  1. 1. General Parkway Change Order No. 1 Regular Agenda Item No. 6 March 28, 2019
  2. 2. General Parkway
  3. 3. General Parkway
  4. 4. Change Order No. 1 • Removal of additional soil • Additional stabilization & imported fill • Almost full length of project • Change order amount - $63,467.50 • Additional 40 days • Completion June 2019

×