Ceca   adjudication  the process - january 2013
Upcoming SlideShare
Loading in...5
×
 

Ceca adjudication the process - january 2013

on

  • 218 views

 

Statistics

Views

Total Views
218
Views on SlideShare
218
Embed Views
0

Actions

Likes
0
Downloads
4
Comments
0

0 Embeds 0

No embeds

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

Ceca   adjudication  the process - january 2013 Ceca adjudication the process - january 2013 Presentation Transcript

  • Adjudication: The Process clear pr acti cal advi ce Stephen McLellan January 2013
  • Stephen McLellan Solicitor Construction and Engineering Watson Burton LLP Telephone: 0845 901 0936 Email: stephen.mclellan@watsonburton.com
  • Adjudication 1. Background to adjudication 2. The process 2.1 starting the process 2.2 submissions 2.3 decision / enforcement 3. The future of adjudication
  • 1 Background to Adjudication What is adjudication? • 3rd party adjudicator • 28 day process (up to 42 days) • Interim decision • Costs not recoverable
  • 1 Background to Adjudication - Housing Grants, Construction and Regeneration Act 1996 “The intention of Parliament in enacting the Act was plain. It was to introduce a speedy mechanism for settling disputes in construction contracts on a provisional interim basis, and requiring the decision of adjudicators to be enforced pending the final determination of disputes by arbitration, litigation or agreement….”
  • 1 Background to Adjudication “…The timetable for adjudications is very tight…many would say unreasonably tight, and likely to result in injustice. Parliament must be taken to have been aware of this. So far as procedure is concerned, the adjudicator is given a fairly free hand”. (Macob Civil Engineering Ltd -v- Morrison Construction Ltd [1999])
  • 1 Background to Adjudication - Local Democracy, Economic Development and Construction Act 2009 • came into force October 2011 • requirement for construction contracts to be “in writing” removed • parties cannot agree who will pay the costs of the process before the Notice of Adjudication is issued
  • 2 The Process - When can you use adjudication? • • there must be a dispute qualifying contract – the following are excluded: – sale of goods contracts – extraction of oil, gas, materials – work associated with nuclear processing, power generation, water or effluent treatment, production and processing of chemicals etc. – contracts with residential occupants
  • 2 2.1 The Process Starting the process • the Notice of Adjudication – identifies intention to adjudicate – defines the adjudicator’s jurisdiction • can be deliberately narrow or wide
  • 2 2.1 The Process Starting the process • appointment of an adjudicator – named in contract? – agreed between parties – nomination 7 days after Notice of Adjudication
  • 2 2.2 The Process Submissions - Referral Notice • re-statement of the dispute • complete explanation of the claim: - identify the parties - contract documents and relevant terms - what obligations have been breached? • relevant supporting documentation: - witness statements?
  • 2 2.2 The Process Submissions - Referral Notice (continued…) • points of law • request for a meeting or hearing?
  • 2 2.2 The Process Submissions - Response • be prepared • understand the extent of the dispute - is clarification required? • are there any jurisdictional issues? • extension of time? 7 days from the Referral Notice
  • 2 2.2 The Process Submissions - written questions - meeting - further submissions
  • 2 2.3 The Process Decision / enforcement - Decision • reasons to be provided? • 28 to 42 days from referral • effect of decision • payment • other, e.g. construing contract • temporarily binding
  • 2 2.3 The Process Decision / enforcement - Enforcement • binding - must comply, cannot appeal - if a party disagrees with a decision, can challenge by litigation / arbitration • courts will enforce the decision, in the first instance • shortened process – summary judgement
  • 3 The Future for Adjudication • verbal contracts – disputes over oral terms? • costs – “Tolent” clauses banned
  • Further information - Useful websites www.rics.org/drs www.adjudication.org www.adjudication.co.uk www.watsonburton.com
  • Adjudication: The Process clear pr acti cal advi ce Stephen McLellan January 2013