Resource Levelling - PMBOK - Example

388 views
285 views

Published on

An example describing resource levelling according to PMBOK

Published in: Education, Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
388
On SlideShare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
17
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Resource Levelling - PMBOK - Example

  1. 1. Waleed Liaqat 122 SEC A Construction Project Management Assignment # 3 Submitted to: Lec. Bilal Zafar From:
  2. 2. Activity Duration ES EF LS LF TF FF A 2 0 2 0 2 0 0 B 4 2 6 4 8 2 0 C 6 2 8 2 8 0 0 D 9 2 11 6 15 4 4 E 5 6 11 10 15 4 4 F 7 8 15 8 15 0 0 G 3 15 18 15 18 0 nil 18 Total Duration of project (Days) B 4 D 9 C 6 F 7 E 5 G 3 A 2 PS Critical
  3. 3. Activity A 3 3 B 2 2 2 2 C 4 4 4 4 4 4 D 3 3 3 3 3 3 3 3 3 E 4 4 4 4 4 F 2 2 2 2 2 2 G 4 4 4 Day 1 2 3 4 5 6 7 8 9 10 11 13 14 15 16 17 18 Total Laborers 3 3 9 9 9 9 11 11 9 9 9 2 2 2 4 4 4 KEY OveruseFloat Non critical Activity Critical Activity 0 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 1 3 1 4 15 1 6 1 7 18 LABORERS DAYS BEFORE LEVELLING
  4. 4. Activity A 3 3 B X X 2 2 2 2 C 4 4 4 4 4 4 D 3 3 3 3 3 3 3 3 3 E X X 4 4 4 4 F 2 2 2 2 2 2 G 4 4 4 Day 1 2 3 4 5 6 7 8 9 10 11 13 14 15 16 17 18 Total Laborers 3 3 7 7 9 9 9 9 9 9 9 6 2 2 4 4 4 0 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 LABORERS DAYS INTERMEDIATE LEVELLING
  5. 5. Activity A 3 3 B X X 2 2 2 2 C 4 4 4 4 4 4 D D D D D 3 3 3 3 3 3 3 3 E X X 4 4 4 4 F 2 2 2 2 2 2 G 4 4 4 Day 1 2 3 4 5 6 7 8 9 10 11 13 14 15 16 17 18 Total Laborers 3 3 4 4 6 6 9 9 9 9 9 9 5 5 4 4 4 Float X ASSIGNMENT FIX D DISTRIBUTIO N FIX KEY Critical Activity Non critical Activity 0 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 LABORERS DAYS AFTER COMPLETE LEVELLING

×