  1. 1. POLICE HEADQUARTERS – GUARANTEED MAXIMUM PRICE MONDAY, OCTOBER 8, 2018
  2. 2. OVERVIEW OF PRESENTATION  Project Overview  Project Status  GMP Development / GMP  Total Project Cost  Project Schedule  Contract Amendment
  3. 3. PROJECT OVERVIEW  2016 Facility Program  $28M and 78,000 SF  October 2, 2017  $27.94 Million and 74,815 SF  Council desires a traditional design theme  November 9, 2017  New design concepts reviewed and Council direction provided  January 11, 2018  Approval of current design concept  Approval of project delivery method - Construction Manager at Risk  April 26, 2018  Approval of Vaughn Construction as the Construction Manager at Risk firm
  4. 4. PROJECT STATUS / GMP  PGAL – Design Phase - Design Development 100%  Next Phase: Construction Documents  Vaughn Construction – Pre-Construction Services  Working with PGAL on design review, constructability, material selection and developing the Guaranteed Maximum Price (GMP)  GMP – The maximum amount the construction portion of the project will cost per Vaughn Construction  They assume liability for construction cost overruns (except for any Owner requested changes)
  5. 5. GMP DEVELOPMENT  Vaughn Construction – Develop GMP  Comprehensive review of drawings and specs  Supplemental info from User Group (City Departments and Police Department Staff)  Material and labor take-off / estimating  Trades / Subcontractors provided budget analysis  Constructability and schedule review  Review of material and products
  6. 6. GMP  At the time of the Request For Proposals, the amount available for construction was specified as $25,000,000  Vaughn Construction Developed a GMP of $24,833,300  Delta of $166,700  Will be used to cover other Owner related project costs  GMP is within the specified construction budget  Project Budget has 2 parts  Construction Costs (GMP of $24,833,300)  Owner / Below the line Costs  includes design fees  Any item or service not covered by the GMP  The sum of these parts equals the Total Project Cost
  7. 7. TOTAL PROJECT COST  2016 Facility Program  $28,000,000  The proposed project budget, as submitted in the FY 2019 budget, is $29,500,000  FY 2016 dollars  Design changes  Project Delay Cost Escalation  Steel Tariffs and increased labor / material costs  Owner related costs not previously accounted for  As we have moved through the budget process, we anticipated the cost would increase and we are accounting for this in the FY 2019 budget.
  8. 8. ANTICIPATED PROJECT SCHEDULE  Oct. 8, 2018 – GMP presented for approval (notice to proceed to follow)  Nov. 12, 2018 – Vaughn mobilization / Construction begins  Nov. 16, 2018 – Ground Breaking Ceremony  10am on-site  Feb. 28, 2020 – Vaughn Substantial Completion  March 2, 2020 – Police Department Move-in  March 30, 2020 – Vaughn Final Completion
  9. 9. RECOMMENDATIONS  Approve the amendment to Vaughn Construction’s contract to include the GMP of $24,833,300 which is within the previously defined construction budget.

×