Lick Creek Trail
Project Status Report
City Council Meeting
May 22, 2014
Background
• 2002 – Proposed in the Bikeway and Pedestrian Master Plan
• 2004 – Prioritized by the Hike and BikeTask Force...
Segment A
Segment A
 Segment A (Eagle/Longmire/Barron)
 Reconstruct sidewalks
 Address ADA issues
 Stripe bike lanes
 Minimize ...
Segment B
Segment C
Budget Information
 Project Budget: $4,410,000
 Expended to Date: $590,983
 Balance: $3,819,017
 Construction Estimate...
Schedule Information
 July 2014: Bid for Construction
 August 2014: Award Construction Contract
 September 2014: Receiv...
QUESTIONS ?
Upcoming SlideShare
Loading in …5
×

Lick Creek Hike & Bike Trail

890 views

Published on

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
890
On SlideShare
0
From Embeds
0
Number of Embeds
574
Actions
Shares
0
Downloads
2
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Lick Creek Hike & Bike Trail

  1. 1. Lick Creek Trail Project Status Report City Council Meeting May 22, 2014
  2. 2. Background • 2002 – Proposed in the Bikeway and Pedestrian Master Plan • 2004 – Prioritized by the Hike and BikeTask Force and adopted by City Council as a High Priority • 2008 – Funding included in bond referendum approved by voters ($4.4 million) • 2011 – Awarded contract to Halff Associates to conduct a preliminary design study • May 2012 – Route alternatives presented to Council • January 2013 – Awarded design contract to Halff Associates
  3. 3. Segment A
  4. 4. Segment A  Segment A (Eagle/Longmire/Barron)  Reconstruct sidewalks  Address ADA issues  Stripe bike lanes  Minimize impacts to landscaping, fences, and neighborhood signs inside the ROW  Keep all improvements inside the existing ROW or existing public access easements
  5. 5. Segment B
  6. 6. Segment C
  7. 7. Budget Information  Project Budget: $4,410,000  Expended to Date: $590,983  Balance: $3,819,017  Construction Estimate w/10% Contingency: $3,400,000  Budgeted Annual O&M Costs: $33,000
  8. 8. Schedule Information  July 2014: Bid for Construction  August 2014: Award Construction Contract  September 2014: Receive/Review Initial Submittals, Hold Preconstruction Conference, and Establish Notice To Proceed Date  October 2014: Notice To Proceed With Construction  October 2015: Final Completion
  9. 9. QUESTIONS ?

×