Successfully reported this slideshow.
We use your LinkedIn profile and activity data to personalize ads and to show you more relevant ads. You can change your ad preferences anytime.
Energy Last Mile Connectivity
Gaurav Bhatiani, Harsha Meenawat
IL&FS Academy of Applied Development
Rajasthan Priorities c...
Cost – Benefit Analysis of 3 Interventions for Rural Electrification
• Grid connectivity
• Solar Micro Grids
• Diesel Micr...
Why is Rural Electrification Important?
• Critical for the pathway to modern
economy
• Can change the nature of productivi...
Why should we look at these three models of electrification?
• All schemes have focused on grid extension in a top-down ap...
Intensive Village Electrification in Rajasthan
0
10
20
30
40
50
60
70
80
90
100
%
22% rural households were un-electrified...
Bikaner Rural Household Electrification – Demand for Power
• According to Saubhagya scheme survey
•38% rural households to...
Common Assumptions
• This analysis assumes that all labour costs grow at the projected real growth rate
• Capital costs ar...
1st analyzed solution
Extending Grid Connectivity in Bikaner
Model and Implementation Considerations
• Project life – 10 years starting from 2019
• Model – Connect all un-electrified ...
Costs
• New distribution assets created based on
current density of assets of JdVVNL
• Multiplier of 2.5 to account for lo...
Benefits
• Revenue accrued by DISCOM assumed
as a proxy for benefits accrued by
private citizens
• Salvage value of assets...
Risks and Uncertainties
• Uncertainties in demand estimation – varying estimates of actual number of rural
households
• Co...
Benefit – Cost Ratio
Discount rate
3% 5% 8%
NPV benefits 3,121 2,736 2,267
NPV costs 3,452 2,717 2,142
BCR 0.90 1.01 1.06
...
2nd analyzed solution
Distributed Generation using Solar Micro Grids in Bikaner
Model and Implementation considerations
• Project life – 10 years starting from 2019
• Installation of solar micro grids d...
Costs
• 169 MW of total solar micro grid
capacity added in year 1
• New capacity added each year based on
demand and growt...
Benefits
• Revenue accrued by DISCOM assumed
as a proxy for benefits accrued by
private citizens
• Salvage value of assets...
Risks and Uncertainties
• Uncertainties in demand estimation – varying estimates of actual number of rural
households
• Co...
Benefit – Cost Ratios
Sensitivity Analysis Resulting BCR at 5% Discount Rate
Capital Costs Over – Run by 10% 0.65
Capital ...
3rd analyzed solution
Distributed Generation using Diesel Powered Micro Grids in Bikaner
Model and Implementation Considerations
• Project life – 10 years starting from 2019
• Installation of diesel powered micr...
Costs
• 45 MW of diesel genset capacity added in year 1
• New capacity added each year based on
demand and growth in numbe...
Benefits
• Revenue accrued by DISCOM assumed
as a proxy for benefits accrued by
private citizens
• Salvage value of assets...
Risks and Uncertainties
• Uncertainties in demand estimation – varying estimates of actual number of rural
households
• Co...
Benefit – Cost Ratios
Discount rate
3% 5% 8%
NPV benefits 3,179 2,784 2,303
NPV costs 3,661 2,722 2,077
BCR 0.87 1.02 1.11...
Summary BCR
Interventions Discount Benefit Cost BCR
Grid
Electrification
3% ₹ 3,121 ₹ 3,452 0.90
5% ₹ 2,736 ₹ 2,717 1.01
8...
Upcoming SlideShare
Loading in …5
×

Rajasthan priorities energy last mile, ilfs

Rajasthan priorities energy last mile, ilfs

  • Be the first to comment

  • Be the first to like this

Rajasthan priorities energy last mile, ilfs

  1. 1. Energy Last Mile Connectivity Gaurav Bhatiani, Harsha Meenawat IL&FS Academy of Applied Development Rajasthan Priorities conference, Jaipur June 8-10, 2018
  2. 2. Cost – Benefit Analysis of 3 Interventions for Rural Electrification • Grid connectivity • Solar Micro Grids • Diesel Micro Grids • Comparison across models of centralized and distributed systems of generation • All interventions are targeted towards achieving a common goal of electrification of rural households
  3. 3. Why is Rural Electrification Important? • Critical for the pathway to modern economy • Can change the nature of productivity of households and markets • Welfare benefits of electrification •Lighting •Health •Education •Productivity •Increased labour participation •Enterprise development •Income generation India Current Scenario • An estimated 239 million people are without electricity access in India •25% of population estimated without electricity access globally • Urban electrification rate 97% • Rural electrification rate 74% • Electrification Programmes – •RGGVY •DDUGJY •Saubhagya Scheme
  4. 4. Why should we look at these three models of electrification? • All schemes have focused on grid extension in a top-down approach • Grid is predominantly fossil fuel powered •Coal accounts for 77% of total electricity generation and power accounts for 44% domestic GHG emissions of India • Centralized energy generation has externalized costs – particularly environmental – which are borne by society • Distributed generation reduces the amount of energy lost in transmitting electricity
  5. 5. Intensive Village Electrification in Rajasthan 0 10 20 30 40 50 60 70 80 90 100 % 22% rural households were un-electrified in Rajasthan as of October 2017 60% average rural household electrification rate across districts
  6. 6. Bikaner Rural Household Electrification – Demand for Power • According to Saubhagya scheme survey •38% rural households to be electrified in Bikaner as of October 2017 • Annual per capita residential electricity consumption is estimated at 225 units in 2019 • Residential electricity consumption is estimated to grow at 8% • Average number of hours of supply in Rajasthan is 22 hours
  7. 7. Common Assumptions • This analysis assumes that all labour costs grow at the projected real growth rate • Capital costs are estimated and fixed at 2017 levels • To capture the increase in purchasing power, revenues are also assumed to increase at real growth rate levels • Common outcome of provision of electricity to meet the demand of rural households
  8. 8. 1st analyzed solution Extending Grid Connectivity in Bikaner
  9. 9. Model and Implementation Considerations • Project life – 10 years starting from 2019 • Model – Connect all un-electrified households to electricity grid serviced by JdVVNL with 24 hours continuous supply per day • Set up of new distribution assets and additional generation capacity • Grid is assumed to be predominantly coal fired • JdVVNL would charge RERC approved electricity tariff to customers • Electricity generation from coal fired power plants leads to carbon emissions which would not have been emitted otherwise • Legacy model – grid has been the focus of rural electrification for a long time with national programmes
  10. 10. Costs • New distribution assets created based on current density of assets of JdVVNL • Multiplier of 2.5 to account for low population density • Capital outlay for assets in year 1 and 6 based on power demand in year 5 and 10 respectively • Cost of electricity estimated based on full cost recovery • Social Cost of Carbon accounts for costs borne by society at large due to carbon emissions from electricity generation using coal Costs of Grid Electrification Costs incurred (INR cr) at 5% Discount rate Cost of additional electricity generated ₹1,598 Capital costs incurred for transmission, distribution and meters ₹185 Operating and maintainence costs ₹751 Social cost of carbon ₹184 Total Costs ₹2,717
  11. 11. Benefits • Revenue accrued by DISCOM assumed as a proxy for benefits accrued by private citizens • Salvage value of assets that have a life more than project duration Benefits from Grid Electrification Benefits accrued (INR cr) at 5% Discount Rate Total Revenues ₹ 2,649 Salvage Value ₹ 87 Total Benefits ₹ 2,736
  12. 12. Risks and Uncertainties • Uncertainties in demand estimation – varying estimates of actual number of rural households • Costs for asset estimation depends on estimation of power demand • Cost of Carbon uncertainties – current levels of social cost of carbon may not capture real costs • Cost of coal – fluctuations in international coal prices • Possibility of WTP to be lesser than current tariff assumption and its escalation over the years
  13. 13. Benefit – Cost Ratio Discount rate 3% 5% 8% NPV benefits 3,121 2,736 2,267 NPV costs 3,452 2,717 2,142 BCR 0.90 1.01 1.06 Sensitivity Analysis Resulting BCR at 5% Discount Rate Increase in estimated O&M costs by 25% 0.94 Under recovery of revenues by 10% 0.91 Under recovery of revenues by 25% 0.76
  14. 14. 2nd analyzed solution Distributed Generation using Solar Micro Grids in Bikaner
  15. 15. Model and Implementation considerations • Project life – 10 years starting from 2019 • Installation of solar micro grids distributed across villages as per local capacity requirements • Model options - DDG with Discom, private OEM, PPP, community based models • Service delivery expected to be at par with grid connectivity • Tariff as per RERC approved grid tariff rates • Soft energy path with possibility of local enterprise development • Model tested in various locations across the country but not a mainstream model like grid
  16. 16. Costs • 169 MW of total solar micro grid capacity added in year 1 • New capacity added each year based on demand and growth in number of households • Battery life 5 years, replaced starting year 6 onwards • Additional battery back up to address intermittency (10 percent) • O&M costs to maintain micro solar grids Costs of Solar Micro Grid Costs incurred (INR cr) at 5% discount rate Capital costs of solar micro grids ₹ 9,745 Costs of battery replacements ₹ 1,387 Operation and maintenance costs ₹ 218 Total costs ₹ 11,350
  17. 17. Benefits • Revenue accrued by DISCOM assumed as a proxy for benefits accrued by private citizens • Salvage value of assets that have a life more than project duration Benefits from Solar Micro Grid Benefits accrued (INR cr) at 5% Discount Rate Total Revenues ₹ 2,649 Salvage Value ₹ 5,477 Total Benefits ₹ 8,126
  18. 18. Risks and Uncertainties • Uncertainties in demand estimation – varying estimates of actual number of rural households • Costs for asset estimation depends on estimation of power demand • Decreasing costs of Solar panels and battery • Possibility of WTP to be lesser than current tariff assumption and its escalation over the years
  19. 19. Benefit – Cost Ratios Sensitivity Analysis Resulting BCR at 5% Discount Rate Capital Costs Over – Run by 10% 0.65 Capital Costs Over – Run by 25% 0.57 Decrease in the capital cost for Solar Power by 10% 0.78 Decrease in the capital cost for Solar Power by 25% 0.91 Under recovery of revenues by 10% 0.69 Under recovery of revenues by 25% 0.66 Discount rate 3% 5% 8% NPV benefits 9,654 8,126 6,334 NPV costs 12,469 11,350 9,958 BCR 0.77 0.72 0.64
  20. 20. 3rd analyzed solution Distributed Generation using Diesel Powered Micro Grids in Bikaner
  21. 21. Model and Implementation Considerations • Project life – 10 years starting from 2019 • Installation of diesel powered micro grids distributed across villages as per local capacity requirements • Model options - DDG with Discom, private OEM, PPP, community based models • Service delivery expected to be at par with grid connectivity • Tariff as per RERC approved grid tariff rates • Model is soft path to energy, though based on fossil fuels – could be combined with other models • Electricity Generation from Diesel would lead to carbon emissions not emitted otherwise
  22. 22. Costs • 45 MW of diesel genset capacity added in year 1 • New capacity added each year based on demand and growth in number of households • Cost of Diesel estimated based on World Bank Commodity Price Forecast • Network connection costs incurred per household • Operating & Maintenance costs • Social Cost of Carbon accounts for costs borne by society at large due to carbon emissions from electricity generation using diesel Costs of Diesel Micro Grids Costs Incurred (INR Cr) at 5% Discount Rate Capital costs for diesel gensets ₹ 122 Cost of diesel ₹ 2,080 Network connection costs ₹ 130 O&M costs ₹ 117 Social Cost of Carbon ₹ 274 Total Costs ₹2,722
  23. 23. Benefits • Revenue accrued by DISCOM assumed as a proxy for benefits accrued by private citizens • Salvage value of assets that have a life more than project duration Benefits from Diesel Micro Grid Benefits accrued (INR cr) at 5% Discount Rate Total Revenues ₹ 2,649 Salvage Value ₹ 135 Total Benefits ₹ 2,784
  24. 24. Risks and Uncertainties • Uncertainties in demand estimation – varying estimates of actual number of rural households • Costs for asset estimation depends on estimation of power demand • Cost of Carbon uncertainties – current levels of social cost of carbon may not capture real costs • Cost of diesel – fluctuations in international crude prices • Possibility of WTP to be lesser than current tariff assumption and its escalation over the years
  25. 25. Benefit – Cost Ratios Discount rate 3% 5% 8% NPV benefits 3,179 2,784 2,303 NPV costs 3,661 2,722 2,077 BCR 0.87 1.02 1.11 Change in Variable Resulting BCR at 5% Discount Rate Increase in Crude Oil price from forecast by 10% 0.97 Increase in Crude Oil price from forecast by 25% 0.91 Increase in Social Cost of Carbon by 50% 0.97 Under recovery of revenues by 10% 0.93 Under recovery of revenues by 25% 0.78
  26. 26. Summary BCR Interventions Discount Benefit Cost BCR Grid Electrification 3% ₹ 3,121 ₹ 3,452 0.90 5% ₹ 2,736 ₹ 2,717 1.01 8% ₹ 2,267 ₹ 2,142 1.06 Solar Micro Grids 3% ₹ 9,654 ₹ 12,469 0.77 5% ₹ 8,126 ₹ 11,350 0.72 8% ₹ 6,334 ₹ 9,958 0.64 Diesel Micro Grids 3% ₹ 3,179 ₹ 3,661 0.87 5% ₹ 2,784 ₹ 2,722 1.02 8% ₹ 2,303 ₹ 2,077 1.11

×