  1. 1. November 9, 2020 Eglinton Crosstown LRT Leaside-Laird CLC
  2. 2. Leaside Station
  3. 3. LEASIDE STATION UPDATE 3INSERT FOOTER Activity Location Approx. Date & Duration Final lining and permanent works Waterproofing, rebar, steel, conduit installations, formwork, and concrete pours Underneath Eglinton Avenue within the Station Box Underway through to early 2021 Main Entrance Construction Waterproofing, rebar, steel, conduit installations, formwork, and concrete pours South east corner of Bayview Ave and Eglinton Ave Underway through to early 2021 Secondary Entrance Construction Waterproofing, rebar, steel, conduit installations, formwork, and concrete pours North west corner of Bayview Ave and Eglinton Ave Underway through to early 2021
  4. 4. LEASIDE STATION LOOK-AHEAD 4INSERT FOOTER Year What to Expect 2020 • Extended construction hours will continue through 2020. • Periodic lane closures may be required to facilitate deliveries, dewatering and concrete works. • Permanent works are underway at the station box and entrances, and will continue into early 2021, including waterproofing, formwork, rebar installation and concrete works • Construction of the entrances will progress upwards from the station to street level. • Architectural works, including tile installations, masonry work, and glazing, is expected to begin at the Main Entrance in approximately one (1) month.
  5. 5. CURRENT TRAFFIC CONFIGURATION 5 Through early 2021
  6. 6. CONSTRUCTION PROGRESS PHOTOS 6CENTRAL WEST WORKS MONTHLY MEETING CONCOURSE LEVEL – STATION BOX
  7. 7. CONSTRUCTION PROGRESS PHOTOS 7CENTRAL WEST WORKS MONTHLY MEETING MAIN ENTRANCE OVERVIEW
  8. 8. Laird Station
  9. 9. LAIRD STATION UPDATE 9 Activity Location Approx. Date & Duration • Installation of cable trays, conduits, drainpipes, fire dampers, sheet metal and drainpipes. • Shaft build back: North street level slab formwork installation. Conduit and rebar installation for south street slabs. Main Entrance Ongoing through to late 2020 • Shaft build back: Rebar installation on north concourse wall and formwork at arch. Secondary Entrance Ongoing through to late 2020 • OCS signage installation on east side, conduit rebar installation on east emergency walkways. • Waterproofing of grouting, OCS support installation. Tunnels Ongoing through to late 2020
  10. 10. CURRENT TRAFFIC CONFIGURATION 10 Through to late 2020
  11. 11. LAIRD STATION EXTENDED HOURS 11 • As early as September 14, 2020, construction activities at the both entrance shafts and tunnels will take place between the hours of 6:00 a.m. and 1:00 a.m., Monday to Saturday, through to the end of the year. • Work may occasionally take place on Sundays as required. WHAT TO EXPECT • Occasional overnight noise from construction equipment including trucks, machinery and crews may occur at the Main and Secondary entrances for concrete works. • Work within the tunnels is not expected to impact nearby residents as these activities will take place below grade. • Site lighting is required and will be positioned away from residential properties. • Crews will endeavor to schedule noisier activities during the day where possible. • Site-based mitigation measures will be implemented.
  12. 12. CONSTRUCTION PROGRESS PHOTOS 12 SECONDARY ENTRANCE NORTH CONCOURSE WALL REBAR INSTALLATION MAIN ENTRANCE FALSEWORK INSTALLATION
  13. 13. Section One At-Grade: Brentcliffe Portal to Sunnybrook Park Stop
  14. 14. SECTION ONE AT-GRADE UPDATE 14 Activity Location Approx. Date & Duration Boulevard works, final curbs and sidewalks. West of Brentcliffe Road – South Side September 30, 2020 to Mid-November Work is currently on hold Retaining Wall (East of Brentcliffe Road) Early August – December 2020 Multi-use path construction: backfill and compaction ongoing. Serena Gundy Park – West of Leslie St. Mid-July – December 2020 Construction of duct bank under bridge West Don River Bridge October 5 for six weeks Pedestrian staircase installation Eglinton and Leslie St. – South side October 30 for four weeks Bridge Rehabilitation CP Bridge, east of Leslie St. August 24 for 13 weeks CP BRIDGE REHABILITATION
  15. 15. BRENTCLIFFE PORTAL TO LESLIE STREET 15 September 30, 2020 through to mid-November • The pedestrian sidewalk will remain on the south side of Eglington Avenue East only. • The traffic configuration will accommodate road works on the south side of Eglinton Avenue East west of Brencliffe Road and in the centre of Eglinton Avenue, east of Brentcliffe Road. • Construction activities include: • Concrete removals • Construction of new sidewalk and curbs • Installation of new pavers • Installation of new traffic lighting elements • Asphalt and final paving
  16. 16. RETAINING WALL CONSTRUCTION NORTH SIDE OF EGLINTON EAST OF BRENTCLIFFE ROAD 16 • This retaining wall is required to hold and stabilize the embankment created from the newly widened road. • Construction commenced early August 2020. • Due to an unplanned movement of earth at the retaining wall construction site, construction has been paused. • CTS has followed all recommendations from the design and engineering teams to stabilize the area. • The area has been backfilled to further stabilize the embankment and tarped to prevent soil erosion. • Plans are being reviewed for the continued construction of the retaining wall. • Final landscaping and restoration plans are in review with Metrolinx and the City of Toronto.
  17. 17. DUCT BANK INSTALLATION WEST DON RIVER BRIDGE 17 • Crews will be installing duct banks under the bridge using a manlift and an excavator to lift the materials into place. • An alternating lane closure under the West Don River Bridge will be in place to facilitate bridge works. • Access to the E.T Seaton Park parking lot, south of Eglinton Avenue East will be maintained • There will be no changes to the current traffic configuration on Eglinton Avenue East. October 5, 2020 for six weeks
  18. 18. RAMP CONSTRUCTION, WEST OF LESLIE STREET MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK 18 • Construction activities for path construction include: Excavation, backfill and installation of topsoil • Landscaping will take place in 2021 as part of the final restoration plan. Mid-July 2020 through to December 2020
  19. 19. PARKING LOT CLOSURE FOR NEW PEDESTRIAN STAIRCASE INSTALLATION EGLINTON AVENUE EAST AT LESLIE STREET – SOUTH SIDE 19 • Crews will be installing structural steel to form the new pedestrian staircase. A crane will be installed at the work zone to lift materials into place. • To accommodate these activities, a section of the E.T Seton Park north parking lot will be closed. Access for pedestrian, cyclists and vehicles will be maintained. • No changes to traffic on Eglinton Avenue East. October 30, 2020 for four weeks
  20. 20. CP BRIDGE REHABILITATION EAST OF LESLIE STREET 20 • A working platform will be set up at the bridge in advance of the activities. • Crews will be removing rust, painting, replacing structural steel elements and performing concrete repairs. • Noise can be expected from concrete chipping and other rehabilitation works. August 24, 2020 for 13 weeks
  21. 21. CONSTRUCTION PROGRESS PHOTOS 21 SUNNYBROOK PARK STOP WEST DON RIVER BRIDGE DUCT BANK INSTALLATION

×