December 2013Introductory Meeting: Connecticut Expansion Project Page 1
SGA Environmental Roundtable
Tennessee Gas Pipelin...
Agenda
• Tennessee Gas Pipeline Overview
• Project Overview
• Project Timeline
• FERC Limited Notice to Proceed Challenges...
• Over 50 years of experience in pipeline system design, construction, and operation
• Tennessee is prepared to meet the d...
Project Overview
Facility Facility Type Length (approx miles) County State
251-1 36-inch pipeline loop 1.4 Albany NY
258-1 36-inch pipeline...
Connecticut Expansion Project
Timeline
Milestone Date
Project Kickoff August 2013
Environmental Surveys and Data Gathering...
Limited Notice to Proceed Challenges
• NLEB/Indiana Bats (N/A if outside of 150 foot of KNOWN
roost trees)
• MBTA (TOY res...
Limited Notice to Proceed Timeline
• Chronology of TGP’s request for NTP for tree felling:
• 03/22/16: Filed tree felling ...
Notice to Proceed cont.
• 04/13/16: TGP files 2nd response to FERC’s 2nd request for additional information to support the...
Current Status
• NTP- has not been issued
• MA WQC- not issued (1 year review period ends July 17)
• CT WQC - not issued (...
Thank You
Questions?
Upcoming SlideShare
Loading in …5
×

CT EXP SGApresentation

65 views

Published on

  • Be the first to comment

  • Be the first to like this

CT EXP SGApresentation

  1. 1. December 2013Introductory Meeting: Connecticut Expansion Project Page 1 SGA Environmental Roundtable Tennessee Gas Pipeline Connecticut Expansion Project Brian Benito Jr. Senior Environmental Specialist Kinder Morgan Major Projects June 14, 2016
  2. 2. Agenda • Tennessee Gas Pipeline Overview • Project Overview • Project Timeline • FERC Limited Notice to Proceed Challenges • FERC Limited Notice to Proceed Docket Filings • Federal and State Permitting Status • Questions?
  3. 3. • Over 50 years of experience in pipeline system design, construction, and operation • Tennessee is prepared to meet the demands of a growing market with the integrity and commitment to service that have made it one of the safest and most reliable pipelines in the United States • Supply Regions: Gulf of Mexico, Texas, Appalachia, Mid-Continent & Apps Shale, Rockies, and Canada • Markets: Northeast (including major metropolitan centers in NY/NJ and Boston), Mid-Atlantic, and the Southeast • Pipeline Interconnects: >100 interconnects with most major interstate and intrastate pipeline systems in and around TGP’s markets Growing Markets and Supply Experience and Reliability Size • Over 11,900 Miles of pipeline • Over 90 Bcf of Working Gas Storage • 1.4 million certificated horsepower • Spans from the Mexican border to southern New Hampshire Tennessee Gas Pipeline Background
  4. 4. Project Overview
  5. 5. Facility Facility Type Length (approx miles) County State 251-1 36-inch pipeline loop 1.4 Albany NY 258-1 36-inch pipeline loop 3.8 Berkshire MA 261-1 24-inch pipeline loop 8.1 Hampden/Hartford MA/CT 13.3 Varying existing ROW widths Connecticut Expansion Project Detailed Facilities ROW Configuration – Existing NY ROW is 65, 70, and 100 feet wide with a 24- inch and 30-inch pipeline (9 properties) – Existing ROW in MA is nominal 80 and 90 feet wide with a 24-inch and 30-inch pipeline (16 properties) – Existing ROW in CT is nominal 30 to 50 feet wide with 1 existing 16-inch pipeline (71 properties)
  6. 6. Connecticut Expansion Project Timeline Milestone Date Project Kickoff August 2013 Environmental Surveys and Data Gathering Oct/Nov 2013 MEPA FEIR April 2015 FERC EA Oct 2015 FERC Certificate March 11, 2016 (605 days after filing) ACOE NY/NE Soon CT/MA WQC Sooner IP & (Limited) Notice to Proceed Filed March 22, 2016
  7. 7. Limited Notice to Proceed Challenges • NLEB/Indiana Bats (N/A if outside of 150 foot of KNOWN roost trees) • MBTA (TOY restrictions) • ACOE Section 404 jurisdiction (N/A if non mechanized and vegetation left in place) • CT/MA Section 401 jurisdiction (N/A in CT and N/A in MA if non mechanized and vegetation removed) • CT NDDB Dwarf wedgemussels (N/A if 100’ buffer maintained) • MA Article 97 (N/A-State forest parcel not included in NTP) • Section 106 (Tribes unresponsive)
  8. 8. Limited Notice to Proceed Timeline • Chronology of TGP’s request for NTP for tree felling: • 03/22/16: Filed tree felling NTP request and IP http://elibrary.FERC.gov/idmws/file_list.asp?accession_num=20160322-5172 – Included with the NTP filing is the Williams Company Constitution Project NY ACOE concurrence that tree felling by hand (non mechanized) is not regulated under Section 404 • 03/25/16: FERC’s 1st request for additional information to support the request http://elibrary.FERC.gov/idmws/file_list.asp?accession_num=20160325-3003 – FERC inquired about MBTA TOY restrictions associated with felling tree during the breeding season – FERC requested “evidence” that NY&NE ACOE concur that 404 is not required – FERC requested “evidence” that CT&MA DEP concur that 401 is not required • 03/30/16: TGP files response to FERC’s 1st request for additional information to support the request http://elibrary.FERC.gov/idmws/file_list.asp?accession_num=20160330-5304 – TGP acknowledges that tree felling will not be completed prior to states 3/31 TOY window but points FERC back to IP statement showing TGP has requested and extension until 5/1 from USFWS – Emails from NY&NE ACOE that states 404 is not tripped provided “trees that have been felled in wetlands are not removed with mechanized equipment (this includes pulling or pushing in such a manner that would result in a discharge of sediment) until the proper authorizations have been obtained” – General TGP statement reminding FERC that absent a federal nexus, there is no means for a state water quality certification under Section 401 of CWA • 03/30/16: FERC’s 2nd request for additional information to support the request http://elibrary.FERC.gov/idmws/file_list.asp?accession_num=20160330-3061 – FERC requests a copy of the USFWS TOY extension letter • 04/11/16: TGP files 1st response to FERC’s 2nd request for additional information to support the request http://elibrary.FERC.gov/idmws/file_list.asp?accession_num=20160411-5119 – TGP files documentation showing TOY restriction extension request to USFWS
  9. 9. Notice to Proceed cont. • 04/13/16: TGP files 2nd response to FERC’s 2nd request for additional information to support the request http://elibrary.FERC.gov/idmws/file_list.asp?accession_num=20160413-5241 – TGP files documentation that USFWS acknowledges that there is no TOY restriction associated with MTBA • 05/04/16: FERC’s 3rd request for additional information to support the request http://elibrary.FERC.gov/idmws/file_list.asp?accession_num=20160504-3010 – In response to an email from USFWS, FERC requested TGP to provide a list of qualified wildlife rehabilitators in the Project area that may be called upon, if necessary, during tree felling and other Project activities • 05/06/16: TGP files response to FERC’s 3rd request for additional information to support the request http://elibrary.FERC.gov/idmws/file_list.asp?accession_num=20160506-5079 – TGP files list
  10. 10. Current Status • NTP- has not been issued • MA WQC- not issued (1 year review period ends July 17) • CT WQC - not issued (DWM consultations ongoing) • NY WQC- issued 2/9/2016 • NY ACOE- expected anyday • NE ACOE- awaiting CT/MA 401, FWS DWM BO, Section 106 in MA • Article 97- May 9th condemnation proceedings concluded; favorable ruling stayed until July 29th
  11. 11. Thank You Questions?

×