas Ramadan
 
Ch6 ضبط جودة الخرسانة إحصائياً
Ch6 ضبط جودة الخرسانة إحصائياًCh6 ضبط جودة الخرسانة إحصائياً
Ch6 ضبط جودة الخرسانة إحصائياًAnas Ramadan
 
Ch5 تصميم الخلطات الخرسانية
Ch5 تصميم الخلطات الخرسانيةCh5 تصميم الخلطات الخرسانية
Ch5 تصميم الخلطات الخرسانيةAnas Ramadan
 
Ch4 صناعة الخرسانة
Ch4 صناعة الخرسانةCh4 صناعة الخرسانة
Ch4 صناعة الخرسانةAnas Ramadan
 
Ch3 الأنواع المختلفة (الخاصة) من الخرسانة
Ch3 الأنواع المختلفة (الخاصة) من الخرسانةCh3 الأنواع المختلفة (الخاصة) من الخرسانة
Ch3 الأنواع المختلفة (الخاصة) من الخرسانةAnas Ramadan
 
Ch2 الإضافات
Ch2 الإضافاتCh2 الإضافات
Ch2 الإضافاتAnas Ramadan
 
Ch1 الخرسانة
Ch1 الخرسانةCh1 الخرسانة
Ch1 الخرسانةAnas Ramadan
 
Precast concrete الخرسانة سابقة الصب
Precast concrete الخرسانة سابقة الصبPrecast concrete الخرسانة سابقة الصب
Precast concrete الخرسانة سابقة الصبAnas Ramadan
 

More from Anas Ramadan (20)

Ch13 contents
Ch13 contentsCh13 contents
Ch13 contents
 
Ch12 refer
Ch12 referCh12 refer
Ch12 refer
 
Ch11 متانة الخرسانة (المعمرية او الديمومة
Ch11 متانة الخرسانة (المعمرية او الديمومةCh11 متانة الخرسانة (المعمرية او الديمومة
Ch11 متانة الخرسانة (المعمرية او الديمومة
 
Ch10 الانكماش والزحف
Ch10 الانكماش والزحفCh10 الانكماش والزحف
Ch10 الانكماش والزحف
 
Ch9 الاختبارات غير المتلفة للخرسانة
Ch9 الاختبارات غير المتلفة للخرسانةCh9 الاختبارات غير المتلفة للخرسانة
Ch9 الاختبارات غير المتلفة للخرسانة
 
Ch8 خواص واختبارات الخرسانة المتصلدة
Ch8 خواص واختبارات الخرسانة المتصلدةCh8 خواص واختبارات الخرسانة المتصلدة
Ch8 خواص واختبارات الخرسانة المتصلدة
 
Ch7 خواص واختبارات الخرسانة الطازجة
Ch7 خواص واختبارات الخرسانة الطازجةCh7 خواص واختبارات الخرسانة الطازجة
Ch7 خواص واختبارات الخرسانة الطازجة
 
Ch6 ضبط جودة الخرسانة إحصائياً
Ch6 ضبط جودة الخرسانة إحصائياًCh6 ضبط جودة الخرسانة إحصائياً
Ch6 ضبط جودة الخرسانة إحصائياً
 
Ch5 تصميم الخلطات الخرسانية
Ch5 تصميم الخلطات الخرسانيةCh5 تصميم الخلطات الخرسانية
Ch5 تصميم الخلطات الخرسانية
 
Ch4 صناعة الخرسانة
Ch4 صناعة الخرسانةCh4 صناعة الخرسانة
Ch4 صناعة الخرسانة
 
Ch3 الأنواع المختلفة (الخاصة) من الخرسانة
Ch3 الأنواع المختلفة (الخاصة) من الخرسانةCh3 الأنواع المختلفة (الخاصة) من الخرسانة
Ch3 الأنواع المختلفة (الخاصة) من الخرسانة
 
Ch2 الإضافات
Ch2 الإضافاتCh2 الإضافات
Ch2 الإضافات
 
Ch1 الخرسانة
Ch1 الخرسانةCh1 الخرسانة
Ch1 الخرسانة
 
01 intro
01 intro01 intro
01 intro
 
Precast concrete الخرسانة سابقة الصب
Precast concrete الخرسانة سابقة الصبPrecast concrete الخرسانة سابقة الصب
Precast concrete الخرسانة سابقة الصب
 
Footing a
Footing aFooting a
Footing a
 
Bearing capacity
Bearing capacityBearing capacity
Bearing capacity
 
Bearing 2
Bearing 2Bearing 2
Bearing 2
 
5 compaction
5 compaction5 compaction
5 compaction
 
2 soil phases
2 soil phases2 soil phases
2 soil phases
 

Primavera 4

  • 1. ‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬ ‫‪Primavera‬‬ ‫ﺍﻟﻤﻭﺭﺩ: ﻫﻭ ﻜل ﻤﺎﺩﺓ ﺃﻭ ﺁﻟﻴﺔ ﺃﻭ ﻴﺩ ﻋﺎﻤﻠﺔ ﻴﺘﻡ ﺍﺴﺘﺨﺩﺍﻤﻬﺎ ﻓﻲ ﻋﻤﻠﻴﺔ ﻤﺎ‬ ‫ﻨﺨﺘﺎﺭ ‪ Resource‬ﻓﺘﻔﺘﺢ ﻨﺎﻓﺫﺓ‬ ‫ﺇﺫﻥ ﻹﺩﺨﺎل ﺍﻟﻤﻭﺍﺭﺩ ﻤﻥ ﻗﺎﺌﻤﺔ ‪Data‬‬ ‫ﻴﺘﻡ ﺇﺩﺨﺎل ﺍﻟﻤﻭﺍﺭﺩ ﻓﻲ ﺤﻘل ‪ Resource‬ﻭﻫﻨﺎ ﻴﺠﺏ ﺍﻟﺘﻤﻴﻴﺯ ﺒﻴﻥ ﺁﻟﻴﺔ ﻭﻴﺩ ﻋﺎﻤﻠﺔ ﻓﻜﻴﻑ ﻴﻤﻜﻥ ﺍﻟﺘﻤﻴﻴﺯ؟‬ ‫ﻤﺎﻟﻔﺭﻕ ﺒﻴﻥ ﻤﻭﺍﺭﺩ ﺍﻵﻟﺔ ﻭﻤﻭﺍﺭﺩ ﺍﻟﻴﺩ ﺍﻟﻌﺎﻤﻠﺔ؟‬ ‫ﺍﻟﻤﺎﺩﺓ ﻓﻲ ﺠﺩﻭل ﺍﻟﻜﻤﻴﺎﺕ ﻫﻲ ﺜﺎﺒﺘﺔ ﻭﻜﻤﻴﺘﻬﺎ ﻻ ﺘﺯﻴﺩ ﻭﻻ ﺘﻨﻘﺹ ﻤﻊ ﺘﻐﻴﺭ ﻤﺩﺓ ﺘﻨﻔﻴﺫ ﺍﻟﻌﻤﻠﻴﺔ.‬ ‫ﺒﻴﻨﻤﺎ ﺍﻟﻴﺩ ﺍﻟﻌﺎﻤﻠﺔ ﻴﻤﻜﻥ ﺃﻥ ﺘﺘﻐﻴﺭ ﻜﻤﻴﺘﻬﺎ ﺒﺎﻟﺯﻴﺎﺩﺓ ﻭﺍﻟﻨﻘﺼﺎﻥ ﻤﻊ ﺘﻐﻴﺭ ﻤﺩﺓ ﺘﻨﻔﻴﺫ ﺍﻟﻌﻤﻠﻴﺔ ﻭﻜﺫﻟﻙ ﺍﻵﻟﺔ ﻤﻤﻜﻥ ﺃﻥ ﺘﺘﻐﻴﺭ‬ ‫ﻜﻤﻴﺘﻬﺎ ﺒﺎﻟﺯﻴﺎﺩﺓ ﻭﺍﻟﻨﻘﺼﺎﻥ.‬ ‫ﺇﺫﻥ ﻟﻠﺘﻤﻴﻴﺯ ﺒﻴﻥ ﻤﻭﺭﺩ ﺁﻟﺔ ﺃﻭ ﻤﺎﺩﺓ ﺃﻭ ﻴﺩ ﻋﺎﻤﻠﺔ ﻨﺭﺍﻋﻲ ﺒﺎﻟﺘﺴﻤﻴﺔ ﺃﻥ ﻴﺩل ﺍﻟﺤﺭﻑ ﺍﻷﻭل ﻋﻠﻰ ﺍﻟﻤﺎﺩﺓ ﻤﺜﻼ :‬ ‫‪ L‬ﻴﺩل ﻋﻠﻰ ﻴﺩ ﻋﺎﻤﻠﺔ‬ ‫‪ M‬ﻴﺩل ﻋﻠﻰ ﺁﻟﺔ‬ ‫‪ Q‬ﻴﺩل ﻋﻠﻰ ﻤﺎﺩﺓ‬ ‫ﻟﻨﻔﺭﺽ ﺍﻟﻤﻬﻨﺩﺴﻴﻥ ﺍﻟﻤﻭﺠﻭﺩﻴﻥ ﻤﻘﺴﻤﻴﻥ ﻟﻤﺠﻤﻭﻋﺎﺕ ﻓﻲ ﺍﻟﻤﺸﺭﻭﻉ " ﻤﺠﻤﻭﻋﺔ ١ + ﻤﺠﻤﻭﻋﺔ ٢ + ﻤﺠﻤﻭﻋﺔ ٣ " .‬ ‫ﺒﺤﺎل ﺤﺼﻭل ﻨﻘﺹ ﻓﻲ ﺃﻱ ﻤﺠﻤﻭﻋﺔ ﻴﻤﻜﻥ ﺃﻥ ﻴﺴﺘﻜﻤل ﺍﻟﻨﻘﺹ ﻤﻥ ﺒﺎﻗﻲ ﺍﻟﻤﺠﻤﻭﻋﺎﺕ‬ ‫ﻜﻴﻑ ﺴﻨﺩﺨل ﺃﺴﻤﺎﺀ ﺍﻟﻤﻬﻨﺩﺴﻴﻥ ﺒﺤﻴﺙ ﻴﺘﻌﺎﻤل ﺍﻟﺤﺎﺴﺏ ﻤﻌﻬﻡ ﻋﻠﻰ ﺃﻨﻬﻡ ﻤﻭﺯﻋﻴﻥ ﻟﻤﺠﻤﻭﻋﺎﺕ ٣،٢،١‬ ‫ﺒﻌﻤﻭﺩ ﺍﻟﻤﻭﺭﺩ ﻨﻜﺘﺏ * ‪ Civil‬ﺜﻡ ﻨﻜﺘﺏ .…,1‪Civil‬‬ ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬ ‫01/١‬ ‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬
  • 2. ‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬ Primavera Civil * Civil 1 Civil 2 ‫ﺍﻟﻨﺠﻤﺔ ﺘﺸﻜل‬ Civil 3 ‫ ﻓﺈﺫﺍ ﻅﻬﺭ ﻨﻘﺹ ﺒﻬﺎ‬Civil1 ‫ ﻓﺈﻥ ﺍﻟﺤﺎﺴﺏ ﻓﻲ ﻫﺫﻩ ﺍﻟﺤﺎﻟﺔ ﻴﺫﻫﺏ ﺇﻟﻰ‬Civil * ‫ﻭﻫﻨﺎ ﺇﺫﺍ ﻋﻤﻠﻨﺎ ﺘﺴﻭﻴﺔ ﻋﻠﻰ ﺍﻟﻤﻭﺭﺩ‬ .‫ ﻭﻫﻜﺫﺍ‬Civil1 ‫ ﻭﻴﻌﻁﻲ‬Civil2 ‫ﻴﺄﺨﺫ ﻤﻥ‬ Civil 1 ‫ﻭﻫﻨﺎ ﻴﻜﻭﻥ ﺭﺒﻁ ﺍﻟﻌﻤﻠﻴﺎﺕ ﻋﻠﻰ‬ Civil 2 Civil3 .‫ ﺤﻴﺙ ﺍﻟﻨﺠﻤﺔ * ﺘﺘﻡ ﻋﻠﻰ ﻭﺠﻭﺩ ﻤﺠﻤﻭﻋﺔ‬Civil* ‫ﻭﻟﻜﻥ ﺍﻟﺘﺴﻭﻴﺔ ﺘﺘﻡ ﻋﻠﻰ‬ ‫ﺍﻟﻴﺩ ﺍﻟﻌﺎﻤﻠﺔ ﻭﺍﺤﺩﺘﻬﺎ ﻤﺠﻤﻭﻋﺔ ﻭﻜل ﻤﺠﻤﻭﻋﺔ ﺤﺴﺏ ﻁﺒﻴﻌﺔ ﺍﻟﻤﻭﺭﺩ ﻤﺜﻼ‬ ‫ ﻨﺩﺨل ﺒﻴﺎﻨﺎﺕ ﺍﻟﻤﻭﺍﺭﺩ ﺤﻴﺙ ﻓﻲ ﺍﻟﻌﻤﻭﺩ ﺍﻷﻭل ﻨﺩﺨل ﺍﺴﻡ ﺍﻟﻤﻭﺭﺩ ﻭﻓﻲ‬Resource ‫ﺇﺫﻥ ﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﻤﻥ ﻨﺎﻓﺫﺓ‬ .‫ﺍﻟﻌﻤﻭﺩ ﺍﻟﺜﺎﻨﻲ ﻨﺩﺨل ﺍﻟﻭﺤﺩﺓ ﻤﺜﻼ ﻭﺤﺩﺓ ﺍﻟﻴﺩ ﺍﻟﻌﺎﻤﻠﺔ ﻫﻲ ﻤﺠﻤﻭﻋﺔ‬ Resource Description unit price per unit LABOUR L_CARPEN ‫ﻨﺠﺎﺭ ﺒﻴﺘﻭﻥ‬ 2 carpenter no. 20.00/day L_ELECTR ‫ﻜﻬﺭﺒﺎﺌﻲ‬ 2worker no. 11.00/day L_MASON ‫ﺒﻨﺎﺀ‬ 2worker no. 11.00/day L_OR_CAR "‫2 ﻨﺠﺎﺭ ﺸﺭﻗﻲ "ﻟﻸﺒﻭﺍﺏ ﺍﻟﺩﺍﺨﻠﻴﺔ‬worker(oriental carpenter) no. 11.00/day L_OVERH ‫ ﺍﻟﻬﻴﻜل ﺍﻹﺩﺍﺭﻱ ﻟﻠﻤﺸﺭﻭﻉ‬over head man power no. 285232.00 L_O_work ‫ﻋﺎﻤل ﻋﺎﺩﻱ‬ ordinary worker no. 5.00/day L_PAINT ‫ﺩﻫﺎﻥ ﻋﺎﺩﻱ‬ Painter 1 Worker no. 5.00/day L_PLAST ‫ﻤﻠﻴﺱ‬ 2 worker no. 11.00/day L_POLISH ‫ﺠﻠﻰ‬ Polisher 1 worker 5.00/day L_SANITA ‫ﻤﻌﻠﻡ ﺼﺤﻴﺔ‬ Sanitary 2 worker no. 11.00/day L_STUDY ‫ ﺍﻟﻬﻴﻜل ﺍﻟﺩﺍﺭﺱ ﻟﻠﻤﺸﺭﻭﻉ‬Study the project 114100.00/day L_ST_FIX ‫ﺤﺩﺍﺩ‬ Steel fixer 2 worker no. 20.00/day L_SURVEY ‫ﺎﺡ‬ ‫ﻤ‬ ‫ﺴ‬ Survey -3 labor no. 16.00/day L_TILES ‫ﺒﻼﻁ‬ 2worker no. 11.00/day MACHINE M_BAGER ‫ﺒﺎﻏﺭ‬ Bagger no. 240.00/day M_BOBCAT BobCat no. 120.00/day ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬ ٢/10 PDF created with pdfFactory trial version www.pdffactory.com
  • 3. ‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬ Primavera M_BUS ‫ﺒﺎﺹ‬ Bus no. 80.00/day M_CAR ‫ﺴﻴﺎﺭﺓ‬ Car for eng. no. 40.00/day M_CA_CRA ‫ﺴﻴﺎﺭﺓ ﻤﻊ ﺭﺍﻓﻌﺔ‬ Car with crane no. 160.00/day M_COMPAC ‫ﻤﺩﺤﻠﺔ‬ Compactor no. 40.00/day M_VIBRAT ‫ﺭﺠﺎﺝ ﺨﺭﺴﺎﻨﺔ‬ Vibrator no. 20.00/day M_SERVIS ‫ﺴﻴﺎﺭﺍﺕ ﺨﺩﻤﺔ‬ Service no. 50.00/day M_TRACTO ‫ﺘﺭﺍﻜﺘﻭﺭ‬ Tractors no. 50.00/day M_WH_LO ‫ﻟﺘﺴﻭﻴﺔ ﺍﻟﺸﻭﺍﺭﻉ‬ Wheel loaders no. 240.00/day M_TRUCK ‫ﺸﺎﺤﻨﺔ‬ Truck 12 m3 no. 105.00/day M_WATER ‫ﺸﺎﺤﻨﺔ ﻤﻊ ﺼﻬﺭﻴﺞ‬ Truck for water 20 m3 no. 120.00/day M_WL_CRA ‫ﺭﺍﻓﻌﺔ ﺠﺩﺍﺭﻴﺔ‬ Wall crane no. 16.00/day MATERIAL Q_ASPHAL ‫ﺃﺴﻔﻠﺕ‬ Asphalt work Ls 66480.00 Q_AS_ELA ‫ ﻤﻭﺍﺩ ﺍﻹﻨﻬﺎﺀﺍﺕ ﺍﻟﻜﻬﺭﺒﺎﺌﻴﺔ‬Fixture electricity material Ls 2200.00 Q_AS_SSA ‫ﻤﻭﺍﺩ ﺇﻨﻬﺎﺀﺍﺕ ﺼﺤﻴﺔ‬ Fixture sanitary material Ls 3200.00 Q_BARDOR ‫ﺤﺠﺭ ﺭﺼﻴﻑ‬ Curb stone material Lm 3.00 Q_BLC_FG ‫ﺒﻠﻭﻙ ﻟﻠﺴﻭﺭ‬ Block for fence M3 20.00 Q_BLOCK ‫ﺒﻠﻭﻙ‬ Block M3 20.00 Q_BL_ELA ‫ ﺴﻭﺍﺩﺍﺕ ﻜﻬﺭﺒﺎﺀ‬Primary installation electrical material Ls 200.00 Q_BL_SAA ‫ ﺴﻭﺍﺩﺍﺕ ﺼﺤﻴﺔ‬Primary installation sanitary material Ls 1000.00 Q_CERAMI ‫ﺴﻴﺭﺍﻤﻴﻙ‬ Ceramic material M2 4.50 Q_COL_LI ‫ﺃﻋﻤﺩﺓ ﺇﻨﺎﺭﺓ‬ Columns for external lighting no 200.00 Q_CONC20 ٢٠٠ ‫ﺨﺭﺴﺎﻨﺔ ﻋﻴﺎﺭ‬ Concrete 200kg/m3 M3 17.00 Q_CONC30 ٣٠٠ ‫ﺨﺭﺴﺎﻨﺔ ﻋﻴﺎﺭ‬ Concrete 300 kg/m3 M3 20.00 Q_CONC35 ٣٥٠ ‫ﺨﺭﺴﺎﻨﺔ ﻋﻴﺎﺭ‬ Concrete 350 kg/m3 M3 23.00 Q_CRU_S ‫ﺒﻘﺎﻴﺎ ﻤﻘﺎﻟﻊ‬ Crushed stone material M3 3.50 Q_ELE_DI ‫ﻤﻭﺍﺩ ﻏﺭﻓﺔ ﺍﻟﻜﻬﺭﺒﺎﺀ‬ Tran station dis. Ls 13500.00 Q_EX_E_M ‫ ﻤﻭﺍﺩ ﺍﻟﺘﻤﺩﻴﺩﺍﺕ ﺍﻟﻜﻬﺭﺒﺎﺌﻴﺔ ﺍﻟﺨﺎﺭﺠﻴﺔ‬External electrical material Ls 132000.00 Q_E_S_PM ‫ ﺍﻷﻨﺎﺒﻴﺏ ﺍﻟﺼﺤﻴﺔ ﺍﻟﺨﺎﺭﺠﻴﺔ‬External sanitary pipe material Lm Q_FORMWO ٣ ‫ﻗﺎﻟﺏ ﺨﺸﺒﻲ ﻡ‬ Formwork material per m3 M3 3.00 Q_FORM_W ٢‫ﻗﺎﻟﺏ ﺨﺸﺒﻲ ﻡ‬ Formwork material per m2 M2 1.00 ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬ ٣/10 PDF created with pdfFactory trial version www.pdffactory.com
  • 4. ‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬ Primavera Q_F_F_M ‫ﻤﻭﺍﺩ ﻤﻜﺎﻓﺤﺔ ﺍﻟﺤﺭﻴﻕ‬ Fire fighting material Ls 31000.00 Q_GARDEN ‫ﻤﻭﺍﺩ ﺍﻟﺤﺩﺍﺌﻕ‬ Garden material Ls Q_INSULA ‫ﻤﻭﺍﺩ ﺍﻟﻌﺯل‬ Insulation material & Labour Ls 1600.00 Q_INS_UW‫ ﻤﻭﺍﺩ ﻏﺯل ﺨﺯﺍﻥ ﻤﻁﻤﻭﺭ‬Insulation for under ground water tank M2 3.00 Q_MORTAR ‫ﻤﻭﻨﺔ‬ Mortar M3 17.00 Q_PAINTM ‫ﺩﻫﺎﻥ‬ Paint material Ton Q_PAVIOR ‫ﺒﻼﻁ ﺃﺭﻀﻴﺔ‬ Cement screed PC_Paviors M2 3.70 Q_PI_RNE‫ﻤﻭﺍﺴﻴﺭ ﻟﺸﺒﻜﺔ ﺼﺭﻑ ﻤﻴﺎﻩ ﺍﻷﻤﻁﺎﺭ‬Pipe for rain water net work Lm 4.50 Q_PI_SNE‫ ﻤﻭﺍﺴﻴﺭ ﺼﺭﻑ ﻤﻴﺎﻩ ﻤﺎﻟﺤﺔ‬Pipe for sanitary water net work Lm 4.00 Q_PUMP ‫ﺘﺠﻬﻴﺯﺍﺕ ﻤﺤﻁﺔ ﺍﻟﻀﺦ‬ Pumping station material Ls 11635.00 Q_REINFO ‫ﺤﺩﻴﺩ ﺍﻟﺘﺴﻠﻴﺢ‬ Steel for concrete Ton 260.00 Q_RENDR ‫ ﻤﻭﺍﺩ ﺭﺸﺔ ﺘﻴﺭﻭﻟﻴﺔ‬External rendering with white cement M3 75.00 Q_SCIRTI ‫ﺍﻟﻨﻌﻠﺔ‬ Skirting material Lm 1.50 Q_SERVIC ‫ﻨﺜﺭﻴﺎﺕ ﺍﻟﻤﻭﻗﻊ‬ Paper & computer & …. Ls 171140.00 Q_SEW_PI ‫ ﻤﻭﺍﺴﻴﺭ ﺼﺭﻑ ﺼﺤﻲ‬Swage pipe Lm 22.50 Q_SOIL ‫ ﻤﻭﺍﺩ ﺭﺩﻤﻴﺔ ﻤﻥ ﺨﺎﺭﺝ ﺍﻟﻤﻭﻗﻊ‬Back filling from barrow M3 1.60 Q_STAIRS ‫ﺒﻼﻁ ﺃﺩﺭﺍﺝ‬ Stair tiles material Lm 4.50 Q_STEEL ‫ﻤﻭﺍﺩ ﺃﻋﻤﺎل ﻤﻌﺩﻨﻴﺔ‬ Metal works Ton 700.00 Q_ST_GAT ‫ﻤﻭﺍﺩ ﺍﻟﺒﻭﺍﺒﺔ‬ Gate for fence no. 1000.00 Q_TEL_M ‫ ﻤﻭﺍﺩ ﺸﺒﻜﺔ ﺍﻟﺘﻠﻔﻭﻥ ﺍﻟﺨﺎﺭﺠﻴﺔ‬External telephone material Ls 16850.00 Q_TERAZO ‫ﺒﻼﻁ ﻋﺎﺩﻱ‬ Terrazzo material*10 M2 3.00 Q_U_B_PI ‫ ﻤﻭﺍﺴﻴﺭ ﺍﻟﺨﺯﺍﻥ ﺍﻟﻤﻁﻤﻭﺭ‬Un gr . pipe for building Ls 542.50 Q_WI_ELA ‫ﻤﻭﺍﺴﻴﺭ ﺍﻷﺴﻼﻙ ﺍﻟﻜﻬﺭﺒﺎﺌﻴﺔ‬Wire electricity material Ls 600.00 Q_W_DOOR ‫ﺃﺒﻭﺍﺏ ﺨﺸﺒﻴﺔ‬ Wooden doors Ls 3375.00 ‫ ﻴﺴﺘﺨﺩﻡ ﻟﺘﺤﻴﺩ ﻤﺎ ﺇﺫﺍ ﻜﺎﻥ‬Resource ‫ ﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﺒﻨﺎﻓﺫﺓ‬Driving ‫ ﻓﻲ ﺍﻟﻌﻤﻭﺩ ﺍﻟﺜﺎﻟﺙ‬Driving ‫ﺍﻟﺨﺎﺼﺔ‬ ‫ﺍﻟﻤﻭﺭﺩ ﻤﺘﺤﻜﻡ ﺃﻡ ﻻ‬ ‫ﻤﺎﻟﻤﻘﺼﻭﺩ ﺒﻤﺘﺤﻜﻡ ؟ ﺇﺫﺍ ﻜﺎﻥ ﺍﻟﻤﻭﺭﺩ ﻏﻴﺭ ﻤﺘﺤﻜﻡ ﻓﻤﻬﻤﺎ ﺯﺍﺩﺕ ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﺃﻭ ﻨﻘﺼﺕ ﺘﺒﻘﻰ ﺍﻟﻤﺩﺓ ﺜﺎﺒﺘﺔ ﻭﻻ ﺘﺘﻐﻴﺭ‬ ‫ﺒﻴﻨﻤﺎ ﺇﺫﺍ ﻜﺎﻥ ﺍﻟﻤﻭﺭﺩ ﻤﺘﺤﻜﻡ ﻓﺈﻥ ﻤﺩﺓ ﺍﻟﻌﻤﻠﻴﺔ ﺘﺯﻴﺩ ﺃﻭ ﺘﻨﻘﺹ ﺒﺯﻴﺎﺩﺓ ﺃﻭ ﻨﻘﺼﺎﻥ ﺍﻟﻤﻭﺭﺩ‬ Driving ‫ﻏﺎﻟﺒﺎ ﻓﻲ ﻜل ﺍﻟﺨﻁﻁ ﺍﻟﺯﻤﻨﻴﺔ ﻻ ﻨﻔﻌل ﻫﺫﺍ ﺍﻟﺨﻴﺎﺭ‬ ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬ ٤/10 PDF created with pdfFactory trial version www.pdffactory.com
  • 5. ‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬ ‫‪Primavera‬‬ ‫ﺍﻟﺨﺎﺼﻴﺔ ‪ Base‬ﻓﻲ ﺍﻟﻌﻤﻭﺩ ﺍﻟﺭﺍﺒﻊ ﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﺒﻨﺎﻓﺫﺓ ‪ Resource‬ﺭﻭﺯﻨﺎﻤﺔ ﺍﻟﻤﻭﺭﺩ ﺭﻭﺯﻨﺎﻤﺔ ﺍﻟﻤﺸﺭﻭﻉ‬ ‫ﻜﺎﻥ ﺭﻗﻤﻬﺎ ١ ﻭﻫﻨﺎ ﺴﻴﺄﺨﺫ ﺭﻭﺯﻨﺎﻤﺔ ﺍﻟﻤﺸﺭﻭﻉ ﺤﻴﺙ ﻴﺸﻜل ﻨﺴﺨﺔ ﻋﻨﻬﺎ ﻭﻴﺴﻤﻴﻬﺎ ﺒﺎﺴﻡ ﺭﻭﺯﻨﺎﻤﺔ ﺍﻟﻤﻭﺭﺩ ﻭﻴﺴﻤﺢ‬ ‫ﺒﺈﺠﺭﺍﺀ ﺃﻱ ﺘﻌﺩﻴل ﻋﻠﻴﻬﺎ‬ ‫ﻓﻲ ﺍﻟﺠﺯﺀ ﺍﻟﺴﻔﻠﻲ ﻤﻥ ﻨﺎﻓﺫﺓ ‪ Resource‬ﻟﺩﻴﻨﺎ ﻨﺎﻓﺫﺓ ‪ Limits‬ﺍﻟﺤﺩﻭﺩ ﻭﻨﺎﻓﺫﺓ ‪ Prices‬ﺍﻟﻜﻠﻑ‬ ‫١- ‪ Limits‬ﺍﻟﺤﺩﻭﺩ ﻫﻲ ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﺍﻟﻤﺘﻭﻓﺭﺓ ﻟﺩﻴﻨﺎ‬ ‫‪ Normal‬ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﺍﻻﻋﺘﻴﺎﺩﻴﺔ ﺍﻟﻤﻭﺠﻭﺩﺓ ﻓﻲ ﺍﻟﻤﻭﻗﻊ‬ ‫ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﺍﻟﻌﻅﻤﻰ ﺍﻟﺘﻲ ﻴﻤﻜﻥ ﺃﻥ ﺘﺘﺄﻤﻥ ﻓﻲ ﺍﻟﻤﻭﻗﻊ‬ ‫‪Max‬‬ ‫ﺘﺤﺩﻴﺩﻩ ﻟﻪ ﻁﺭﻴﻘﺘﻴﻥ ١- ﺍﻟﺸﺭﻜﺔ ﺘﺤﺩﺩ ٥١ ﻤﺠﻤﻭﻋﺔ ﻹﻨﻬﺎﺀ ﺍﻟﻤﺸﺭﻭﻉ‬ ‫٢-ﺍﻟﺸﺭﻜﺔ ﺘﺴﺄل ﻤﺩﻴﺭ ﺍﻟﻤﺸﺭﻭﻉ ﻜﻡ ﻤﺠﻤﻭﻋﺔ ﻨﺠﺎﺭ ﻴﺤﺘﺎﺝ ﻹﻨﻬﺎﺀ ﺍﻟﻤﺸﺭﻭﻉ ﻓﻲ ﺍﻟﻤﺩﺓ‬ ‫ﺍﻟﻤﺤﺩﺩﺓ ﻭﺒﻬﺫﻩ ﺍﻟﺤﺎﻟﺔ ﻤﺩﻴﺭ ﺍﻟﻤﺸﺭﻭﻉ ﻴﻀﻊ ﺍﻟﺨﻁﺔ ﺍﻟﺯﻤﻨﻴﺔ ﺒﺎﻟﻜﺎﻤل ﻭﺒﺎﻷﺨﻴﺭ ﻴﺤﺴﺏ‬ ‫ﺒﺎﻟﺒﺭﻨﺎﻤﺞ ﻜﻡ ﻤﺠﻤﻭﻋﺔ ﻴﺤﺘﺎﺝ ﻭﺍﻟﻨﺎﺘﺞ ﺍﻟﺘﻲ ﻴﻅﻬﺭ ﻤﻌﻪ ﻴﺯﻴﺩﻩ ﺒﻨﺴﺒﺔ ٠٢ % ﻭﻴﻌﻁﻲ ﺍﻟﻨﺎﺘﺞ‬ ‫ﻜـ‪Normal‬‬ ‫ﺍﻟﺨﺎﺼﻴﺔ ‪ through‬ﻓﻲ ﺍﻟﻌﻤﻭﺩ ﺍﻟﺨﺎﻤﺱ ﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﺒﻨﺎﻓﺫﺓ ‪ Resource‬ﺘﻌﺒﺭ ﻋﻥ ﺘﻐﻴﺭ ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﻤﻊ‬ ‫ﺍﻟﺯﻤﻥ‬ ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬ ‫01/٥‬ ‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬
  • 6. ‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬ ‫‪Primavera‬‬ ‫ﻤﺜﻼ ﺸﺭﻜﺔ ﺴﺘﺅﻤﻥ ﻟﻠﻤﺸﺭﻭﻉ ﺨﻼ ﻤﺩﺓ ﻤﻌﻴﻨﺔ ﻤﻥ ﺘﺎﺭﻴﺦ .... ﺇﻟﻰ ﺘﺎﺭﻴﺦ ....... ٥١ ﻋﺎﻤل ﺜﻡ ﻭﺒﻌﺩ ﻤﺩﺓ ﺯﻤﻨﻴﺔ‬ ‫ﻤﻌﻴﻨﺔ ﺃﺭﺒﻌﺔ ﺃﺸﻬﺭ ﻤﺜﻼ ﻟﺩﻴﻬﺎ ﻋﻤﺎل ﻴﻌﻤﻠﻭﻥ ﻟﺩﻯ ﺸﺭﻜﺔ ﺃﺨﺭﻯ ﻭﺴﻴﻨﻬﻭﻥ ﻋﻤﻠﻬﻡ ﺒﺘﺎﺭﻴﺦ ..... ﻓﺒﻌﺩ ﻫﺫﺍ ﺍﻟﺘﺎﺭﻴﺦ‬ ‫ﻴﻤﻜﻥ ﺇﻀﺎﻓﺔ ٥ ﻤﺠﻤﻭﻋﺎﺕ ﻤﻨﻬﻡ ﺃﻭ ٠١ ﻟﻤﺸﺭﻭﻋﻨﺎ ﻭﺒﻬﺫﺍ ﻴﺼﺒﺢ ﻟﺩﻴﻨﺎ ٠٢ ﻤﺠﻤﻭﻋﺔ ﻋﻤﺎل ، ﻭﺒﻌﺩ ﺸﻬﺭ ﺘﻌﻭﺩ‬ ‫ﻜﻤﻴﺔ ﺍﻟﻤﻭﺍﺭﺩ ﻜﺎﻟﺴﺎﺒﻕ ﻭﻫﺫﺍ ﻨﺩﺨﻠﻪ ﻤﻥ ﺨﻼل ﺍﻟﻌﻤﻭﺩ ‪ Through‬ﻤﺜﻼ ﻨﺩﺨل:‬ ‫‪Normal‬‬ ‫‪Max‬‬ ‫‪Through‬‬ ‫21‬ ‫51‬ ‫7002/5/2‬ ‫02‬ ‫52‬ ‫7002/9/3‬ ‫21‬ ‫51‬ ‫ﻨﺘﺭﻙ ﻓﺭﺍﻍ‬ ‫ﻓﻴﺄﺨﺫ ﺍﻟﺭﻗﻡ ٥١ ﻋﻠﻰ ﻜﺎﻤل ﺍﻟﻤﺸﺭﻭﻉ‬ ‫‪ Price‬ﻜﻠﻔﺔ ﺍﻟﻤﺠﻤﻭﻋﺔ‬ ‫ﻤﺎ ﻫﻲ ﻭﻅﻴﻔﺔ ﺍﻟﻤﻔﺘﺎﺡ ‪ Calculate‬؟‬ ‫ﻟﻨﻔﺭﺽ ﺃﻨﻨﺎ ﺃﺩﺨﻠﻨﺎ ﺍﻟﻤﻭﺍﺭﺩ ﻭﺍﻟﻌﻤﻠﻴﺎﺕ ﻭﺭﺒﻁﻨﺎ ﺍﻟﻤﻭﺍﺭﺩ ﻤﻊ ﺍﻟﻌﻤﻠﻴﺎﺕ ﺜﻡ ﺤﺩﺙ ﺘﻐﻴﺭ ﻓﻲ ﺴﻌﺭ ﺍﻟﻤﻭﺭﺩ ﻜﺎﻥ‬ ‫ﻨﻀﻐﻁ ﻤﻔﺘﺎﺡ ‪ Calculate‬ﻓﻴﻌﻴﺩ ﺍﻟﺒﺭﻨﺎﻤﺞ‬ ‫ﻫﻨﺎ ﻨﺤﺘﺎﺝ ﻟﺘﻌﺩﻴل ﺍﻟﺴﻌﺭ‬ ‫٠٠١ ﺃﺼﺒﺢ ٥٢١‬ ‫ﺤﺴﺎﺏ ﻜﻠﻑ ﺍﻟﻌﻤﻠﻴﺎﺕ ﻜﻠﻬﺎ ﻟﻠﻤﺸﺭﻭﻉ ﺍﻋﺘﻤﺎﺩﺍ ﻋﻠﻰ ﺍﻟﻜﻠﻔﺔ ﺍﻟﺠﺩﻴﺩﺓ‬ ‫ﻤﺎ ﻫﻲ ﻭﻅﻴﻔﺔ ﺍﻟﻤﻔﺘﺎﺡ ‪ Transfare‬؟‬ ‫ﻭﻅﻴﻔﺘﻪ ﻨﻘل ﺍﻟﻤﻭﺍﺭﺩ ﻤﻥ ﺍﻟﻤﺸﺭﻭﻉ ﺇﻟﻰ ﺍﻟﻤﺸﺭﻭﻉ ﺍﻟﺤﺎﻟﻲ‬ ‫ﻤﺎ ﻫﻲ ﻭﻅﻴﻔﺔ ﺍﻟﻤﻔﺘﺎﺡ ‪ Calendars‬؟‬ ‫ﻭﻅﻴﻔﺘﻪ ﺃﻥ ﺍﻟﺒﺭﻨﺎﻤﺞ ﻴﻔﺘﺢ ﺍﻟﺭﻭﺯﻨﺎﻤﺔ ﻤﻥ ﺃﺠل ﺘﻌﺩﻴل ﺭﻭﺯﻨﺎﻤﺔ ﺍﻟﻤﻭﺭﺩ ﺍﻟﺤﺎﻟﻲ‬ ‫ﺍﻷﻥ ﺴﻨﺘﺤﺩﺙ ﻋﻥ ﻭﻅﻴﻔﺔ ﺍﻟﻨﺎﻓﺫﺓ ‪ Resource Curve‬ﻭﺍﻟﺘﻲ ﻨﻔﺘﺤﻬﺎ ﻤﻥ ﺍﻟﻘﺎﺌﻤﺔ ‪Data‬‬ ‫‪Data‬‬ ‫‪Resource curve‬‬ ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬ ‫01/٦‬ ‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬
  • 7. ‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬ ‫‪Primavera‬‬ ‫ﻫﻭ ﻤﻨﺤﻨﻲ ﺩﺨﻭل ﺍﻟﻤﻭﺭﺩ ﺇﻟﻰ ﺍﻟﻌﻤﻠﻴﺔ ، ﻭﺍﻟﻠﻭﻥ ﺍﻷﺼﻔﺭ ﻴﻌﺒﺭ ﻋﻥ ﺍﻟﻜﻤﻴﺔ ﺍﻟﻴﻭﻤﻴﺔ ﺒﻴﻨﻤﺎ ﺍﻟﻠﻭﻥ ﺍﻷﺯﺭﻕ ﻴﻌﺒﺭ ﻋﻥ‬ ‫ﺍﻟﺘﺭﺍﻜﻤﻴﺔ‬ ‫ﻨﻀﻐﻁ ﻤﻔﺘﺎﺡ ‪ Display‬ﻟﻤﻌﺭﻓﺔ ﺃﻨﻭﺍﻉ ﺍﻟﻤﻨﺤﻨﻴﺎﺕ ﺍﻟﻤﺘﻭﻓﺭﺓ ﻟﺩﻴﻨﺎ‬ ‫ﻟﻤﻌﺭﻓﺔ ﺃﻨﻭﺍﻉ ﺍﻟﻤﻨﺤﻨﻴﺎﺕ ﺍﻟﻤﺘﻭﻓﺭﺓ ﻟﺩﻴﻨﺎ؟‬ ‫ﻨﻨﻘﺭ ﻫﻨﺎ ﻓﺘﻅﻬﺭ ﺃﺸﻜﺎل‬ ‫ﻤﻨﺤﻨﻴﺎﺕ ﺠﺩﻴﺩﺓ‬ ‫‪ Linear‬ﺍﻟﻤﻭﻀﺢ ﺒﺎﻟﺯﺍﻭﻴﺔ ﺍﻟﻴﺴﺭﻯ ﺍﻟﻌﻠﻴﺎ ﻟﻠﻨﺎﻓﺫﺓ‬ ‫١-‬ ‫ﻨﻼﺤﻅ ﺃﻨﻪ ﺜﺎﺒﺕ ﻜل ﻴﻭﻡ ﻴﺯﻴﺩ ﺒﻨﻔﺱ ﺍﻟﻨﺴﺒﺔ " ﻤﺜﻠﺙ ﻤﺘﺴﺎﻭﻱ ﺍﻟﺴﺎﻗﻴﻥ "‬ ‫‪ Triangular‬ﺍﻟﻤﻭﻀﺢ ﺒﺎﻟﺯﺍﻭﻴﺔ ﺍﻟﻴﻤﻨﻰ ﺍﻟﻌﻠﻴﺎ ﻟﻠﻨﺎﻓﺫﺓ‬ ‫٢-‬ ‫ﻴﻜﻭﻥ ﻗﻠﻴل ﻭﻴﺯﻴﺩ ﺜﻡ ﻴﻘل ﻤﺭﺓ ﺜﺎﻨﻴﺔ‬ ‫‪ Triangular Increase‬ﺍﻟﻤﻭﻀﺢ ﺒﺎﻟﺯﺍﻭﻴﺔ ﺍﻟﻴﺴﺭﻯ ﺍﻟﺴﻔﻠﻰ ﻟﻠﻨﺎﻓﺫﺓ‬ ‫٣-‬ ‫ﺒﺩﺍﻴﺔ ﻤﺜﻠﺜﻴﺔ ﻭﺘﺯﺩﺍﺩ ﺤﺘﻰ ﻨﻬﺎﻴﺔ ﺍﻟﻤﺸﺭﻭﻉ‬ ‫‪ Triangular Decrease‬ﺍﻟﻤﻭﻀﺢ ﺒﺎﻟﺯﺍﻭﻴﺔ ﺍﻟﻴﻤﻨﻰ ﺍﻟﺴﻔﻠﻰ ﻟﻠﻨﺎﻓﺫﺓ‬ ‫٤-‬ ‫ﻤﺜﻠﺙ ﻤﺘﻨﺎﻗﺹ ، ﺒﺩﺍﻴﺔ ﻜﺒﻴﺭﺓ ﻭﺘﻨﺎﻗﺹ ﺤﺘﻰ ﻨﻬﺎﻴﺔ ﺍﻟﻤﺸﺭﻭﻉ‬ ‫ﻭﺘﻭﺠﺩ ﻤﺠﻤﻭﻋﺎﺕ ﺃﺨﺭﻯ ﻤﻥ ﺍﻟﻤﻨﺤﻨﻴﺎﺕ ﻹﻅﻬﺎﺭﻫﺎ ﻨﻀﻐﻁ ﺯﺭ‬ ‫ﻟﻪ ﻓﺎﺌﺩﺘﻴﻥ:‬ ‫ﻤﺎ ﻫﻲ ﺍﻟﻔﺎﺌﺩﺓ ﻤﻥ ﺍﺴﺘﺨﺩﺍﻡ ﻫﺫﺍ ﺍﻟﻤﻨﺤﻨﻲ؟‬ ‫١- ﺘﻐﻴﺭ ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﺍﻟﻴﻭﻤﻴﺔ ﺍﻟﺩﺍﺨﻠﺔ ﻟﻠﻌﻤﻠﻴﺔ ﻭﻫﺫﺍ ﻓﻴﻪ ﻨﻘﺼﺎﻥ ﻟﻠﻜﻠﻔﺔ‬ ‫٢- ﺘﻭﻓﻴﺭ ﻜﻤﻴﺎﺕ ﺍﻟﻤﻭﺍﺭﺩ ﻟﻌﻤﻠﻴﺎﺕ ﺃﺨﺭﻯ ﺘﻜﻭﻥ ﻤﺘﺯﺍﻤﻨﻪ ﻤﻊ ﻫﺫﻩ ﺍﻟﻌﻤﻠﻴﺔ‬ ‫ﺘﺨﻔﻴﺽ ﻓﻲ ﺍﻟﻜﻠﻔﺔ ﻭﺘﻭﻓﻴﺭ ﻓﻲ ﻜﻤﻴﺔ ﺍﻟﻤﻭﺭﺩ ﺍﻟﻤﺴﺘﺨﺩﻡ ﻻﺴﺘﺨﺩﺍﻤﻪ ﻓﻲ ﻋﻤﻠﻴﺎﺕ ﻤﺘﺯﺍﻤﻨﺔ ﻤﻊ ﺍﻟﻌﻤﻠﻴﺔ ﺍﻟﺤﺎﻟﻴﺔ‬ ‫ﻨﻌﻭﺩ ﻟﻨﺎﻓﺫﺓ ‪Resource Curve‬‬ ‫ﺍﻵﻥ ﻟﺘﺸﻜﻴل ﻤﻨﺤﻨﻲ‬ ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬ ‫01/٧‬ ‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬
  • 8. ‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬ ‫‪Primavera‬‬ ‫ﺜﻡ ﻭﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﻨﻀﻴﻑ ﺴﻁﺭ ﻓﻲ ﻗﺴﻡ ‪ " Designator‬ﻨﺤﺫﻑ ﺍﻟﺴﻁﺭ ﺍﻷﺨﻴﺭ ٩ ﻭﻨﻀﻴﻑ ﺒﺩﻴﻼ ﻟﻪ‬ ‫"ﻭﻨﺴﻤﻴﻪ ﻭﻨﻜﺘﺏ ﻭﺼﻑ ﻟﻪ‬ ‫‪Designator‬‬ ‫‪Title‬‬ ‫9‬ ‫‪test‬‬ ‫ﺜﻡ ﻨﻌﺩل ﺒﺎﻟﻨﺴﺏ ﺍﻟﻤﻜﺘﻭﺒﺔ ﺃﺴﻔﻠﻪ ﺒﺸﻜل ﻻ ﻋﻠﻰ ﺍﻟﺘﻌﻴﻴﻥ ﻭﻨﻼﺤﻅ ﺘﻐﻴﺭ ﻟﻭﻥ ﺍﻟﻤﺩﺓ ‪ Total‬ﺇﻟﻰ ﺍﻟﻠﻭﻥ ﺍﻷﺤﻤﺭ‬ ‫ﻋﻨﺩﻤﺎ ﺘﺯﻴﺩ ﻋﻥ ٠٠١ ﺤﻴﺙ ﻴﺠﺏ ﺃﻥ ﺘﺒﻘﻰ ﻗﻴﻤﺔ ‪١٠٠ = Total‬‬ ‫ﻭﻹﺭﺠﺎﻉ ﻫﺫﻩ ﺍﻟﻨﺴﺒﺔ ‪ Total‬ﺇﻟﻰ ٠٠١ ﻨﻀﻐﻁ ﺯﺭ ‪ Prorate‬ﺤﻴﺙ ﻴﻘﻭﻡ ﻫﺫﺍ ﺍﻟﺯﺭ ﺒﺈﺭﺠﺎﻉ ﺍﻟﻨﺴﺒﺔ ﺇﻟﻰ‬ ‫٠٠١% ﻋﻥ ﻁﺭﻴﻕ ﺘﺨﻔﻴﻀﻪ ﺍﻟﻌﻤﻠﻴﺎﺕ ﺒﻨﺴﺒﺔ ﺜﺎﺒﺘﺔ ﻟﻜل ﺍﻟﻤﺩﺩ ﺍﻟﺯﻤﻨﻴﺔ‬ ‫ﻭﻅﻴﻔﺔ ﺍﻟﺯﺭ ‪ Template‬ﺃﻨﻪ ﻴﺄﺨﺫ ﻤﻨﺤﻨﻲ ﻤﻭﺠﻭﺩ ﺴﺎﺒﻘﺎ ﻭﻴﺸﻜل ﻨﺴﺨﺔ ﻋﻨﻪ ﻭﻴﻌﺩل ﻋﻠﻴﻪ‬ ‫ﻨﻀﻐﻁ ﻤﻔﺘﺎﺡ ‪ Template‬ﻓﺘﻅﻬﺭ ﻨﺎﻓﺫﺓ‬ ‫ﻨﺨﺘﺎﺭ ﻤﻨﻬﺎ ﺸﻜﻼ ﻤﺎ‬ ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬ ‫01/٨‬ ‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬
  • 9. ‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬ ‫‪Primavera‬‬ ‫ﺜﻡ ﻨﻀﻐﻁ ‪OK‬‬ ‫ﺜﻡ ﻨﺠﺭﻱ ﺘﻌﺩﻴﻼﺘﻨﺎ ﻭﻨﻀﻐﻁ ﺯﺭ ‪ Prorate‬ﺜﻡ ‪. OK‬‬ ‫ﻭﻅﻴﻔﺔ ﺍﻟﻤﻔﺘﺎﺡ ‪ Restore‬ﻫﻭ ﺇﺭﺠﺎﻉ ﺍﻟﻘﻴﻤﺔ ﺍﻻﻓﺘﺭﺍﻀﻴﺔ ﻟﻠﻤﻨﺤﻨﻴﺎﺕ ﺍﻟﺠﺎﻫﺯﺓ .‬ ‫ﻨﻨﺘﻘل ﺍﻵﻥ ﺇﻟﻰ ﺃﻤﺭ ﺁﺨﺭ ﻤﻥ ﺃﻭﺍﻤﺭ ﺍﻟﻘﺎﺌﻤﺔ ‪ Data‬ﻭﻫﻭ ‪ Cost account‬ﺍﻟﺸﺠﺭﺓ ﺍﻟﻤﺤﺎﺴﺒﻴﺔ:‬ ‫‪Data‬‬ ‫‪Cost Account‬‬ ‫ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ‬ ‫ﻨﻜﺘﺏ ﺍﻟﻔﺌﺔ ﻭﺸﺭﺤﻬﺎ‬ ‫ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﺴﻔﻠﻰ‬ ‫ﻨﻜﺘﺏ ﺍﻟﺸﺠﺭﺓ ﺍﻟﻤﺤﺎﺴﺒﻴﺔ‬ ‫ﻜﻴﻑ ﺘﺒﻨﻰ ﺍﻟﺸﺠﺭﺓ ﺍﻟﻤﺤﺎﺴﺒﻴﺔ؟‬ ‫١- ﺃﺭﻗﺎﻡ ﻤﻜﻭﻨﺔ ﻤﻥ ﺨﺎﻨﺘﻴﻥ ﻤﺜﻼ ٢١ ﺃﻭ ٣١ ﺃﻭ ٤١ ﺃﻭ ..... ﺤﺘﻰ ٩٩‬ ‫٢- ﻜل ﺜﻨﺎﺌﻲ ﻴﺘﻔﺭﻉ ﻤﻨﻪ ﺜﻼﺜﻲ ﻭﻜل ﺜﻼﺜﻲ ﻴﺘﻔﺭﻉ ﻤﻨﻪ ﺭﺒﺎﻋﻲ ﻭﻜل ﺭﺒﺎﻋﻲ ﻴﺘﻔﺭﻉ ﻤﻨﻪ ﺨﻤﺎﺴﻲ ﻭﻜل ﺨﻤﺎﺴﻲ‬ ‫ﻴﺘﻔﺭﻉ ﻤﻨﻪ ﺴﺩﺍﺴﻲ ﻭﻜل ﺴﺩﺍﺴﻲ ﻴﺘﻔﺭﻉ ﻤﻨﻪ ﻋﺸﺭﻱ ﻷﻨﻪ ﺭﻗﻡ ﺍﻟﻔﻭﺍﺘﻴﺭ .‬ ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬ ‫01/٩‬ ‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬
  • 10. ‫ﺍﻟﻤﺤﺎﻀﺭﺓ ﺍﻟﺭﺍﺒﻌﺔ‬ ‫‪Primavera‬‬ ‫ﻤﺜﻼ ﺘﺴﺘﻁﻴﻊ ﺇﺩﺨﺎل ٠٠٠٠١ ﻓﺎﺘﻭﺭﺓ ﺘﺤﺕ ﻜل ﺭﻗﻡ .‬ ‫ﻤﺜﻼ ﻟﻨﻔﺭﺽ ﺃﻥ ﺍﻟﺤﺴﺎﺏ ﺭﻗﻡ ٢١ "ﺍﻟﻤﻜﻭﻥ ﻤﻥ ﺨﺎﻨﺘﻴﻥ " ﻴﻌﺒﺭ ﻋﻥ ﻤﻭﺠﻭﺩﺍﺕ ﺜﺎﺒﺘﺔ ﻟﻤﺅﺴﺴﺔ ﻤﺜل ) ﺍﻟﺒﻨﺎﺀ ،‬ ‫ﺍﻵﻟﻴﺎﺕ ، ﺍﻟﻔﺭﺵ ، ﺍﻷﺭﺍﻀﻲ ﺍﻟﺘﻲ ﺘﻤﻠﻜﻬﺎ ﺍﻟﻤﺅﺴﺴﺔ ..( ﻫﺫﻩ ﺍﻟﻤﻭﺠﻭﺩﺍﺕ ﺍﻟﺜﺎﺒﺘﺔ ﻴﻤﻜﻥ ﺃﻥ ﺘﻜﻭﻥ ﻓﻲ ]ﺍﻟﻘﻭﺍﻋﺩ‬ ‫)ﺒﺎﻟﻤﺩﻴﻨﺔ( ﺃﻭ ﻓﻲ ﺍﻟﻔﺭﻭﻉ )ﺒﺎﻟﻀﻭﺍﺤﻲ([‬ ‫ﻴﺘﻔﺭﻉ ﻋﻥ ﺍﻟﺨﺎﻨﺘﻴﻥ‬ ‫ﻜﻴﻑ ﺴﻨ ‪‬ﺭﻑ ﺃﻥ ﻜل ﻤﻥ ﻫﺫﻩ ﺍﻟﻤﻭﺠﻭﺩﺍﺕ ﻴﺘﺒﻊ ﻟﻠﺤﺴﺎﺏ ﺭﻗﻡ ٢١ ﺍﻟﺘﺎﺒﻊ ﻟﻠﻤﺅﺴﺴﺔ‬ ‫ﻌ‬ ‫ﺜﻼﺙ ﺨﺎﻨﺎﺕ ﻤﺜﻼ ١٢١ ﺃﻭ ٢٢١ ......ﺜﻡ ﻴﺘﻔﺭﻉ ﻋﻥ ﺍﻟﺨﺎﻨﺘﻴﻥ ﺜﻼﺙ ﺨﺎﻨﺎﺕ ﻭﻫﻜﺫﺍ‬ ‫)ﺒﺎﻟﻤﺩﻴﻨﺔ( ١٢١‬ ‫ﻓﻲ ﺍﻟﻘﻭﺍﻋﺩ‬ ‫ﺤﺴﺎﺏ ﺍﻟﻤﺅﺴﺴﺔ ٢١ ﻤﻭﺠﻭﺩﺍﺕ ﺜﺎﺒﺘﺔ‬ ‫١١١٢٢١‬ ‫ﺘﺨﺯﻴﻥ ١١٢٢١‬ ‫ﻴﻤﻜﻥ ﺃﻥ ﺘﻜﻭﻥ‬ ‫ﺃﺭﺍﻀﻲ ١٢٢١‬ ‫ﻓﻲ ﺍﻟﻔﺭﻭﻉ )ﺒﺎﻟﻀﻭﺍﺤﻲ( ٢٢١‬ ‫ﺒﻨﺎﺀ ٢١٢٢١‬ ‫ﺍﻵﻟﻴﺎﺕ ٢٢٢١‬ ‫ﺒﺭﻨﺎﻤﺞ ﺍﻟﻤﺤﺎﺴﺒﺔ ﻴﺠﻤﻊ ﻜل ﺍﻟﻔﻭﺍﺘﻴﺭ ﺍﻟﺘﻲ ﺃﺭﻗﺎﻤﻬﺎ ﺍﻟﺴﺘﺔ ﺍﻷﻭﻟﻰ ﺘﺴﺎﻭﻱ ﺍﻟﺭﻗﻡ ١١١٢١ ﻤﺜﻼ ﻭﺒﻌﺩ ﺃﻥ ﻴﺠﻤﻌﻬﺎ ﻴﺭﺤﻠﻬﺎ‬ ‫ﻟﻬﺫﺍ ﺍﻟﺤﺴﺎﺏ ﻭﻫﻜﺫﺍ .....‬ ‫ﻨﻔﺱ ﺍﻟﻨﻅﺎﻡ ‪ Primavera‬ﻭﻟﻜﻥ ‪ Primavera‬ﻫﻭ ٣١ ﻭﻟﻴﺱ ﻋﺸﺭﻱ ﺤﻴﺙ ﻟﺩﻴﻪ ٢١ ﻋﺩﺩ ﻭﻭﺍﺤﺩ ﺤﺭﻓﻲ .‬ ‫ﺍﻟﺨﺎﻨﺔ ﺍﻟﺤﺭﻓﻴﺔ ﻫﻨﺎ ﻫﻲ ﺍﻟﻔﺌﺔ ﺤﻴﺙ ﻟﺩﻴﻨﺎ ﻫﻨﺎ ﻤﺤﺎﺴﺒﺔ ﻤﺸﺎﺭﻴﻊ ﻤﺜﻼ ﻟﺩﻴﻨﺎ ﺃﻋﻤﺩﺓ ، ﻓﻘﻴﻤﺔ ﺃﻋﻤﺎل ﺍﻷﻋﻤﺩﺓ ﺘﺄﺘﻲ ﻤﻥ‬ ‫ﺘﻜﺎﻟﻴﻑ ﻤﻘﺎﻭل + ﺘﻜﺎﻟﻴﻑ ﻴﺩ ﻋﺎﻤﻠﻪ + ﺘﻜﺎﻟﻴﻑ ﻤﻭﺍﺩ + ........، ﺇﺫﻥ ﻫﻨﺎ ﻻ ﻨﺴﺘﻁﻴﻊ ﻭﻀﻊ ﺭﻗﻡ ﻟﻴﺩ ﻋﺎﻤﻠﺔ ﻭﺭﻗﻡ‬ ‫ﻟﻠﻤﻭﺍﺩ ﺒل ﺘﻭﺠﺩ ﻁﺭﻴﻘﺔ ﺃﺨﺭﻯ ﻟﻠﺘﻤﻴﻴﺯ ﻭﻫﻲ ﻜﺘﺎﺒﺔ ﺍﻟﻔﺌﺔ ، ﻓﺒﺤﺎل ﻜﻭﻥ ﺍﻟﻔﺌﺔ ‪ L‬ﻤﺜﻼ ﻓﻬﻲ ﺘﻌﺒﺭ ﻋﻥ ﺍﻟﻴﺩ ﺍﻟﻌﺎﻤﻠﺔ ..‬ ‫‪L‬‬ ‫ﻴﺩ ﻋﺎﻤﻠﺔ‬ ‫‪E‬‬ ‫ﺁﻟﻴﺎﺕ‬ ‫‪M‬‬ ‫ﻤﻭﺍﺩ‬ ‫‪S‬‬ ‫ﻤﻘﺎﻭل ﺒﺎﻁﻥ‬ ‫‪O‬‬ ‫ﺃﺨﺭﻯ‬ ‫ﺇﺫﻥ ﺒﺩﻭﻥ ﺨﺎﻨﺔ ﺤﺭﻓﻴﺔ ﻴﻌﻁﻲ ﺭﻗﻡ ﺇﺠﻤﺎﻟﻲ ﻭﻤﻊ ﺍﻟﺨﺎﻨﺔ ﺍﻟﺤﺭﻓﻴﺔ ﻴﻌﻁﻲ ﻟﻜل ﻓﺌﺔ ﻟﻭﺤﺩﻫﺎ.‬ ‫ﺒﻨﻅﺎﻡ ﺍﻟﻤﺤﺎﺴﺒﺔ " ﻨﺎﻓﺫﺓ ‪ " Cost Accounts‬ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﻤﺴﺘﻘﻠﺔ ﻋﻥ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﺴﻔﻠﻰ .‬ ‫ﻨﻜﺘﺏ ﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﻌﻠﻴﺎ ﺍﻟﻔﺌﺔ ﻭﺸﺭﺤﻬﺎ ﺒﻴﻨﻤﺎ ﻨﻜﺘﺏ ﻓﻲ ﺍﻟﻨﺎﻓﺫﺓ ﺍﻟﺴﻔﻠﻰ ﺍﻟﺸﺠﺭﺓ ﺍﻟﻤﺤﺎﺴﺒﻴﺔ‬ ‫ﻡ.ﺴﻤﺭ ﻅﺎﻫﺭ‬ ‫01/٠١‬ ‫‪PDF created with pdfFactory trial version www.pdffactory.com‬‬