Agile = No Planning = Bull$h!t

103 views

Published on

A common misconception is that Agile teams don’t plan. However, Agile Coach, Reese Schmit says that's bull$h!t. Agile teams plan all the time. The difference is they focus on doing so at the right time and the right fidelity.

How long did it take you to plan your last six-month project before the team started working? Weeks? Months?! In 45 minutes, you can plan that six-month project in 10% of the time it would have taken you to plan it the old way. Plan the Agile way. Using a real project, Reese teaches you how to build a backlog, estimate that backlog, prioritize it, order it based on ROI, capacity plan, and track to completion.

The goal is to not deliver a plan. The goal is to deliver value. Know how to plan at the right time so your teams can get to the delivering value part that really matters.

Published in: Business
  • Be the first to comment

  • Be the first to like this

Agile = No Planning = Bull$h!t

  1. 1. Copyright © 2017 Agile Velocity, LLC.  All Rights Reserved. AGILE VELOCITY PROPRIETARY Agile = No Planning = Bull$h!t Reese Schmit, Agile Coach Agile Velocity
  2. 2. Sponsors Advocates In Kind Supporters
  3. 3. “…I have always found that plans are useless, but planning is indispensable. ” -Dwight D. Eisenhower
  4. 4. The point is not to Deliver the plan @ReeseNDesist
  5. 5. Agile Teams plan product construction in layers
  6. 6. • One item per sticky written with sharpie • 1 major project • 1 minor update • Something in the middle Let’s get your house ready to sell
  7. 7. Story Points Story Points A relative measure of scope of a Story i.e. How big a feature is compared to other features taking into account complexity, uncertainty and risk Velocity The average amount of work the team has Finished over previous Sprints
  8. 8. Let’s Size this Backlog
  9. 9. Let’s Prioritize Now that it’s Sized
  10. 10. by ROI Ordering MoSCoW
  11. 11. Feature Points Cumulative Total Story A 2 2 Story B 5 7 Story C 3 10 Story D 1 11 Story E 3 14 Story F 2 16 Story G 5 21 Story H 2 23 Story I 2 25 Story J 3 28 Story K 5 33 Story L 2 35 Story M 8 43 Story N 2 45 Story O 5 50 Story P 2 52 Story Q 8 60 •Team Historical Velocity = 10 Points/ Sprint •Sprints are 2 weeks each •Release is scheduled for 6 Sprints/ 12 weeks •Backlog has been reduced to 60 points How comfortable would you be committing to the business that the team will deliver the scope of Story A-Q in 12 weeks? Do we commit to our Capacity?
  12. 12. Feature Points Cumulative Total Story A 2 2 Story B 5 7 Story C 3 10 Story D 1 11 Story E 3 14 Story F 2 16 Story G 5 21 Story H 2 23 Story I 2 25 Story J 3 28 Story K 5 33 Story L 2 35 Story M 8 43 Story N 2 45 Story O 5 50 Story P 2 52 Story Q 8 60 While we are still forecasting to deliver 60 points, as far as committing to features we would say: “We are virtually certain we will deliver stories A-K, and Stories L and M have a 50% chance. It is unlikely that Stories N-Q will make it in the release.” 90% Confidence 50% Confidence 10% Confidence Do we commit to our Full Capacity? Fixed Date - (#Sprints x Velocity) / Risk Factors = Confidence Target Fixed Scope - Total Scope x Risk Factor / Velocity = #Sprints Chance Story Points Confidence 10% (6x10) / 1 = 60 50% (6x10) / 1.4 = 43 90% (6x10) / 1.8 = 33 inscopeatrisk
  13. 13. 1.Total up your backlog 2.Determine you are 90% confidant you can complete 3.Determine what you are 10% confidant you can complete 4.Create stickies and place them at those spots next to your backlog Your turn!
  14. 14. After 2 Sprints we completed A-G and achieved our target velocity. New Stories X-Z arrived. Now we would say, “We are virtually certain we will deliver stories H-L incl. X, and Stories Y & Z have a 50% chance. It is unlikely that Stories M-N will make it in the release, and we almost certainly won’t have time for O-Q.” is ongoing RELEASE PLANNING Feature Points Cumulative Total Story A 2 Done Story B 5 Done Story C 3 Done Story D 1 Done Story E 3 Done Story F 2 Done Story G 5 Done Story H 2 2 Story I 2 4 Story J 3 7 Story X 8 15 Story K 5 20 Story L 2 22 Story Y 5 27 Story Z 2 29 Story M 8 37 Story N 2 39 Story O 5 44 Story P 2 46 Story Q 8 54 inscopeatriskoutofscope
  15. 15. BurnUP Release
  16. 16. And just like that we have a Plan

×