We use your LinkedIn profile and activity data to personalize ads and to show you more relevant ads. You can change your ad preferences anytime.

FY19 Bond Authorization

504 views

Published on

FY19 Bond Authorization

Published in: Government & Nonprofit
  • Be the first to comment

  • Be the first to like this

FY19 Bond Authorization

  1. 1. March 28, 2019
  2. 2. Bond Issuance Process 3/28 – Council Publication of Notice of Issuance 4/12 –Rating agency discussion and visit with Staff  S&P –Visit – current rating AA+  Moody’s - Call – current rating Aa1 5/13* – Estimated Pricing date 5/13 – Council Ordinance Authorizing Issuance 6/1 – Offering date 6/10 – Closing date
  3. 3. FY19 Issuance Key Projects General Government Projects Amount Streets $ 7,711,000 Parks $ 8,464,000 General Government $ 22,925,000 Subtotal $ 39,100,000 Utility Projects Electric $ 4,200,000 Water $ 13,006,000 Wastewater $ 24,994,000 Subtotal $ 42,200,000 Debt Issuance Estimate $ 700,000 Total Anticipated Issue $ 82,000,000
  4. 4. FY19 Issuance Key Projects Amount Greens PrairieTrail - CL W ofWoodlake to Royder 2,000,000 Greens Prairie Rd - Arrington to CL W of WS Phillips 1,000,000 SH 40 and FM 2154 Interchange 1,000,000 Royder Rd Ph 3 - FM 2154 to I&GN Road 900,000 Other Street, Signal and Sidewalk Projects 2,811,000 StreetsTotal $ 7,711,000 Southeast Park 4,600,000 Thomas Park Rehabilitation 1,000,000 Other Parks Improvements 2,864,000 ParksTotal $ 8,464,000 New City Hall 18,900,000 New Police Station 1,500,000 Fuel System Rehab 920,000 Other Facility &Technology Projects 1,605,000 General Government Total $ 22,925,000 Governmental Subtotal $ 39,100,000
  5. 5. FY19 Issuance Key Projects Amount Land Acquisition - Wells 5,000,000 Transmission and Distribution Projects 1,919,000 Combo SPPS Site Improvements 1,284,000 Other Water Projects 4,803,000 WaterTotal $ 13,006,000 LC Capacity Expansion & Nutrient Removal 10,800,000 CCWWTP Centrifuge Improvements FY18 2,490,000 CC Diversion Lift Station/Force Mn 2,340,000 SouthwoodValley Trunkline 1,479,000 Other Wastewater Projects 7,885,000 WastewaterTotal $ 24,994,000 Advanced Metering Infrastructure (AMI) 4,200,000 ElectricTotal $ 4,200,000 Utility CO Subtotal $ 42,200,000
  6. 6. Council Action Council Action •Future Council Action

×