SlideShare a Scribd company logo
1 of 24
Classification of contracts
Activities in construction project
• Engineering
– Issues related to process finalization, structural
analysis & design, technical issues related to
equipment design & selection
• Procurement
– Procurement of materials , also includes
identification of suitable vendors
• Construction
– This covers construction, installation & test run of
a constructed facility before handed to owner
Classification
• Seperated contracts
• Management contracts
• Integrated contracts
• Discretionary contracts
Separated contracts
• Lump sum contract
• Measurement contract
• Item rate
• Percentage rate
• Cost plus percentage
Management contract
• Management contract
• Construction management contract
• Design, management & construction contract
• Integrated contract
• Design build contract
• Turn key contract
• Build, operate & transfer contract
Discretionary contract
• Partnering contract
• Joint venture contract
Separated
• Traditional system & sequential process
• Division b/w design & construction responsibility
• Design - project briefing, outlining proposal,
detail design, etc.
• Delay - preparation & approval of drawings,
mistakes in design documentation
• Lengthy tendering period & suitable for small to
medium sized projects where time is not critical
• Major drawbacks
– Time consuming aspects of development process
– Effect of cost uncertainty
– Effect of buildability
– Fragmentation of organizational interfaces
Lump sum contract
• Drawings & details provided by client &
contractor quotes single lump sum figure
which is the total contact value of work
• Total sum based on analysis of rates &
estimated quantities
• Advantage - client know exact amount of
funds required to complete structure
• Successful lumpsum contract
– Quantities of items Involved are calculated at
tendering stage itself
– Nature of work done must be reasonably
measurable
– Contractor must be give All the facilities to which
he is contractually entitled
• Revision of amount in Case of change in
design by client
Measurable contract
• Payment made according to actual work
varied out, which is determined by physical
measurements
Item rate contract
• The contractor agrees to carry out a unit quantity
of particular work (cm3,m2) for particular sum of
money
• In this tender document consists of detailed BOQ
, where estimated quantity of work for each item
involved in particular work are listed along with
detailed description
• Total contract value - multiply total quantity with
quoted item rate and add cost of all items
• Some items are not covered in BOQ but
essential for completing job, in such cases
rates are given on basis of labor, material,
equipment etc
S.no Item Measurement
unit
Quantity Rate Amount
1 Cement Kgs 50 280 14000
2 Steel Ton 2 42000 84000
Percentage rate contract
• Tender document contains scheduled rates for
each work in addition to detailed estimate for
execution of work
• Contractor works out his rates for items i
usual manner& arrives at total price which is
converted to total percentage by which
amount differs
• Adopted by government departments & large
organizations
• Contractor amount -- Z
• Z > W , the % rate = (z-w)/w *100 above W
• Z < W , the % rate =(w-z)/w*100 below W
S.no Item Measure
ment unit
Quantity Rate Amount
1 Cement Kgs 50 280 14000
2 Steel Ton 2 42000 84000
W 14000+84000
Cost plus percentage
• Client agrees to pay contractor a certain % of
actual cost incurred by contractor while
completing a job in addition to cost itself.
• Tenderer only quotes his percentage
• Usually taken up when time is not available to
make estimate and workout details of items
involved
• Suitable for small jobs.
Management contract
• Managing contractor is appointed and he
deals with number of small contractors
• Client deals with only contractor and designer
• Contractor provides planning, management &
coordination services to client
• Responsibilities
– Preparing overall construction schedule
– Work package schedule
– Coordinating with designer
– Assistance in subcontractors selection
– Coordinating among different subcontractors
Construction management contract
• Construction manager appointed by client to
provide planning, management &
coordination
• Owner appoints designer & contractors
• Role of construction manager is to coordinate
among different subcontractors & ensuring
timely completion of project within budget
cost according to specifications
• Some responsibilities are
– Advising the designer
– Advising on making suitable work package
– Assisting in procurement
– Managing bidding process
Design, management & construction contract
• Client appoints single contractor to take care
of design & construction
• Basic design concepts may be provided by
client himself or through an independent
agency
• After basic concepts client calls for tender and
selects appropriate agency for designing ,
management & construction services
Integrated contract
• Design- build
– In this contractor takes the responsibilities of both
design & construction based on basic plans drawn
up by the client
– This avoids conflict b/w designer & contractor
– Often adopted when client has no in-house design
with him
– This method Reduces the cost , develops the
technical power in contractor & reduces disputes
The turn-key contract
• Responsibilities of all activities are taken up by
contracting agency
• The owner simply wants to “turn the key” at
completion to take over the facility
• All activities related to surveying , drawing
specifications , design , project planning ,
construction & test operation are given to one
large organisation
• They are useful in projects involving combination
of civil, electrical, mechanical, chemical & mining
engineering
• Mostly seen in petrochemical plants & nuclear
power stations
• STEPS
• In a project client first prepares documents
regarding requirements of facilities to be
constructed
• Later he selects the best proposal submitted by
multiple bidders

More Related Content

What's hot

3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...Praveen Premkumar
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentationArchDuty
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts fritzlejarso
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4Moustafa Ismail Abu Dief
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTVISHNU VIJAYAN
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in constructionMahSobeh
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionAshwiniChaudhari13
 
International construction contract
International construction contractInternational construction contract
International construction contractGlobal Negotiator
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender NoticeSakshi Kirar
 

What's hot (20)

3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Construction contract
Construction contract Construction contract
Construction contract
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
 
Contracts
ContractsContracts
Contracts
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 
Construction contracts
Construction contractsConstruction contracts
Construction contracts
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Module 4 lecture 1
Module  4 lecture 1Module  4 lecture 1
Module 4 lecture 1
 
Construction contract
Construction contractConstruction contract
Construction contract
 
International construction contract
International construction contractInternational construction contract
International construction contract
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
 

Viewers also liked

Types of contract
Types of contractTypes of contract
Types of contractSweetp999
 
Pozvánka na eGovernment SR 2011
Pozvánka na eGovernment SR 2011Pozvánka na eGovernment SR 2011
Pozvánka na eGovernment SR 2011Geokomunita
 
Pert cpm-120421125920-phpapp02
Pert cpm-120421125920-phpapp02Pert cpm-120421125920-phpapp02
Pert cpm-120421125920-phpapp02kongara
 
Air Barrier Systems in Buildings
Air Barrier Systems in BuildingsAir Barrier Systems in Buildings
Air Barrier Systems in BuildingsShahin MB
 
Types of contract - Legal Environment of Business - Business Law - Manu Melwi...
Types of contract - Legal Environment of Business - Business Law - Manu Melwi...Types of contract - Legal Environment of Business - Business Law - Manu Melwi...
Types of contract - Legal Environment of Business - Business Law - Manu Melwi...manumelwin
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
Rate Analysis Site Meeting
Rate Analysis   Site MeetingRate Analysis   Site Meeting
Rate Analysis Site MeetingSanjay Patnaik
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
Introduction to contract law - offer by Maxwell ranasinghe
Introduction to contract law  - offer by Maxwell ranasingheIntroduction to contract law  - offer by Maxwell ranasinghe
Introduction to contract law - offer by Maxwell ranasingheMaxwell Ranasinghe
 
project-report-on-working-capital
project-report-on-working-capitalproject-report-on-working-capital
project-report-on-working-capitalRamesh Ankathi
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project managementAli Heydari
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementAditi Shah
 

Viewers also liked (20)

Types of contract
Types of contractTypes of contract
Types of contract
 
Pozvánka na eGovernment SR 2011
Pozvánka na eGovernment SR 2011Pozvánka na eGovernment SR 2011
Pozvánka na eGovernment SR 2011
 
Pert cpm-120421125920-phpapp02
Pert cpm-120421125920-phpapp02Pert cpm-120421125920-phpapp02
Pert cpm-120421125920-phpapp02
 
Item rate contract
Item rate contractItem rate contract
Item rate contract
 
Plainsboro cts update
Plainsboro cts updatePlainsboro cts update
Plainsboro cts update
 
Air Barrier Systems in Buildings
Air Barrier Systems in BuildingsAir Barrier Systems in Buildings
Air Barrier Systems in Buildings
 
Types of contract - Legal Environment of Business - Business Law - Manu Melwi...
Types of contract - Legal Environment of Business - Business Law - Manu Melwi...Types of contract - Legal Environment of Business - Business Law - Manu Melwi...
Types of contract - Legal Environment of Business - Business Law - Manu Melwi...
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Rate Analysis Site Meeting
Rate Analysis   Site MeetingRate Analysis   Site Meeting
Rate Analysis Site Meeting
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Nature of contract
Nature of contractNature of contract
Nature of contract
 
Introduction to contract law - offer by Maxwell ranasinghe
Introduction to contract law  - offer by Maxwell ranasingheIntroduction to contract law  - offer by Maxwell ranasinghe
Introduction to contract law - offer by Maxwell ranasinghe
 
project-report-on-working-capital
project-report-on-working-capitalproject-report-on-working-capital
project-report-on-working-capital
 
Datta_Resume
Datta_ResumeDatta_Resume
Datta_Resume
 
Types of contract in Project management
Types of contract in Project managementTypes of contract in Project management
Types of contract in Project management
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 

Similar to Classification of contracts

types-170309142854.pptx
types-170309142854.pptxtypes-170309142854.pptx
types-170309142854.pptxssuser42980c
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureHASMANIRA
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract Venuri Lakshani
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Construction Management - L1 (1).ppt
Construction Management - L1 (1).pptConstruction Management - L1 (1).ppt
Construction Management - L1 (1).pptmona700185
 
Construction management l1
Construction management   l1Construction management   l1
Construction management l1Faisal Rana
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyorLY97
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor温 庄壁
 
Professional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbalProfessional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbalZakee Kazmee
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Felix Vong
 
The Design Assist Method of Project Delivery
The Design Assist Method of Project DeliveryThe Design Assist Method of Project Delivery
The Design Assist Method of Project DeliverySHKLaw
 
Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014SHKLaw
 

Similar to Classification of contracts (20)

types-170309142854.pptx
types-170309142854.pptxtypes-170309142854.pptx
types-170309142854.pptx
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Construction Management - L1 (1).ppt
Construction Management - L1 (1).pptConstruction Management - L1 (1).ppt
Construction Management - L1 (1).ppt
 
Construction management l1
Construction management   l1Construction management   l1
Construction management l1
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Professional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbalProfessional practices (lec 03) by k.iqbal
Professional practices (lec 03) by k.iqbal
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
SANPPT
SANPPTSANPPT
SANPPT
 
TOPIC1.pdf
TOPIC1.pdfTOPIC1.pdf
TOPIC1.pdf
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
 
The Design Assist Method of Project Delivery
The Design Assist Method of Project DeliveryThe Design Assist Method of Project Delivery
The Design Assist Method of Project Delivery
 
Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014
 

Recently uploaded

Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxStephen Sitton
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESkarthi keyan
 
CS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfCS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfBalamuruganV28
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Communityprachaibot
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSneha Padhiar
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming languageSmritiSharma901052
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdfAkritiPradhan2
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Erbil Polytechnic University
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdfsahilsajad201
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfNainaShrivastava14
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHSneha Padhiar
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsapna80328
 
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmDeepika Walanjkar
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTSneha Padhiar
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfisabel213075
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 

Recently uploaded (20)

Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptx
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
 
CS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfCS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdf
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Community
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming language
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdf
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveying
 
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdf
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 

Classification of contracts

  • 2. Activities in construction project • Engineering – Issues related to process finalization, structural analysis & design, technical issues related to equipment design & selection • Procurement – Procurement of materials , also includes identification of suitable vendors • Construction – This covers construction, installation & test run of a constructed facility before handed to owner
  • 3. Classification • Seperated contracts • Management contracts • Integrated contracts • Discretionary contracts
  • 4. Separated contracts • Lump sum contract • Measurement contract • Item rate • Percentage rate • Cost plus percentage
  • 5. Management contract • Management contract • Construction management contract • Design, management & construction contract • Integrated contract • Design build contract • Turn key contract • Build, operate & transfer contract
  • 6. Discretionary contract • Partnering contract • Joint venture contract
  • 7. Separated • Traditional system & sequential process • Division b/w design & construction responsibility • Design - project briefing, outlining proposal, detail design, etc. • Delay - preparation & approval of drawings, mistakes in design documentation • Lengthy tendering period & suitable for small to medium sized projects where time is not critical
  • 8. • Major drawbacks – Time consuming aspects of development process – Effect of cost uncertainty – Effect of buildability – Fragmentation of organizational interfaces
  • 9. Lump sum contract • Drawings & details provided by client & contractor quotes single lump sum figure which is the total contact value of work • Total sum based on analysis of rates & estimated quantities • Advantage - client know exact amount of funds required to complete structure
  • 10. • Successful lumpsum contract – Quantities of items Involved are calculated at tendering stage itself – Nature of work done must be reasonably measurable – Contractor must be give All the facilities to which he is contractually entitled • Revision of amount in Case of change in design by client
  • 11. Measurable contract • Payment made according to actual work varied out, which is determined by physical measurements
  • 12. Item rate contract • The contractor agrees to carry out a unit quantity of particular work (cm3,m2) for particular sum of money • In this tender document consists of detailed BOQ , where estimated quantity of work for each item involved in particular work are listed along with detailed description • Total contract value - multiply total quantity with quoted item rate and add cost of all items
  • 13. • Some items are not covered in BOQ but essential for completing job, in such cases rates are given on basis of labor, material, equipment etc S.no Item Measurement unit Quantity Rate Amount 1 Cement Kgs 50 280 14000 2 Steel Ton 2 42000 84000
  • 14. Percentage rate contract • Tender document contains scheduled rates for each work in addition to detailed estimate for execution of work • Contractor works out his rates for items i usual manner& arrives at total price which is converted to total percentage by which amount differs • Adopted by government departments & large organizations
  • 15. • Contractor amount -- Z • Z > W , the % rate = (z-w)/w *100 above W • Z < W , the % rate =(w-z)/w*100 below W S.no Item Measure ment unit Quantity Rate Amount 1 Cement Kgs 50 280 14000 2 Steel Ton 2 42000 84000 W 14000+84000
  • 16. Cost plus percentage • Client agrees to pay contractor a certain % of actual cost incurred by contractor while completing a job in addition to cost itself. • Tenderer only quotes his percentage • Usually taken up when time is not available to make estimate and workout details of items involved • Suitable for small jobs.
  • 17. Management contract • Managing contractor is appointed and he deals with number of small contractors • Client deals with only contractor and designer • Contractor provides planning, management & coordination services to client
  • 18. • Responsibilities – Preparing overall construction schedule – Work package schedule – Coordinating with designer – Assistance in subcontractors selection – Coordinating among different subcontractors
  • 19. Construction management contract • Construction manager appointed by client to provide planning, management & coordination • Owner appoints designer & contractors • Role of construction manager is to coordinate among different subcontractors & ensuring timely completion of project within budget cost according to specifications
  • 20. • Some responsibilities are – Advising the designer – Advising on making suitable work package – Assisting in procurement – Managing bidding process
  • 21. Design, management & construction contract • Client appoints single contractor to take care of design & construction • Basic design concepts may be provided by client himself or through an independent agency • After basic concepts client calls for tender and selects appropriate agency for designing , management & construction services
  • 22. Integrated contract • Design- build – In this contractor takes the responsibilities of both design & construction based on basic plans drawn up by the client – This avoids conflict b/w designer & contractor – Often adopted when client has no in-house design with him – This method Reduces the cost , develops the technical power in contractor & reduces disputes
  • 23. The turn-key contract • Responsibilities of all activities are taken up by contracting agency • The owner simply wants to “turn the key” at completion to take over the facility • All activities related to surveying , drawing specifications , design , project planning , construction & test operation are given to one large organisation
  • 24. • They are useful in projects involving combination of civil, electrical, mechanical, chemical & mining engineering • Mostly seen in petrochemical plants & nuclear power stations • STEPS • In a project client first prepares documents regarding requirements of facilities to be constructed • Later he selects the best proposal submitted by multiple bidders