FWP 2017 l Philippe VEYAN, EDF EN

  1. 1. PROVENCE GRAND LARGE © SBM Offshore
  2. 2. #FWPAtlan*c PILOT FARM PROVENCE GRAND LARGE Floa*ng wind pioneer
  3. 3. 3 HISTORY § Launched in 2010 with Nénuphar-Technip, selec@on NER 300 2012 § Site decided mid -2013, 1st authoriza@on package obtained in 2014 § New turbine and float in 2015 & 2016 •  3 x 8 MW Siemens •  3 x TLP SBM Offshore § Award by french state in 2016 § New permits submiUed mid-2017
  4. 4. 4 CONSENT § 1000 mee@ngs since 2010, 300 ac@ve local players § CNDP concerta@on achieved in april 2017 § May 2017 : new permits (PGL + Rte) submiUed § « Commissions nau@ques » approval in sep 2017 § 1 liaison commiUee § 1 scien@fique commiUee § 1 local industries work group § Local partnerships : fishing, universi@es, local councils, etc.
  5. 5. 5 ENGINEERING § Metmast onshore since 2015 § Metocean buoy decommissioned in 2016 ader 2 years § All ocean surveys (Geophy, UXO, geotech) completed Oct 2017 § Floa@ng lidar deployed in oct 2017 § Early Works (derisking studies) with Siemens et SBM § Grid connec@on conven@on signed with RTE § Cable package contract no@ce in sept 2017
  6. 6. 6 PORT § 15 sites surveyed in french mediterranean harbours § Selected site : west basins of Marseille – Fos harbour § Main issues •  Scarcity of available grounds •  Quay and ground loads •  Co-ac@vity with exis@ng traffic •  Marine safety •  Civil and military aeronau@cal procedures •  Authorisa@ons!
  7. 7. 7 LINKS WITH COMMERCIAL PHASE § Poten@al in PACA up to 2 GW, 25% of regional produc@on § Local players expect pilot phase REX first! § Step 1 : speed up pilot projects processing •  Limited scale/impact => procedures shoud speed up •  Environment monitoring to remain « per@nent » et « reasonnable » •  Upstream involvement of local environment stakeholders § Step 2 : In // clarify « commercial » roadmap •  Give long term target to industrial players / investors •  Start working on poten@al areas now! •  Strengthen consulta@on process with local stakeholders •  Tenders to be launched separatetly un@l parity with fixed offshore achieved •  An@cipa@on of grid connec@on, logis@cs and harbors infrastrucures