DS-17-014 City Council Chambers Concept

  1. 1. January 17, 2017
  2. 2.  Workshop broadcast discussion Jun. 2016  City Hall Structural Assessment Sep. 2016  Council Chambers relocation site evaluations Nov. 2016  Architectural renderings Dec. 2016-Jan. 2017
  3. 3.  Demolition  New walls, doors, casework, lighting, ceiling, electrical, paint  Elevated flooring in Council break room and A/V studio  New entry and exit doors and exterior canopy  Accessible sidewalks and ramps  New seating
  4. 4.  Lighting and ceiling above dais  Electrical and data at dais and podium  Elevated floor, stairs and ramp to dais  Casework and low walls at dais  Killeen seal
  5. 5.  Create new broadcast studio  Move head end and broadcasting equipment  Hardwire sound, lighting, video, cameras  Relocate production and streaming equipment  Install modern dais
  6. 6. ADVANTAGES  Not decommissioning space  All meetings in same place  One set of broadcasting equipment (reuse)  Flexible floorplan  Additional seating  Sound improvements  Broadcast and streaming of all Council meetings DISADVANTAGES  Move = expense  Workshops at City Hall during construction  No separate meeting spaces

×