City Council Meeting
June 12, 2014
 2008 Bond Authorization
 Proposal adding approximately 15,000 SF/parking
 Different proposals without clear scope of w...
 Proceed with project within framework of audit
report recommendations
 Summary of audit recommendations (13)
 Specific...
 Specific direction to not pursue
 Coffee shop / Bookstore
 Computer lab
 A second branch
 Additional book drops
 Ge...
 RFQ advertises in July 2014
 Short list interviews September 2014
 Design contract award in October 2014
 Design comp...
 Budget: $8,385,000
 Expended to date: $6,919.23
 Balance: $8,378,080.77
 Staff Recommendation:
Proceed with design wi...
Questions ?
Upcoming SlideShare
Loading in …5
×

Ringer Library Expansion Project Plan

794 views

Published on

  • Be the first to comment

  • Be the first to like this

Ringer Library Expansion Project Plan

  1. 1. City Council Meeting June 12, 2014
  2. 2.  2008 Bond Authorization  Proposal adding approximately 15,000 SF/parking  Different proposals without clear scope of work  Ringer Library Operations Audit report April 2014  Council Presentation in May 2014
  3. 3.  Proceed with project within framework of audit report recommendations  Summary of audit recommendations (13)  Specific redesign recommendations (11)
  4. 4.  Specific direction to not pursue  Coffee shop / Bookstore  Computer lab  A second branch  Additional book drops  General design principles  Consider long – term operational costs  Receive staff input  Remember noise reduction
  5. 5.  RFQ advertises in July 2014  Short list interviews September 2014  Design contract award in October 2014  Design complete in October 2015  Construction complete in October 2016
  6. 6.  Budget: $8,385,000  Expended to date: $6,919.23  Balance: $8,378,080.77  Staff Recommendation: Proceed with design within framework of audit report recommendations
  7. 7. Questions ?

×