Lick Creek Sewer Trunk Line Contract

  1. 1. Regular Agenda Item #4 Lick Creek Sewer Trunk Line Construction Contract
  2. 2. Project Details • Identified in 2016 Wastewater Master Plan update • Parallel line from Lick Creek WWTP to north side of William D. Fitch • Route through Lick Creek Park and Pebble Creek Country Club • 54-inch and 48-inch PVC pipe
  3. 3. Contract Details • $10,932,672.50 • Thalle Construction Company, Inc. • 510 days • Golf course work to occur between November 1, 2019 and February 29, 2020

×