Final Project
Subject: Tramway Transportation
using PPP Model in Indian Cities
Present Scenario of Urban India
• From the year 1981 to 2001, the population increase in 6 major
metropolis is 1.9 times whereas motor vehicles increased by 7.75
times.
• Expected increase of vehicles population in this cities is 372 million
in 2035 from 49.1 in at present.
• Fuel consumption in 2035 will be over 6 times that of now.
• Energy demand in transport sector is projected to grow at 5-8% per
annum.
• Increase in Urban population from 30% at present to 40% by 2030
Infrastructure Need : Urban Mass Transportation System
The infrastructure need of the hour in Urban India is an efficient
and reliable inner-city transportation system. And this need arise
due to many factors.
• Increase in travel demand due to Economic prosperity both
personal and commercial.
• Increase in personalized mode and poor urban infrastructure
planning, leading to congestion, traffic and pollution.
• Demand for an efficient alternative public transport system.
• Poor quality of existing urban transport network.
• Economic loss due to non-availability of mass urban transport
systems.
Urban travel Demand Projection
759
1039
2511
0
500
1000
1500
2000
2500
3000
1994 2001 2021
Year
MillionPassenger-Kms
Infrastructure Problems Addressed by Tramway PPP Project
• Tramway Project if implemented will reduce congestion and Traffic.
• Reduction in air and noise pollution.
• More safe and efficient way to travel in a city.
• Will reduce travel time significantly.
• Reduce economic loss due to poor transportation systems.
• Using modern technology like ground level electric field to run the
system make it more easy to implement and operate.
• Efficient energy utilization and conservation.
• Most importantly, Tram Project, if implemented successfully will
provide affordable and quality service to the citizens.
• Also, the construction can be done adapting to the existing nature
of the infrastructure with few alterations unlike big projects like
metro rails.
• High transportation capacity and lower operating costs compared
to bus transport.
• Easy receptiveness and replacement of newer technology to the
transport system is more easy and faster.
Ideal PPP Model for TramRail in India
• The ideal PPP model to be used in this instance would be a Build
Operate & Transfer or BOT model.
• The contract period could any where between 15 to 25 years.
• Transparent bidding process should be put in place to attract
international companies with specific experience in the field of
Tram and railway operations.
• Also take into account existing Tram Projects or proposals in India.
Reasons Private Sector would want to involve
• First and foremost, Tram Transportation project is an good project.
There is an urgent need and demand for such a project.
• India is an untapped market with huge potential and internal
demand.
• Can easily achieve the scale and revenue targets due massive
population and huge reliance on public transport system.
• Massive challenges involved but can be very rewarding for the
private player, if it is able to successfully complete the project.
• Supportive Government policies conducive to infrastructure
projects and business development.
Risk Allocation Framework
Risk Type Sensitivity Primary Risk Bearer
Delays in Land
acquisition
High Government
Financing Risk Medium Private Sector
Planning Medium Private Sector
Regulatory & Approval
Delays
Low Private Sector
Pre-Operative Risks
Risk Type Sensitivity Primary Risk Bearer
Design Risk Medium Private Sector
Construction Risk Medium Private Sector
Change in Scope Risk Low Government
Construction Phase Risks
Risk Type Sensitivity Primary Risk Bearer
Technology Risk Low Private Sector
Operations &
maintenance Risk
Medium Private Sector
Market Risk High Private Sector
Performance Risk High Private Sector
Operational Phase Risk
Risk Type Sensitivity Primary Risk Bearer
Handover Risk Low Private Sector
Interface Risk Medium Private Sector
Force majeure Low Shared
Change in Law Low Private Sector
Other Risks
Conclusion
• Tram Rail Project will be a path breaking project in
modern India and will definitely boost the
development of public sector Transportation
infrastructure.
• This will ensure quality and affordable transportation
service to the citizens at the same time help in
effectively utilizing the urban space as well as
managing the energy utilization.

More Related Content

What's hot

Smart Transportation Case Study by IBM
Smart Transportation Case Study by IBMSmart Transportation Case Study by IBM
Smart Transportation Case Study by IBMIBMTransportation
 
Urban transportation crisis in india
Urban transportation crisis in indiaUrban transportation crisis in india
Urban transportation crisis in indiaSAMITINJAY SHARMA
 
A study of sustainable transportation system in ahmedabad and delhi
A study of sustainable transportation system in ahmedabad and delhiA study of sustainable transportation system in ahmedabad and delhi
A study of sustainable transportation system in ahmedabad and delhiIJARIIT
 
Smart and Connected Transport - A Case Study of Delhi
Smart and Connected Transport - A Case Study of DelhiSmart and Connected Transport - A Case Study of Delhi
Smart and Connected Transport - A Case Study of DelhiJaspal Singh
 
Transportation problem with relevance to indian cities
Transportation problem with relevance to indian citiesTransportation problem with relevance to indian cities
Transportation problem with relevance to indian citiesSailish Cephas
 
National Urban Transport Policy
National Urban Transport PolicyNational Urban Transport Policy
National Urban Transport PolicyPhani Mohan K
 
National urban transport policy
National urban transport policyNational urban transport policy
National urban transport policyShubham Jain
 
8 rajnish glasgow 9th june
8  rajnish glasgow   9th june8  rajnish glasgow   9th june
8 rajnish glasgow 9th juneREPUTE101
 
TRANSIT ORIENTED DEVELOPMENT
TRANSIT ORIENTED DEVELOPMENTTRANSIT ORIENTED DEVELOPMENT
TRANSIT ORIENTED DEVELOPMENTRidam Shah
 
National Urban Transport Policy
National Urban Transport PolicyNational Urban Transport Policy
National Urban Transport PolicyAshu Kedia
 
Transport problems in urban india
Transport problems in urban indiaTransport problems in urban india
Transport problems in urban indiaNeha Budhiraja
 
CONNECTKaro 2015 - Session 4A - Smart Lifestyle and Transit Oriented Development
CONNECTKaro 2015 - Session 4A - Smart Lifestyle and Transit Oriented DevelopmentCONNECTKaro 2015 - Session 4A - Smart Lifestyle and Transit Oriented Development
CONNECTKaro 2015 - Session 4A - Smart Lifestyle and Transit Oriented DevelopmentWRI Ross Center for Sustainable Cities
 
a study of suspentable transportation system in ahmedabad & dehli
a study of suspentable transportation system in ahmedabad & dehlia study of suspentable transportation system in ahmedabad & dehli
a study of suspentable transportation system in ahmedabad & dehliRONAKMODI36
 
PPP in Transport - Mumbai Metro One
PPP in Transport - Mumbai Metro OnePPP in Transport - Mumbai Metro One
PPP in Transport - Mumbai Metro Onekopila
 
Lesson 4 national transport policy
Lesson 4 national transport policyLesson 4 national transport policy
Lesson 4 national transport policyRK Murugan
 
An Integrated Transport Systems Approach to Solving Bangalore's Mobility Prob...
An Integrated Transport Systems Approach to Solving Bangalore's Mobility Prob...An Integrated Transport Systems Approach to Solving Bangalore's Mobility Prob...
An Integrated Transport Systems Approach to Solving Bangalore's Mobility Prob...WRI Ross Center for Sustainable Cities
 

What's hot (20)

Smart Transportation Case Study by IBM
Smart Transportation Case Study by IBMSmart Transportation Case Study by IBM
Smart Transportation Case Study by IBM
 
Urban transportation crisis in india
Urban transportation crisis in indiaUrban transportation crisis in india
Urban transportation crisis in india
 
A study of sustainable transportation system in ahmedabad and delhi
A study of sustainable transportation system in ahmedabad and delhiA study of sustainable transportation system in ahmedabad and delhi
A study of sustainable transportation system in ahmedabad and delhi
 
Smart and Connected Transport - A Case Study of Delhi
Smart and Connected Transport - A Case Study of DelhiSmart and Connected Transport - A Case Study of Delhi
Smart and Connected Transport - A Case Study of Delhi
 
Transportation problem with relevance to indian cities
Transportation problem with relevance to indian citiesTransportation problem with relevance to indian cities
Transportation problem with relevance to indian cities
 
Bus Rapid Transit (BRT)
Bus Rapid Transit (BRT)Bus Rapid Transit (BRT)
Bus Rapid Transit (BRT)
 
National Urban Transport Policy
National Urban Transport PolicyNational Urban Transport Policy
National Urban Transport Policy
 
Mobility and City Streets: Use of Public Buses to Improve Safety
Mobility and City Streets: Use of Public Buses to Improve SafetyMobility and City Streets: Use of Public Buses to Improve Safety
Mobility and City Streets: Use of Public Buses to Improve Safety
 
National urban transport policy
National urban transport policyNational urban transport policy
National urban transport policy
 
Mobility and City Streets: Commut
Mobility and City Streets: CommutMobility and City Streets: Commut
Mobility and City Streets: Commut
 
8 rajnish glasgow 9th june
8  rajnish glasgow   9th june8  rajnish glasgow   9th june
8 rajnish glasgow 9th june
 
TRANSIT ORIENTED DEVELOPMENT
TRANSIT ORIENTED DEVELOPMENTTRANSIT ORIENTED DEVELOPMENT
TRANSIT ORIENTED DEVELOPMENT
 
National Urban Transport Policy
National Urban Transport PolicyNational Urban Transport Policy
National Urban Transport Policy
 
Transport problems in urban india
Transport problems in urban indiaTransport problems in urban india
Transport problems in urban india
 
CONNECTKaro 2015 - Session 4A - Smart Lifestyle and Transit Oriented Development
CONNECTKaro 2015 - Session 4A - Smart Lifestyle and Transit Oriented DevelopmentCONNECTKaro 2015 - Session 4A - Smart Lifestyle and Transit Oriented Development
CONNECTKaro 2015 - Session 4A - Smart Lifestyle and Transit Oriented Development
 
a study of suspentable transportation system in ahmedabad & dehli
a study of suspentable transportation system in ahmedabad & dehlia study of suspentable transportation system in ahmedabad & dehli
a study of suspentable transportation system in ahmedabad & dehli
 
PPP in Transport - Mumbai Metro One
PPP in Transport - Mumbai Metro OnePPP in Transport - Mumbai Metro One
PPP in Transport - Mumbai Metro One
 
Lesson 4 national transport policy
Lesson 4 national transport policyLesson 4 national transport policy
Lesson 4 national transport policy
 
An Integrated Transport Systems Approach to Solving Bangalore's Mobility Prob...
An Integrated Transport Systems Approach to Solving Bangalore's Mobility Prob...An Integrated Transport Systems Approach to Solving Bangalore's Mobility Prob...
An Integrated Transport Systems Approach to Solving Bangalore's Mobility Prob...
 
India Smart Cities and Urban Transport
India Smart Cities and Urban TransportIndia Smart Cities and Urban Transport
India Smart Cities and Urban Transport
 

Viewers also liked

Elevators -Electrical and Safety Professional
Elevators -Electrical and Safety ProfessionalElevators -Electrical and Safety Professional
Elevators -Electrical and Safety ProfessionalNoel Roman
 
Pre-Apprenticeship for Transportation Infrastructure – Project STRIPE
Pre-Apprenticeship for Transportation Infrastructure – Project STRIPEPre-Apprenticeship for Transportation Infrastructure – Project STRIPE
Pre-Apprenticeship for Transportation Infrastructure – Project STRIPEccpc
 
Hyderabad Bicycle District_PPP_asandwhen 2009
Hyderabad Bicycle District_PPP_asandwhen 2009Hyderabad Bicycle District_PPP_asandwhen 2009
Hyderabad Bicycle District_PPP_asandwhen 2009asandwhen
 
Transportation Infrastructure Investment: Macroeconomic and Industry Contribu...
Transportation Infrastructure Investment: Macroeconomic and Industry Contribu...Transportation Infrastructure Investment: Macroeconomic and Industry Contribu...
Transportation Infrastructure Investment: Macroeconomic and Industry Contribu...artba
 
Peter 5th Year Project Presentation
Peter 5th Year Project PresentationPeter 5th Year Project Presentation
Peter 5th Year Project PresentationPeter Murigi
 
PPP Project: Notes of Senegal's PPP strategy for its rural electrification pr...
PPP Project: Notes of Senegal's PPP strategy for its rural electrification pr...PPP Project: Notes of Senegal's PPP strategy for its rural electrification pr...
PPP Project: Notes of Senegal's PPP strategy for its rural electrification pr...Alvaro HIDALGO
 
Ppp for public bicycle sharing and parking management in kharghar navi mumbai...
Ppp for public bicycle sharing and parking management in kharghar navi mumbai...Ppp for public bicycle sharing and parking management in kharghar navi mumbai...
Ppp for public bicycle sharing and parking management in kharghar navi mumbai...Avinash Shabade
 
Vision Enables Intelligent Robotic Transportation System
Vision Enables Intelligent Robotic Transportation SystemVision Enables Intelligent Robotic Transportation System
Vision Enables Intelligent Robotic Transportation Systemshreykhanna
 
Karnataka, India : Antecedentes de los proyectos PPP (marzo 2008)
Karnataka, India : Antecedentes de los proyectos PPP (marzo 2008)Karnataka, India : Antecedentes de los proyectos PPP (marzo 2008)
Karnataka, India : Antecedentes de los proyectos PPP (marzo 2008)DBTGrupoIndia
 
Solid Waste Management for Philippine Cities and Municipalities
Solid Waste Management for Philippine Cities and MunicipalitiesSolid Waste Management for Philippine Cities and Municipalities
Solid Waste Management for Philippine Cities and MunicipalitiesEnergySavings
 
Introduction to the Final Year Project
Introduction to the Final Year ProjectIntroduction to the Final Year Project
Introduction to the Final Year ProjectGihan Wikramanayake
 
THE STUDY OF EFFECTIVENESS OF MUNICIPAL SOLID WASTE MANAGEMENT SYSTEM AT RESI...
THE STUDY OF EFFECTIVENESS OF MUNICIPAL SOLID WASTE MANAGEMENT SYSTEM AT RESI...THE STUDY OF EFFECTIVENESS OF MUNICIPAL SOLID WASTE MANAGEMENT SYSTEM AT RESI...
THE STUDY OF EFFECTIVENESS OF MUNICIPAL SOLID WASTE MANAGEMENT SYSTEM AT RESI...Firdaurs Abdullah
 
Career Counseling about Armed Forces of pakistan
Career Counseling about Armed Forces of pakistanCareer Counseling about Armed Forces of pakistan
Career Counseling about Armed Forces of pakistanSHER MUHAMMAD
 
BRT System in Delhi
BRT System in DelhiBRT System in Delhi
BRT System in DelhiJaspal Singh
 
Vilnius street lighting PPP project presentation by peritus 2012.03
Vilnius street lighting PPP project presentation by peritus 2012.03Vilnius street lighting PPP project presentation by peritus 2012.03
Vilnius street lighting PPP project presentation by peritus 2012.03Andrius Šiaudinis
 
Presentation Public Private Partnership (PPP)
Presentation Public Private Partnership (PPP) Presentation Public Private Partnership (PPP)
Presentation Public Private Partnership (PPP) Khalid Rasulli
 

Viewers also liked (20)

Elevators -Electrical and Safety Professional
Elevators -Electrical and Safety ProfessionalElevators -Electrical and Safety Professional
Elevators -Electrical and Safety Professional
 
Pre-Apprenticeship for Transportation Infrastructure – Project STRIPE
Pre-Apprenticeship for Transportation Infrastructure – Project STRIPEPre-Apprenticeship for Transportation Infrastructure – Project STRIPE
Pre-Apprenticeship for Transportation Infrastructure – Project STRIPE
 
Hyderabad Bicycle District_PPP_asandwhen 2009
Hyderabad Bicycle District_PPP_asandwhen 2009Hyderabad Bicycle District_PPP_asandwhen 2009
Hyderabad Bicycle District_PPP_asandwhen 2009
 
Presentation water use civil final
Presentation  water use civil finalPresentation  water use civil final
Presentation water use civil final
 
Transportation Infrastructure Investment: Macroeconomic and Industry Contribu...
Transportation Infrastructure Investment: Macroeconomic and Industry Contribu...Transportation Infrastructure Investment: Macroeconomic and Industry Contribu...
Transportation Infrastructure Investment: Macroeconomic and Industry Contribu...
 
Peter 5th Year Project Presentation
Peter 5th Year Project PresentationPeter 5th Year Project Presentation
Peter 5th Year Project Presentation
 
PPP Project: Notes of Senegal's PPP strategy for its rural electrification pr...
PPP Project: Notes of Senegal's PPP strategy for its rural electrification pr...PPP Project: Notes of Senegal's PPP strategy for its rural electrification pr...
PPP Project: Notes of Senegal's PPP strategy for its rural electrification pr...
 
Ppp for public bicycle sharing and parking management in kharghar navi mumbai...
Ppp for public bicycle sharing and parking management in kharghar navi mumbai...Ppp for public bicycle sharing and parking management in kharghar navi mumbai...
Ppp for public bicycle sharing and parking management in kharghar navi mumbai...
 
Water in indian infrastructure
Water in indian infrastructureWater in indian infrastructure
Water in indian infrastructure
 
Vision Enables Intelligent Robotic Transportation System
Vision Enables Intelligent Robotic Transportation SystemVision Enables Intelligent Robotic Transportation System
Vision Enables Intelligent Robotic Transportation System
 
Karnataka, India : Antecedentes de los proyectos PPP (marzo 2008)
Karnataka, India : Antecedentes de los proyectos PPP (marzo 2008)Karnataka, India : Antecedentes de los proyectos PPP (marzo 2008)
Karnataka, India : Antecedentes de los proyectos PPP (marzo 2008)
 
Solid Waste Management for Philippine Cities and Municipalities
Solid Waste Management for Philippine Cities and MunicipalitiesSolid Waste Management for Philippine Cities and Municipalities
Solid Waste Management for Philippine Cities and Municipalities
 
Introduction to the Final Year Project
Introduction to the Final Year ProjectIntroduction to the Final Year Project
Introduction to the Final Year Project
 
5th Semester Civil Engineering (2013-December) Question Papers
5th Semester Civil Engineering (2013-December) Question Papers5th Semester Civil Engineering (2013-December) Question Papers
5th Semester Civil Engineering (2013-December) Question Papers
 
THE STUDY OF EFFECTIVENESS OF MUNICIPAL SOLID WASTE MANAGEMENT SYSTEM AT RESI...
THE STUDY OF EFFECTIVENESS OF MUNICIPAL SOLID WASTE MANAGEMENT SYSTEM AT RESI...THE STUDY OF EFFECTIVENESS OF MUNICIPAL SOLID WASTE MANAGEMENT SYSTEM AT RESI...
THE STUDY OF EFFECTIVENESS OF MUNICIPAL SOLID WASTE MANAGEMENT SYSTEM AT RESI...
 
Career Counseling about Armed Forces of pakistan
Career Counseling about Armed Forces of pakistanCareer Counseling about Armed Forces of pakistan
Career Counseling about Armed Forces of pakistan
 
BRT System in Delhi
BRT System in DelhiBRT System in Delhi
BRT System in Delhi
 
Vilnius street lighting PPP project presentation by peritus 2012.03
Vilnius street lighting PPP project presentation by peritus 2012.03Vilnius street lighting PPP project presentation by peritus 2012.03
Vilnius street lighting PPP project presentation by peritus 2012.03
 
Academic performance correlation with the qualification of Final Projects in ...
Academic performance correlation with the qualification of Final Projects in ...Academic performance correlation with the qualification of Final Projects in ...
Academic performance correlation with the qualification of Final Projects in ...
 
Presentation Public Private Partnership (PPP)
Presentation Public Private Partnership (PPP) Presentation Public Private Partnership (PPP)
Presentation Public Private Partnership (PPP)
 

Similar to Ppp final project

THE GREEN TRANSPORT final
THE GREEN TRANSPORT finalTHE GREEN TRANSPORT final
THE GREEN TRANSPORT finalDeepanshu Garg
 
Future of Integrated Transport Systems: Best Sustainable Practices Around The...
Future of Integrated Transport Systems: Best Sustainable Practices Around The...Future of Integrated Transport Systems: Best Sustainable Practices Around The...
Future of Integrated Transport Systems: Best Sustainable Practices Around The...Minakshi Patel
 
Session 7b: Part I- Decarbonising urban transport - WB
Session 7b: Part I- Decarbonising urban transport - WBSession 7b: Part I- Decarbonising urban transport - WB
Session 7b: Part I- Decarbonising urban transport - WBOECD Environment
 
First – Last Mile_MBPJ_2015
First – Last Mile_MBPJ_2015First – Last Mile_MBPJ_2015
First – Last Mile_MBPJ_2015Norma Nun
 
Possibilities For Bus Lane System
Possibilities For Bus Lane SystemPossibilities For Bus Lane System
Possibilities For Bus Lane SystemNaveen Chandra
 
Mumbai Metro Phase 1
Mumbai Metro Phase 1Mumbai Metro Phase 1
Mumbai Metro Phase 1OmkarRasal
 
Smart parking presentation to fin4dev cousera
Smart parking presentation to fin4dev couseraSmart parking presentation to fin4dev cousera
Smart parking presentation to fin4dev couseraiharak
 
Smart parking presentation to fin4dev cousera
Smart parking presentation to fin4dev couseraSmart parking presentation to fin4dev cousera
Smart parking presentation to fin4dev couseraiharak
 
Bus Karo: Innovative financing mechanisms
Bus Karo: Innovative financing mechanisms Bus Karo: Innovative financing mechanisms
Bus Karo: Innovative financing mechanisms WRI India
 
Effective learning from delhi brts –a case study of pune brts
Effective learning from delhi brts –a case study of pune brtsEffective learning from delhi brts –a case study of pune brts
Effective learning from delhi brts –a case study of pune brtseSAT Journals
 
Business model 15.8.17
Business model 15.8.17Business model 15.8.17
Business model 15.8.17sunnytenac
 
Tarun_PPT[1].pptx
Tarun_PPT[1].pptxTarun_PPT[1].pptx
Tarun_PPT[1].pptxXyuJjdjjd
 
High Speed Rail- Need, Challenges, Key Issues and Options: Indian Perspective
High Speed Rail- Need, Challenges, Key Issues and Options: Indian PerspectiveHigh Speed Rail- Need, Challenges, Key Issues and Options: Indian Perspective
High Speed Rail- Need, Challenges, Key Issues and Options: Indian PerspectiveRajesh Prasad
 
TOD - Transit Oriented Development
TOD - Transit Oriented DevelopmentTOD - Transit Oriented Development
TOD - Transit Oriented DevelopmentShruthi Kshirasagar
 
Possibilities for Bus Lane System
Possibilities for Bus Lane SystemPossibilities for Bus Lane System
Possibilities for Bus Lane Systemguestf2886b
 
impact of MRTS on Landuse in Patna
impact of MRTS on Landuse in Patnaimpact of MRTS on Landuse in Patna
impact of MRTS on Landuse in PatnaArchit Nishant
 

Similar to Ppp final project (20)

monorail system implication in Sri Lanka
monorail system implication in Sri Lankamonorail system implication in Sri Lanka
monorail system implication in Sri Lanka
 
THE GREEN TRANSPORT final
THE GREEN TRANSPORT finalTHE GREEN TRANSPORT final
THE GREEN TRANSPORT final
 
Future of Integrated Transport Systems: Best Sustainable Practices Around The...
Future of Integrated Transport Systems: Best Sustainable Practices Around The...Future of Integrated Transport Systems: Best Sustainable Practices Around The...
Future of Integrated Transport Systems: Best Sustainable Practices Around The...
 
Metro Rail and the City
Metro Rail and the CityMetro Rail and the City
Metro Rail and the City
 
Session 7b: Part I- Decarbonising urban transport - WB
Session 7b: Part I- Decarbonising urban transport - WBSession 7b: Part I- Decarbonising urban transport - WB
Session 7b: Part I- Decarbonising urban transport - WB
 
First – Last Mile_MBPJ_2015
First – Last Mile_MBPJ_2015First – Last Mile_MBPJ_2015
First – Last Mile_MBPJ_2015
 
Possibilities For Bus Lane System
Possibilities For Bus Lane SystemPossibilities For Bus Lane System
Possibilities For Bus Lane System
 
Mumbai Metro Phase 1
Mumbai Metro Phase 1Mumbai Metro Phase 1
Mumbai Metro Phase 1
 
Smart parking presentation to fin4dev cousera
Smart parking presentation to fin4dev couseraSmart parking presentation to fin4dev cousera
Smart parking presentation to fin4dev cousera
 
Smart parking presentation to fin4dev cousera
Smart parking presentation to fin4dev couseraSmart parking presentation to fin4dev cousera
Smart parking presentation to fin4dev cousera
 
Bus Karo: Innovative financing mechanisms
Bus Karo: Innovative financing mechanisms Bus Karo: Innovative financing mechanisms
Bus Karo: Innovative financing mechanisms
 
Effective learning from delhi brts –a case study of pune brts
Effective learning from delhi brts –a case study of pune brtsEffective learning from delhi brts –a case study of pune brts
Effective learning from delhi brts –a case study of pune brts
 
Modern Roads
Modern RoadsModern Roads
Modern Roads
 
Business model 15.8.17
Business model 15.8.17Business model 15.8.17
Business model 15.8.17
 
Tarun_PPT[1].pptx
Tarun_PPT[1].pptxTarun_PPT[1].pptx
Tarun_PPT[1].pptx
 
High Speed Rail- Need, Challenges, Key Issues and Options: Indian Perspective
High Speed Rail- Need, Challenges, Key Issues and Options: Indian PerspectiveHigh Speed Rail- Need, Challenges, Key Issues and Options: Indian Perspective
High Speed Rail- Need, Challenges, Key Issues and Options: Indian Perspective
 
Transport Thursday Niel van Oort
Transport Thursday Niel van OortTransport Thursday Niel van Oort
Transport Thursday Niel van Oort
 
TOD - Transit Oriented Development
TOD - Transit Oriented DevelopmentTOD - Transit Oriented Development
TOD - Transit Oriented Development
 
Possibilities for Bus Lane System
Possibilities for Bus Lane SystemPossibilities for Bus Lane System
Possibilities for Bus Lane System
 
impact of MRTS on Landuse in Patna
impact of MRTS on Landuse in Patnaimpact of MRTS on Landuse in Patna
impact of MRTS on Landuse in Patna
 

Recently uploaded

fca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdffca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdfHenry Tapper
 
Governor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraintGovernor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraintSuomen Pankki
 
Vp Girls near me Delhi Call Now or WhatsApp
Vp Girls near me Delhi Call Now or WhatsAppVp Girls near me Delhi Call Now or WhatsApp
Vp Girls near me Delhi Call Now or WhatsAppmiss dipika
 
SBP-Market-Operations and market managment
SBP-Market-Operations and market managmentSBP-Market-Operations and market managment
SBP-Market-Operations and market managmentfactical
 
(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一
(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一
(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一S SDS
 
PMFBY , Pradhan Mantri Fasal bima yojna
PMFBY , Pradhan Mantri  Fasal bima yojnaPMFBY , Pradhan Mantri  Fasal bima yojna
PMFBY , Pradhan Mantri Fasal bima yojnaDharmendra Kumar
 
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...yordanosyohannes2
 
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...Amil baba
 
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACTGOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACTharshitverma1762
 
原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证
原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证
原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证rjrjkk
 
Quantitative Analysis of Retail Sector Companies
Quantitative Analysis of Retail Sector CompaniesQuantitative Analysis of Retail Sector Companies
Quantitative Analysis of Retail Sector Companiesprashantbhati354
 
NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...
NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...
NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...Amil baba
 
Tenets of Physiocracy History of Economic
Tenets of Physiocracy History of EconomicTenets of Physiocracy History of Economic
Tenets of Physiocracy History of Economiccinemoviesu
 
magnetic-pensions-a-new-blueprint-for-the-dc-landscape.pdf
magnetic-pensions-a-new-blueprint-for-the-dc-landscape.pdfmagnetic-pensions-a-new-blueprint-for-the-dc-landscape.pdf
magnetic-pensions-a-new-blueprint-for-the-dc-landscape.pdfHenry Tapper
 
NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...
NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...
NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...Amil Baba Dawood bangali
 
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证jdkhjh
 
Stock Market Brief Deck FOR 4/17 video.pdf
Stock Market Brief Deck FOR 4/17 video.pdfStock Market Brief Deck FOR 4/17 video.pdf
Stock Market Brief Deck FOR 4/17 video.pdfMichael Silva
 
2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGeckoCoinGecko
 
The Triple Threat | Article on Global Resession | Harsh Kumar
The Triple Threat | Article on Global Resession | Harsh KumarThe Triple Threat | Article on Global Resession | Harsh Kumar
The Triple Threat | Article on Global Resession | Harsh KumarHarsh Kumar
 

Recently uploaded (20)

fca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdffca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdf
 
Governor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraintGovernor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraint
 
Vp Girls near me Delhi Call Now or WhatsApp
Vp Girls near me Delhi Call Now or WhatsAppVp Girls near me Delhi Call Now or WhatsApp
Vp Girls near me Delhi Call Now or WhatsApp
 
SBP-Market-Operations and market managment
SBP-Market-Operations and market managmentSBP-Market-Operations and market managment
SBP-Market-Operations and market managment
 
(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一
(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一
(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一
 
PMFBY , Pradhan Mantri Fasal bima yojna
PMFBY , Pradhan Mantri  Fasal bima yojnaPMFBY , Pradhan Mantri  Fasal bima yojna
PMFBY , Pradhan Mantri Fasal bima yojna
 
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
AfRESFullPaper22018EmpiricalPerformanceofRealEstateInvestmentTrustsandShareho...
 
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
NO1 WorldWide Genuine vashikaran specialist Vashikaran baba near Lahore Vashi...
 
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACTGOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
 
原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证
原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证
原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证
 
Quantitative Analysis of Retail Sector Companies
Quantitative Analysis of Retail Sector CompaniesQuantitative Analysis of Retail Sector Companies
Quantitative Analysis of Retail Sector Companies
 
NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...
NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...
NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...
 
Tenets of Physiocracy History of Economic
Tenets of Physiocracy History of EconomicTenets of Physiocracy History of Economic
Tenets of Physiocracy History of Economic
 
Monthly Economic Monitoring of Ukraine No 231, April 2024
Monthly Economic Monitoring of Ukraine No 231, April 2024Monthly Economic Monitoring of Ukraine No 231, April 2024
Monthly Economic Monitoring of Ukraine No 231, April 2024
 
magnetic-pensions-a-new-blueprint-for-the-dc-landscape.pdf
magnetic-pensions-a-new-blueprint-for-the-dc-landscape.pdfmagnetic-pensions-a-new-blueprint-for-the-dc-landscape.pdf
magnetic-pensions-a-new-blueprint-for-the-dc-landscape.pdf
 
NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...
NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...
NO1 WorldWide online istikhara for love marriage vashikaran specialist love p...
 
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
 
Stock Market Brief Deck FOR 4/17 video.pdf
Stock Market Brief Deck FOR 4/17 video.pdfStock Market Brief Deck FOR 4/17 video.pdf
Stock Market Brief Deck FOR 4/17 video.pdf
 
2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko
 
The Triple Threat | Article on Global Resession | Harsh Kumar
The Triple Threat | Article on Global Resession | Harsh KumarThe Triple Threat | Article on Global Resession | Harsh Kumar
The Triple Threat | Article on Global Resession | Harsh Kumar
 

Ppp final project

  • 1. Final Project Subject: Tramway Transportation using PPP Model in Indian Cities
  • 2. Present Scenario of Urban India • From the year 1981 to 2001, the population increase in 6 major metropolis is 1.9 times whereas motor vehicles increased by 7.75 times. • Expected increase of vehicles population in this cities is 372 million in 2035 from 49.1 in at present. • Fuel consumption in 2035 will be over 6 times that of now. • Energy demand in transport sector is projected to grow at 5-8% per annum. • Increase in Urban population from 30% at present to 40% by 2030
  • 3.
  • 4.
  • 5. Infrastructure Need : Urban Mass Transportation System The infrastructure need of the hour in Urban India is an efficient and reliable inner-city transportation system. And this need arise due to many factors. • Increase in travel demand due to Economic prosperity both personal and commercial. • Increase in personalized mode and poor urban infrastructure planning, leading to congestion, traffic and pollution. • Demand for an efficient alternative public transport system. • Poor quality of existing urban transport network. • Economic loss due to non-availability of mass urban transport systems.
  • 6. Urban travel Demand Projection 759 1039 2511 0 500 1000 1500 2000 2500 3000 1994 2001 2021 Year MillionPassenger-Kms
  • 7. Infrastructure Problems Addressed by Tramway PPP Project • Tramway Project if implemented will reduce congestion and Traffic. • Reduction in air and noise pollution. • More safe and efficient way to travel in a city. • Will reduce travel time significantly. • Reduce economic loss due to poor transportation systems. • Using modern technology like ground level electric field to run the system make it more easy to implement and operate.
  • 8. • Efficient energy utilization and conservation. • Most importantly, Tram Project, if implemented successfully will provide affordable and quality service to the citizens. • Also, the construction can be done adapting to the existing nature of the infrastructure with few alterations unlike big projects like metro rails. • High transportation capacity and lower operating costs compared to bus transport. • Easy receptiveness and replacement of newer technology to the transport system is more easy and faster.
  • 9. Ideal PPP Model for TramRail in India • The ideal PPP model to be used in this instance would be a Build Operate & Transfer or BOT model. • The contract period could any where between 15 to 25 years. • Transparent bidding process should be put in place to attract international companies with specific experience in the field of Tram and railway operations. • Also take into account existing Tram Projects or proposals in India.
  • 10. Reasons Private Sector would want to involve • First and foremost, Tram Transportation project is an good project. There is an urgent need and demand for such a project. • India is an untapped market with huge potential and internal demand. • Can easily achieve the scale and revenue targets due massive population and huge reliance on public transport system. • Massive challenges involved but can be very rewarding for the private player, if it is able to successfully complete the project. • Supportive Government policies conducive to infrastructure projects and business development.
  • 11. Risk Allocation Framework Risk Type Sensitivity Primary Risk Bearer Delays in Land acquisition High Government Financing Risk Medium Private Sector Planning Medium Private Sector Regulatory & Approval Delays Low Private Sector Pre-Operative Risks
  • 12. Risk Type Sensitivity Primary Risk Bearer Design Risk Medium Private Sector Construction Risk Medium Private Sector Change in Scope Risk Low Government Construction Phase Risks
  • 13. Risk Type Sensitivity Primary Risk Bearer Technology Risk Low Private Sector Operations & maintenance Risk Medium Private Sector Market Risk High Private Sector Performance Risk High Private Sector Operational Phase Risk
  • 14. Risk Type Sensitivity Primary Risk Bearer Handover Risk Low Private Sector Interface Risk Medium Private Sector Force majeure Low Shared Change in Law Low Private Sector Other Risks
  • 15. Conclusion • Tram Rail Project will be a path breaking project in modern India and will definitely boost the development of public sector Transportation infrastructure. • This will ensure quality and affordable transportation service to the citizens at the same time help in effectively utilizing the urban space as well as managing the energy utilization.